Self-scheduling of a hydro producer in a pool-based electricity market
Abstract
This paper addresses the self-scheduling of a hydro generating company in a pool-based electricity market. This company comprises several cascaded plants along a river basin. The objective is to maximize the profit of the company from selling energy in the day-ahead market. This paper proposes a 0/1 mixed-integer linear programming model to account, in every plant, for the nonlinear and nonconcave three-dimensional (3-D) relationship between the power produced, the water discharged, and the head of the associated reservoir. Additionally, start-up costs due mainly to the wear and tear are considered. Finally, different realistic case studies are analyzed in detail.
Integrity signals
Registry
Cites
Statistics
Claims the paper makes
Claims other papers make about this one
Each is checked against this paper’s own text: does it say what the citing paper says it does?
The mathematical formulation of piecewise functions using mixed-integer linear expressions has been typically used in different power system problems.
“The mathematical formulation of piecewise functions using mixed-integer linear expressions has been typically used in different power system problems, [38,39].”
From Integration of Electric Vehicles in Low-Voltage Distribution Networks Considering Voltage Management (2020) · cites this paper as [39]
Cited by
Sorted by citations
Integration of Electric Vehicles in Low-Voltage Distribution Networks Considering Voltage Management
Carrión, M., Zárate-Miñano, R., & Domínguez, R. (2020) · Energies · doi:10.3390/en13164125 · Cited by 18 · see citing works
- Authors
- Conejo, A. J., Arroyo, J. M., Contreras, J., & Villamor, F. A.
- Affiliations
- University of Castilla-La Mancha (ES)
- Venue
- IEEE Transactions on Power Systems
- Published
- 2002-11
- Volume
- 17
- Issue
- 4
- Pages
- 1265-1272
- ISSN
- 0885-8950 (ISSN-L)
- OpenAlex
- W2122916962
- Cited by
- 326
- References
- 0
- Citations by year
- 2026: 11 · 2025: 4 · 2024: 9 · 2023: 9 · 2022: 18 · 2021: 17 · 2020: 15 · 2019: 10 · 2018: 15 · 2017: 27 · 2016: 18 · 2015: 16 · 2014: 21 · 2013: 19 · 2012: 22
- FWCI
- 2.80
- Type
- journal article
- Language
- en
- Open access
- closed
- Locations
- IEEE Transactions on Power Systems (publishedVersion)
- Topics
- Physical Sciences › Engineering › Electrical and Electronic Engineering › Electric Power System Optimization
- Physical Sciences › Engineering › Ocean Engineering › Water resources management and optimization
- Physical Sciences › Engineering › Electrical and Electronic Engineering › Integrated Energy Systems Optimization
- Keywords
- hydropower scheduling, self-scheduling, pool-based electricity market, day-ahead market, cascade hydropower stations, water discharge, start-up costs, profit maximization, 0-1 mixed integer linear programming
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review