Activity-Based Safety Risk Quantification for Concrete Formwork Construction
The DOI matches its Crossref record; 7 of the 7 references it cites were found in a registry or an index.
Abstract
Most of safety risk research focuses on high-severity safety risks for large-scale construction processes. Such studies help firms identify the highest risk processes so they may be targeted for improvement. However, few studies quantify safety risk at the activity level or include low-severity, high-frequency risks that some literatures suggest contribute to a large proportion of total risk. This paper presents research that involved the holistic quantification of risks for the activities associated with the construction of concrete formwork. Three major research efforts are discussed: (1) identification of activities required to construct concrete formwork; (2) selection of an appropriate all-inclusive and mutually exclusive risk classification system; and (3) the quantification of the average frequency and severity levels for each risk classification associated with each activity. To identify formwork construction activities, 256 worker-hours of observation were conducted and the resulting activity descriptions were reviewed and validated by industry professionals. Risk classifications appropriate for this study were created by aggregating relevant literature. Finally, the Delphi method was implemented to individually quantify average frequency and severity using scales that define the entire spectrum of possible values. In total, 130 frequency ratings and 130 severity ratings were obtained over three rounds of Delphi surveys. Results indicate that there are 13 major activities required to construct concrete formwork and the highest risk activities are applying form oil, lifting and lowering form components, and accepting materials from a crane. The data presented in this paper can be used to target specific high-risk formwork construction activities for improvement.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Safety Hazard Identification on Construction Projects
Carter, G., & Smith, S. D. (2006) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2006)132:2(197 · Cited by 477
Analysis of Construction Worker Fall Accidents
Huang, X., & Hinze, J. (2003) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2003)129:3(262 · Cited by 405
Systems Model of Construction Accident Causation
Mitropoulos, P., Abdelhamid, T. S., & Howell, G. A. (2005) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2005)131:7(816 · Cited by 336
Identifying Critical Cross-Cultural School Psychology Competencies
Rogers, M. R., & Lopez, E. C. (2002) · Journal of School Psychology · doi:10.1016/s0022-4405(02)00093-6 · Cited by 176
Safety Risk Identification and Assessment for Beijing Olympic Venues Construction
Sun, Y., Fang, D., Wang, S., Dai, M., & Lv, X. (2007) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(2008)24:1(40 · Cited by 130
Sustainable construction safety and health rating system
Rajendran, S. (2006) · Cited by 41
(2003) · doi:10.1061/(asce)0733-9364(2003)129:5(492
Cited by
Diamond, I. R., Grant, R. C., Feldman, B. M., Pencharz, P. B., Ling, S. C., Moore, A. M., & Wales, P. W. (2014) · Journal of Clinical Epidemiology · doi:10.1016/j.jclinepi.2013.12.002 · Cited by 3,740
Overview and analysis of safety management studies in the construction industry
Zhou, Z., Goh, Y. M., & Li, Q. (2015) · Safety Science · doi:10.1016/j.ssci.2014.10.006 · Cited by 601
BIM-based fall hazard identification and prevention in construction safety planning
Zhang, S., Sulankivi, K., Kiviniemi, M., Romo, I., Eastman, C. M., & Teizer, J. (2015) · Safety Science · doi:10.1016/j.ssci.2014.08.001 · Cited by 447
Zhang, S., Boukamp, F., & Teizer, J. (2015) · Automation in Construction · doi:10.1016/j.autcon.2015.02.005 · Cited by 392
Tixier, A. J.-P., Hallowell, M. R., Rajagopalan, B., & Bowman, D. (2016) · Automation in Construction · doi:10.1016/j.autcon.2015.11.001 · Cited by 333
Self-citationAMEYAW, E. E., HU, Y., SHAN, M., CHAN, A. P. C., & LE, Y. (2016) · JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT · doi:10.3846/13923730.2014.945953 · Cited by 307
Sousa, V., Almeida, N. M., & Dias, L. A. (2014) · Safety Science · doi:10.1016/j.ssci.2014.02.008 · Cited by 248
Role of Safety Training: Impact on Hazard Recognition and Safety Risk Perception
Namian, M., Albert, A., Zuluaga, C. M., & Behm, M. (2016) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001198 · Cited by 199
Analyzing risk factors in crane-related near-miss and accident reports
Raviv, G., Fishbain, B., & Shapira, A. (2017) · Safety Science · doi:10.1016/j.ssci.2016.08.022 · Cited by 161
Metadata
- Authors
- Hallowell, M. R., & Gambatese, J. A.
- Venue
- Journal of Construction Engineering and Management
- Published
- 2009-10
- Volume
- 135
- Issue
- 10
- Pages
- 990-998
- ISSN
- 0733-9364 (ISSN-L)
- 1943-7862
- OpenAlex
- W2018914771
- Cited by
- 181
- References
- 7
- FWCI
- 13.22
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.