Design for manufacture and assembly in construction: a review
Open accessThe DOI matches its Crossref record; 30 of the 30 references it cites were found in a registry or an index.
Abstract
Design for Manufacture and Assembly (DfMA) is known as both a philosophy and a methodology whereby products are designed in a way that is as amenable as possible for downstream manufacturing and assembly. As construction is moving towards a combination of offsite prefabrication and onsite assembly, DfMA is gaining momentum in this heterogeneous industry. Nevertheless, a comprehensive review of DfMA in construction, its prospects and challenges in particular, seems absent from the literature. This study reviews the processes and principles of DfMA and explores the possible perspectives of DfMA with a view to providing implications to the construction industry. It was found that DfMA in construction has been interpreted from three perspectives: (1) a holistic design process that encompasses how structure or object will be manufactured, assembled and guided with DfMA principles; (2) an evaluation system that can work with virtual design and construction (VDC) to evaluate the efficiency of manufacturing and assembly; and (3) a game-changing philosophy that embraces the ever-changing prefabrication and modular construction technologies. This study suggests that development of design guidelines, forming multidisciplinary team, use of VDC systems and understanding the lean principles are factors that could further enhance the successful application of DfMA in construction.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Tranfield, D., Denyer, D., & Smart, P. (2003) · British Journal of Management · doi:10.1111/1467-8551.00375 · Cited by 15,386
Toyota production system: beyond large-scale production
Ohno, T., & Rosen, C. B. (1998) · CERN Document Server (European Organization for Nuclear Research) · Cited by 4,522
An exploration towards a production theory and its application to construction
Koskela, L. (2000) · Aaltodoc (Aalto University) · Cited by 1,868
Product design for manufacture and assembly
Boothroyd, G. (1994) · Computer-Aided Design · doi:10.1016/0010-4485(94)90082-5 · Cited by 1,726 · cited 13×
“The main highlight is that in each case, a considerable reduction in the part count has been achieved, resulting in a simpler product (Boothroyd, 1994).”
BackgroundMethodInfluentialProduct Design: Techniques in Reverse Engineering and New Product Development
Otto, K., & Wood, K. L. (2000) · Cited by 1,102
Toyota Production System: Beyond Large-Scale Production
Ohno, T., & Bodek, N. (2019) · Productivity Press eBooks · doi:10.4324/9780429273018 · Cited by 793
How to write a literature review paper?
Wee, B. V., & Banister, D. (2016) · Transport Reviews · doi:10.1080/01441647.2015.1065456 · Cited by 578 · cited 1×
“Our pool is close in size to 30 papers minimum threshold for literature reviews suggested by Wee and Banister (2016). The 26 articles were thoroughly reviewed which leads to the last steps involved analysis and synthesis of the selected literature to identify any Table 1.”
BackgroundMajor Barriers to Off-Site Construction: The Developer’s Perspective in China
Mao, C., Shen, Q., Pan, W., & Ye, K. (2015) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000246 · Cited by 446
Re-engineering through pre-assembly: client expectations and drivers
Gibb, A., & Isack, F. (2003) · Building Research & Information · doi:10.1080/09613210302000 · Cited by 397
Pull-Driven Scheduling for Pipe-Spool Installation: Simulation of Lean Construction Technique
Tommelein, I. D. (1998) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(1998)124:4(279 · Cited by 322 · cited 1×
“Since Koskela (1992) brought the production theory into construction, much has been written about the lean concept and lean tools to make the site assembly efficient (Tommelein, 1998).”
Background
Cited by
Digital technologies can enhance climate resilience of critical infrastructure
Argyroudis, S. A., Mitoulis, S. A., Chatzi, E., Baker, J. W., Brilakis, I., Gkoumas, K., Vousdoukas, M., Hynes, W., Carluccio, S., Keou, O., et al. (2022) · Climate Risk Management · doi:10.1016/j.crm.2021.100387 · Cited by 361
Tan, T., Mills, G., Papadonikolaki, E., & Liu, Z. (2021) · Automation in Construction · doi:10.1016/j.autcon.2020.103451 · Cited by 212
A study of literature in modular integrated construction - Critical review and future directions
Abdelmageed, S., & Zayed, T. (2020) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2020.124044 · Cited by 190
Digitizing material passport for sustainable construction projects using BIM
Atta, I., Bakhoum, E. S., & Marzouk, M. M. (2021) · Journal of Building Engineering · doi:10.1016/j.jobe.2021.103233 · Cited by 165
Charef, R., Lu, W., & Hall, D. (2022) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2022.132421 · Cited by 99
Self-citation
Metadata
- Authors
- Gao, S., Jin, R., & Lu, W.
- Venue
- Building Research & Information
- Publisher
- Informa UK Limited
- Published
- 2019-09-05
- Volume
- 48
- Issue
- 5
- Pages
- 538-550
- ISSN
- 0961-3218 (ISSN-L)
- 1466-4321
- OpenAlex
- W2971550880
- Cited by
- 176
- References
- 30
- FWCI
- 10.35
- Type
- journal article
- Language
- en
- Open access
- green
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.