Governance Impact Assessment on Large Infrastructure Project (LIP) Delivery.

Open access
Department of Quantity Surveying, Bayero University, Zarewa, G. A., Ibrahim, A. D., Department of Quantity Surveying, Ahmadu Bello University, Ibrahim, Y. M., Department of Quantity Surveying, Ahmadu Bello University, Adogbo, K. J., Department of Quantity Surveying, Ahmadu Bello University·2018·Journal of Engineering, Project, and Production Management

Abstract

The linkage of failures of many projects, including Large Infrastructure Projects (LIPs), to governance problems by previous studies implies that governance impacts projects' performance.Identification and understanding of the impacts have therefore become necessary in order to ensure that projects are governed in a way that will ensure their successful delivery.This study assessed impact of governance on delivery of Large Infrastructure Projects (LIPs) through a three phase research approach.The first phase involved literature review followed by semi-structured interviews with key stakeholders/role players in the governance of eight LIPs in different locations in Nigeria in the second phase.A thematic data analysis of the study's findings was finally conducted in the third phase to identify themes and sub-themes after which conclusions were drawn.The study established that governance impacts LIPs delivery both positively and negatively depending on how the governance is approached.Four LIPs were successful due to proper initiation, setting aside funds for the projects at the onset, proactive risk management, top management support, and simple governance policies and structures.Intuitive initiation on political exigencies, tying funding to erratic sources of funding without contingency arrangement, Procuring Authorities' (PAs) disregard for due process and consultants' advice, failure of a Procuring Authority (PA) to meet contractual obligations and change of government were identified by the study as major governance aspects that led to the abandonment of 4LIPs.The study concluded that there was a need for significant improvement and standardisation of approaches to governance of LIPs particularly in developing countries like Nigeria and accordingly recommends the development of a governance framework containing guidelines, including sanctions for violators, to guide the governance of the projects in the country.

The claims and statistics of this paper haven’t been checked yet.

Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.

A few free checks a day · papers already verified open instantly · results are public

Integrity signals

Registry

Crossref · 10.32738/jeppm.201801.0003

Cites

Statistics

Claims the paper makes

The claims and statistics of this paper haven’t been checked yet.

Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.

A few free checks a day · papers already verified open instantly · results are public

Claims other papers make about this one

Each is checked against this paper’s own text: does it say what the citing paper says it does?

  • Successful project implementations remain a critical challenge for many organisations.

    “Successful project implementations remain a critical challenge for many organisations.”

    From Blockchain Technology: Potential Applications for Public Sector E-Procurement and Project Management (2022) · cites this paper as [2]

    Section 2.2, “Impact of Governance on Project Delivery” (page unavailable), describes governance challenges that can prevent successful project delivery and cites instances of failed or abandoned projects. This supports the general concern, but the paper’s discussion of large infrastructure projects does not establish that successful implementation remains a critical challenge for many organisations generally. (LLM, conf=0.78)

    Experimental — accuracy not yet measured
  • Project governance has an impact on project performance, and improper project governance is a reason for large infrastructure project failures.

    “Zarewa et al. [2] argued that project governance has an impact on project performance, and improper project governance is a reason for large infrastructure project failures.”

Self-check

Percentages, sums and reported differences re-computed from the paper’s own numbers.

The self-check needs the paper’s full text.

