Integrating RFID and BIM technologies for mitigating risks and improving schedule performance of prefabricated house construction

Open access
Li, Clyde Zhengdao, Zhong, Ray Y., Xue, Fan, Xu, Gangyan, Chen, Ke, Huang, George Guoquan, Shen, Geoffrey Qiping·2017·Journal of Cleaner Production

Abstract

Abstract With its generally recognized benefits of clean and safe working environment and good quality, prefabricated house construction (PHC) as a solution is gaining momentum in the face of various housing challenges in Hong Kong's construction industry. Although prefabrication has its own benefits, its fundamental disadvantages of fragmentation, discontinuity, poor interoperability, and scarce real-time information availability have imposed significant adverse influence on the schedule performance of prefabricated house construction. As a result, despite the promise of the government to provide sufficient houses and harmonious housing, schedule delay problems still frequently beset the industry of PHC. To help address schedule delay problems encountered in the construction of prefabrication housing, this research first identified and analysed critical schedule risk factors that may have significant influence on the schedule performance of PHC. Based on the identified schedule risks, the challenges and corresponding required functions for enhancing schedule performance are determined. Then, a radio frequency identification device (RFID)-enabled BIM platform that integrates various involved stakeholders, information/data flow, offshore prefabrication procedures, and state-of-the-art construction technologies, is developed to handle the critical schedule factors. Smart construction objects and RFID-enabled smart gateway work collaboratively to ease operations within the three echelons of prefabrication manufacturing, logistics and on-site assembly construction, while real-time captured data are used to form a closed-loop visibility and traceability mode in which different end users can supervise the construction statuses, progresses in real time. The developed platform can provide various services, tools and mechanisms to different stakeholders, improve the success of daily operations and decision makings throughout PHC management, such that critical schedule risks can be mitigated and the schedule performance of PHC can be enhanced to ensure timely project delivery.

Overview

The claims and statistics of this paper haven’t been checked yet.

Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.

A few free checks a day · papers already verified open instantly · results are public

Integrity signals

Registry

Crossref · 10.1016/j.jclepro.2017.07.156

Cites

Statistics

Verification

Claims the paper makes

The claims and statistics of this paper haven’t been checked yet.

Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.

A few free checks a day · papers already verified open instantly · results are public

Self-check

Percentages, sums and reported differences re-computed from the paper’s own numbers.

The self-check needs the paper’s full text.

Citations

Cited by

See all 272

Metadata

Authors
Li, C. Z., Zhong, R. Y., Xue, F., Xu, G., Chen, K., Huang, G. G., & Shen, G. Q.
Venue
Journal of Cleaner Production
Publisher
Elsevier BV
Published
2017-11
Volume
165
Pages
1048-1062
ISSN
0959-6526 (ISSN-L)
OpenAlex
W2737493980
Cited by
272
References
0
FWCI
18.83
Type
journal article
Language
en
Open access
bronze

About these checks

Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.

Statistics and arithmetic are recomputed, not judged.

Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.

What counts as a claim ›How we measure confidence ›How we check this ›

Are you an author, or do you see a problem with this page? Request a review

How to cite

Cite CoChat for the checks on this page, and the paper for its own findings.

This page
CoChat. (2026). Citation check: Integrating RFID and BIM technologies for mitigating risks and improving schedule performance of prefabricated house construction. https://app.cochat.ai/papers/10.1016/j.jclepro.2017.07.156
The paper
Li, C. Z., Zhong, R. Y., Xue, F., Xu, G., Chen, K., Huang, G. G., & Shen, G. Q. (2017). Integrating RFID and BIM technologies for mitigating risks and improving schedule performance of prefabricated house construction. Journal of Cleaner Production. https://doi.org/10.1016/j.jclepro.2017.07.156

Data sources

Bibliographic data: Semantic Scholar, OpenAlex, Crossref.

Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).

Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.