Integrating RFID and BIM technologies for mitigating risks and improving schedule performance of prefabricated house construction
Open accessAbstract
Abstract With its generally recognized benefits of clean and safe working environment and good quality, prefabricated house construction (PHC) as a solution is gaining momentum in the face of various housing challenges in Hong Kong's construction industry. Although prefabrication has its own benefits, its fundamental disadvantages of fragmentation, discontinuity, poor interoperability, and scarce real-time information availability have imposed significant adverse influence on the schedule performance of prefabricated house construction. As a result, despite the promise of the government to provide sufficient houses and harmonious housing, schedule delay problems still frequently beset the industry of PHC. To help address schedule delay problems encountered in the construction of prefabrication housing, this research first identified and analysed critical schedule risk factors that may have significant influence on the schedule performance of PHC. Based on the identified schedule risks, the challenges and corresponding required functions for enhancing schedule performance are determined. Then, a radio frequency identification device (RFID)-enabled BIM platform that integrates various involved stakeholders, information/data flow, offshore prefabrication procedures, and state-of-the-art construction technologies, is developed to handle the critical schedule factors. Smart construction objects and RFID-enabled smart gateway work collaboratively to ease operations within the three echelons of prefabrication manufacturing, logistics and on-site assembly construction, while real-time captured data are used to form a closed-loop visibility and traceability mode in which different end users can supervise the construction statuses, progresses in real time. The developed platform can provide various services, tools and mechanisms to different stakeholders, improve the success of daily operations and decision makings throughout PHC management, such that critical schedule risks can be mitigated and the schedule performance of PHC can be enhanced to ensure timely project delivery.
Overview
The claims and statistics of this paper haven’t been checked yet.
Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cited by
Li, C. Z., Xue, F., Li, X., Hong, J., & Shen, G. Q. (2018) · Automation in Construction · doi:10.1016/j.autcon.2018.01.001 · Cited by 420
Self-citationBuilding information modelling for off-site construction: Review and future directions
Yin, X., Liu, H., Chen, Y., & Al-Hussein, M. (2019) · Automation in Construction · doi:10.1016/j.autcon.2019.01.010 · Cited by 420
Internet of Things research in supply chain management and logistics: A bibliometric analysis
Rejeb, A., Simske, S., Rejeb, K., Treiblmaier, H., & Zailani, S. (2020) · Internet of Things · doi:10.1016/j.iot.2020.100318 · Cited by 384
Wang, M., Wang, C. C., Sepasgozar, S., & Zlatanova, S. (2020) · Buildings · doi:10.3390/buildings10110204 · Cited by 357
Smart Infrastructure: A Vision for the Role of the Civil Engineering Profession in Smart Cities
Berglund, E. Z., Monroe, J. G., Ahmed, I., Noghabaei, M., Do, J., Pesantez, J. E., Khaksar Fasaee, M. A., Bardaka, E., Han, K., Proestos, G. T., et al. (2020) · Journal of Infrastructure Systems · doi:10.1061/(asce)is.1943-555x.0000549 · Cited by 185
Metadata
- Authors
- Li, C. Z., Zhong, R. Y., Xue, F., Xu, G., Chen, K., Huang, G. G., & Shen, G. Q.
- Venue
- Journal of Cleaner Production
- Publisher
- Elsevier BV
- Published
- 2017-11
- Volume
- 165
- Pages
- 1048-1062
- ISSN
- 0959-6526 (ISSN-L)
- OpenAlex
- W2737493980
- Cited by
- 272
- References
- 0
- FWCI
- 18.83
- Type
- journal article
- Language
- en
- Open access
- bronze
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
How to cite
Cite CoChat for the checks on this page, and the paper for its own findings.
- This page
- CoChat. (2026). Citation check: Integrating RFID and BIM technologies for mitigating risks and improving schedule performance of prefabricated house construction. https://app.cochat.ai/papers/10.1016/j.jclepro.2017.07.156
- The paper
- Li, C. Z., Zhong, R. Y., Xue, F., Xu, G., Chen, K., Huang, G. G., & Shen, G. Q. (2017). Integrating RFID and BIM technologies for mitigating risks and improving schedule performance of prefabricated house construction. Journal of Cleaner Production. https://doi.org/10.1016/j.jclepro.2017.07.156
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.