The citation lists haven’t been fetched yet

References 28 · Cited by 6

Research works printed but not linked: 34

  1. Akinyokun, O. C., Angaye C. O., and Ubaru, M. O. (2009).Factor Analysis of the Performance Indices of ICTprojects in the Public Sector of Nigerian Economy.Journal of Technology Research, 1, 1-15.
  2. Bekker, M. C. (2008). Project Governance for Large Capital Investments. A Thesis submitted to Graduate School of Technology Management, University of Pretoria, South Africa in partial fulfillment of the requirements for the Award of the Degree of Doctor of Philosophy.
  3. Bekker, M. C. and Steyn, H. (2009).Project Governance: Definition and Framework.Journal of Contemporary Management, 6,214-228.
  4. Benţa, D. Podean, L. M., and Mircean, C. (2011).On Best Practices for Risk Management in Complex Projects.InformaticaEconomică vol.15, no. 2/2011.Retrieved 8/7/2017 from revistaie.ase.ro/content/58/53-Benta,Podean.pdf
  5. Brady, T. and Davies, A. (2013).Governing Complex Infrastructure Developments: Learning from Successful Projects.International Symposium for Next Generation Infrastructure, October 1-4 2013, Wollongong, Australia.
  6. Clarke, A. (1999). "A Practical Use of Key Success Factors to Improve the Effectiveness of Project Management.International Journal of Project Management, 17(3), 139-145
  7. Clarke, T. (2008).Introduction: Theories of Governance- Reconceptualising Corporate Governance Theory after the Enron Experience. In T. Clarke (ed), Theories of Corporate Governance: The Philosophical Foundations of Corporate Governance. Routledge, London, United Kingdom.
  8. Clealand, D. I. (1986). Measuring Success: The Owner's Viewpoint. Proceedings of the 18 th Annual Seminar/Syposium, Montreal Canada, Project Management Institute, 6-12.
  9. Cusack, B. and Lo, S. (2014).Project Governance Requirements: A Case Study. Proceedings of Twenty Second European Conference on Information Systems, Tel Aviv 2014.
  10. Damoah, S. K., Akwei, C., and Mouzughi, Y. (2015). Causes of government project failure in developing countries-Focus on Ghana.2015 Conference Proceedings, f British Academy of Management. Accessed June, 20 th 2017from: https://www.researchgate.net/publication/299537426_ Causes_of_government_project_failure_in_developin g_countries_-_Focus_on_Ghana
  11. Dunovic, I. B. (2010). A Study of Project Governance Frameworks for Large Infrastructure Projects with Reflection on Road Transport Projects. International Journal of Organization, Technology and Management in Construction,2(1), 145-155.
  12. Ibrahim, A.D., Price A.D.F., and Dainty, A.R.J. (2006). An Analysis of Success Factors for PPP in Infrastructure Projects in Nigeria.Journal of Construction Management, 12(1), 2006.
  13. Ika, L. A. (2009). Project Success as a Topic in Project Management Journals. Project Management Journal, 40(4), 6-19. http://dx.doi.org/ 10.1002/pmj.20137. · DOI
  14. Ika, L. A. (2012). Project Management for Development in Africa: Why Projects are Failing and what can be Done about it. Project Management Journal, 43(4), 27-41. http://dx.doi.org/ 10.1002/pmj.21281. · DOI
  15. Khalid, A. and Bassam, A. H. (2017). Critical Success Factors for Public Private Partnerships in the UAE Construction Industry A Comparative Analysis between the UAE and the UK. Journal of Engineering, Project, and Production Management, 2017,7(1), 21-32.
  16. Klakegg, O. J., Williams, T., and Magnussan, O. M. (2007).Design of Innovative Governance Frameworks for Major Public Investment Projects: A Comparative Study of Governance Frameworks in UK and Norway.Research Conference: Projects in Innovation, Innovation in Projects.Brighton, CENTRIM, University of Brighton. Large Projects Governance Research Project Report (2013). Designing Effective Governance Structure for Large Projects.Aalto University, 2013, Helsinki.
  17. Kumar, R. (2011). Research Methodology: A Step-by- Step-Guide for Beginners (Third Edition).SAGE Publications Ltd, 1 Oliver's Yard, 55 City Road, London EC1Y 1SP.
  18. Lechler, T. and Cohen, M. (2009). Exploring the Role of Steering Committees in Realizing Value from Project Management. Project Management Journal, 40(1), 42-54. doi: http://dx.doi.org/10.1002/pmj.20094 · DOI
  19. Lim, C. S. and Mohamed, M. Z. (1999).Criteria of Project Success: An Explanatory Re- examination.International Journal of Project Management, 17(4), 243-248. http://dx.doi.org/ 10.1016/S0263-7863(98)00040-4. · DOI
  20. Mir, F. A. and Pinnington, A. H. (2014). Exploring the Value of Project Management: Linking Project Management Performance and Project Success. International Journal of Project Management,32, 202-217.
  21. Nasser, O. A., Monty, S., and Chong, H. Y. (2016).Guidelines of Using Project Management Tools and Techniques to Mitigate Factors Causing Delays in Public Construction Projects in Kingdom of Saudi Arabia. Journal of Engineering, Project, and Production Management, 6(2), 90-103
  22. Nistor, R. and Beleiu, I. (2014).Approaches Regarding the Dimensions of Project Governance. Proceedings of the 8 th International Management Conference: "Management Challenges for Sustainable Development, November 6 th 7 th 2014. Bucharest, Romania.
  23. Olalusi, O. and Otunola, A. (2012). Abandonment of Building Projects in Nigeria-A Review of Causes and Solutions. International Conference on Chemical, Civil and Environmental Engineering (ICCEE 2012), March 24-25 Dubai.
  24. Olusegun, A. E. and Michael, A. O. (2011).Abandonment of Construction Projects in Nigeria: Causes and Effects. Journal of Emerging Trends in Economics and Management Sciences (JETEMS) 2, 142- 145.Scholarlink Research Institute Journals, 2011 (ISSN: 2141-7024).
  25. Oppong, S. H. (2013) The Problem of Sampling in Qualitative Research-Retrieved from Journal of Engineering, Project, and Production Management, 2018, 8(1), 9-21 Impact Assessment on Large Infrastructure Project (LIP) Delivery 19 www.ajmse.leena- luna.co.jp/AJMSEPDFs/Vol.../AJMSE2013(2.2- 21).pd...-17 th May, 2014.
  26. Patel, M. and Robinson, H. (2010). Impact of Governance on Project Delivery of Complex NHS PFI/PPP Schemes. Journal of Financial Management of Property and Construction, 15(3), 216-234.
  27. Rameezdeen, R., Palliyaguru, R. S., and Amaratunga, D. (2006). Financing Contractors in Developing Countries: Impact of Mobilization Advance Payment. Research Gate. Retrieved July 9, 2017 from https://www.researchgate.net/puglication/46481787_F inancing_contractors_in_....
  28. Robinson, H., Carrillo, P., Anumba, C. J., and Patel, M. (2010).Governance and Knowledge Management for Public Private Partnerships. Wiley-Blackwell. West Sussex, PO1985Q, United Kingdom.
  29. Rubin, H. J. and Rubin, I. S. (2012).Qualitative Interviewing: The Art of Hearing Data (Third Edition). Sage Publications Inc, 2455 Teller Road, Thousand Oaks, California 91320.
  30. Stickney, F. A. and Johnston, W. R. (1983).Delegation and Sharing of Authority by the Project Manager. Project Management Quarterly, 14(1), 42-53.
  31. Swanepoel, H. and De Beer, F. (2006).Community development. Breaking the cycle of poverty 4 th edition. Formeset Printers Cape. South Africa.
  32. Thomas, G. and Fernandez, W. (2008). Success in IT projects: A Matter of efinition? International Journal ofProject Management, 26(7), 733-742. http://dx.doi.org/10.1016/j.ijproman.2008.06.003. · DOI
  33. Ubani, E. C. and Ononju, C. N. (2013).A Study of Failure and Abandonment of Public Sector-Driven Civil Engineering Projects in Nigeria: An Empirical Review. American Journal of Scientific and Industrial Research. ISSN: 2153-649X, doi:10.5251/ajsir.2013.4.1.75-82. · DOI
  34. Zuofa, T. and Ochieng, E. G. (2014).Project Failure: The Way Forward and Panacea for Development. International Journal of Business and Management, 9(11), 2014. Published by Canadian Center of Science and Education.

Authors
Department of Quantity Surveying, B. U., Zarewa, G. A., Ibrahim, A. D., Department of Quantity Surveying, A. B. U., Ibrahim, Y. M., Department of Quantity Surveying, A. B. U., Adogbo, K. J., & Department of Quantity Surveying, A. B. U.
Affiliations
  • Bayero University Kano (NG)
  • Ahmadu Bello University (NG)
Corresponding author
Zarewa, G. A.
Venue
Journal of Engineering, Project, and Production Management
Published
2018-01-31
Volume
8
Issue
1
Pages
9-21
ISSN
  • 2221-6529 (ISSN-L)
  • 2223-8379
OpenAlex
W2796348686
Cited by
6
References
28
Citations by year
2025: 1 · 2023: 1 · 2022: 2 · 2021: 1 · 2019: 1
FWCI
0.40
Type
journal article
Language
en
Open access
Licence
cc-by-nc-nd
Locations
  • Journal of Engineering Project and Production Management (publishedVersion, cc-by-nc-nd)
  • DOAJ (DOAJ: Directory of Open Access Journals) (submittedVersion, cc-by-sa)
Topics
  • Social Sciences › Decision Sciences › Management Science and Operations Research › Construction Project Management and Performance
  • Social Sciences › Business, Management and Accounting › Strategy and Management › Public-Private Partnership Projects
  • Social Sciences › Political Science and International Relations › Public Administration in Developing Nations
Keywords
large-scale infrastructure projects, project governance, project delivery, project failure, project abandonment, procurement authority, risk management, top management support, project initiation, funding allocation, governance framework, Nigeria

About these checks

Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.

Statistics and arithmetic are recomputed, not judged.

Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.

What counts as a claim ›How we measure confidence ›How we check this ›

Are you an author, or do you see a problem with this page? Request a review