Risk Management Assessment in Oil and Gas Construction Projects Using Structural Equation Modeling (PLS-SEM)
Open accessAbstract
Oil and gas construction projects are of great importance to support and facilitate the process of operation and production. However, these projects usually face chronic risks that lead to time overrun, cost overrun, and poor quality, affecting the projects’ success. Hence, this study focused on identifying, classifying, and modeling the risk factors that have negative effects on the success of construction projects in Yemen. The data were collected through a structured questionnaire. Statistical analysis, relative important index method, and probability impact matrix analysis were carried out to classify and rank the risk factors. The partial least squares path modeling or partial least squares structural equation modeling (PLS-PM, PLS-SEM) is a method for structural equation modeling that allows an estimation of complex cause–effect relationships in path models with latent variables. PLS-SEM was employed to analyze data collected from a questionnaire survey of 314 participants comprising the clients, contractors, and consultants working in oil and gas construction projects. The results showed that the goodness of fit index of the model is 0.638. The developed model was deemed to fit because the analysis result of the coefficient of determination test (R2) of the model was 0.720, which indicates the significant explanation of the developed model for the relationship between the causes of risks and their effects on the success of projects. The most impacted internal risk categories include project management, feasibility study design, and resource material availability. The main external risk elements include political, economic, and security considerations. The created risk factor model explained the influence of risk factors on the success of construction projects effectively, according to statistical and expert validation tests.
Overview
The claims and statistics of this paper haven’t been checked yet.
Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Lowry, P. B., & Gaskin, J. (2014) · IEEE Transactions on Professional Communication · doi:10.1109/tpc.2014.2312452 · Cited by 1,901
Flagged first, then by citations
Research works printed but not linked: 93
- 2015, Identification and assessment of risk factors affecting construction projects, HBRC J., 13, 202
- Dziadosz, 2015, Risk analysis in construction project—Chosen methods, Procedia Eng., 122, 258, 10.1016/j.proeng.2015.10.034 · DOI
- Thuyet, 2007, Risk management in oil and gas construction projects in Vietnam, Int. J. Energy Sect. Manag., 1, 175, 10.1108/17506220710761582 · DOI
- Nosair, 2014, Risk assessment and analysis for the construction of off shore oil & gas projects, Int. J. Sci. Res., 2, 317
- Sweis, 2019, Causes of delay in Iranian oil and gas projects: A root cause analysis, Int. J. Energy Sect. Manag., 13, 630, 10.1108/IJESM-04-2018-0014 · DOI
- Kamalirad, S., Kermanshachi, S., Shane, J., and Anderson, S. (June, January 31). Assessment of construction projects’ impact on internal communication of primary stakeholders in complex projects. Proceedings of the 6th CSCE/CRC International Construction Specialty Conference, Vancouver, BC, Canada.
- Doloi, 2012, Understanding impacts of time and cost related construction risks on operational performance of PPP projects, Int. J. Strateg. Prop. Manag., 16, 316, 10.3846/1648715X.2012.688774 · DOI
- Sultan, B., and Kajewski, S. (2003, January 19–21). The Yemen construction industry: Readying the industry for the successful implementation of sustainability. Proceedings of the International Conference on Smart and Sustainable Built Environment, Brisbane, QL, Australia. Available online: http://eprints.qut.edu.au/164/1/Kajewski_SASSBE.pdf.
- Mubin, 2008, Risk analysis for construction and operation of gas pipeline projects in Pakistan, Pak. J. Eng. Appl. Sci., 2, 22
- Hair, 2012, Partial least squares: The better approach to structural equation modeling?, Long Range Plann., 45, 312, 10.1016/j.lrp.2012.09.011 · DOI · Paper page
- Hair, 2011, PLS-SEM: Indeed a silver bullet, J. Mark. Theory Pract., 19, 139, 10.2753/MTP1069-6679190202 · DOI · Paper page
- Sarstedt, M., Ringle, C.M., and Hair, J.F. (2017). Partial Least Squares Structural Equation Modeling, Springer. · DOI · Paper page
- Dijkstra, 2015, Research essay consistent partial least squares path modeling, MIS Q., 39, 297, 10.25300/MISQ/2015/39.2.02 · DOI · Paper page
- Jun, 2011, The effects of project uncertainty and risk management on IS development project performance: A vendor perspective, Int. J. Proj. Manag., 29, 923, 10.1016/j.ijproman.2010.11.002 · DOI
- Memon, 2013, Using structural equation modelling to assess effects of construction resource related factors on cost overrun, World Appl. Sci. J., 21, 6
- Pham, 2014, Schedule delays in engineering, procurement, and construction petrochemical projects in Vietnam: A qualitative research study, Int. J. Energy Sect. Manag., 8, 3, 10.1108/IJESM-06-2013-0009 · DOI
- Sultan, 2017, Priorities for sustainable construction industry development in Yemen, Int. J. Appl. Eng. Res., 12, 886
- Ahmed, 2016, The effect of risk allocation on minimizing disputes in construction projects in Egypt, Int. J. Eng. Res. Technol., 5, 523
- Banaitiene, N., Banaitis, A., Banaitene, N., and Banaitis, A. (2012). Risk Management in Construction Projects, IntechOpen. · DOI
- Zadeh, 2016, An index to assess project management competencies in managing design changes, Int. J. Constr. Eng. Manag., 5, 11
- Muya, 2008, Risk identification on community-based construction projects in Zambia, J. Eng. Des. Technol., 6, 145
- Akadiri, O.P. (2011). Development of a Multi-Criteria Approach for the Selection of Sustainable Materials for Building Projects. [Ph.D. Thesis, University of Wolverhampton]. Available online: http://wlv.openrepository.com/wlv/bitstream/2436/129918/1/Akadiri_PhD%20thesis.pdf.
- Chien, L., Chiu, S., Tseng, W., and Chen, K. (July, January 30). Risk assessment of offshore wind-farm construction. Proceedings of the The 23rd International Offshore and Polar Engineering Conference, Anchorage, AK, USA.
- Issa, 2015, A risk allocation model for construction projects in Yemen, Civ. Environ. Res., 7, 78
- Lam, 2007, Modelling risk allocation decision in construction contracts, Int. J. Proj. Manag., 25, 485, 10.1016/j.ijproman.2006.11.005 · DOI
- Dey, 2012, Project risk management using multiple criteria decision-making technique and decision tree analysis: A case study of Indian oil refinery, Prod. Plan. Control., 23, 903, 10.1080/09537287.2011.586379 · DOI
- Sharma, 2014, Cost overrun factors and project cost risk assessment in construction industry—A state of the art review, Int. J. Civ. Eng., 3, 139
- Nasirzadeh, 2014, Dynamic modeling of the quantitative risk allocation in construction projects, Int. J. Proj. Manag., 32, 442, 10.1016/j.ijproman.2013.06.002 · DOI
- Cagliano, 2015, Choosing project risk management techniques, A theoretical framework J. Risk Res., 18, 232, 10.1080/13669877.2014.896398 · DOI
- Abdelgawad, 2010, Risk management in the construction industry using combined fuzzy FMEA and fuzzy AHP, J. Constr. Eng. Manag., 136, 1028, 10.1061/(ASCE)CO.1943-7862.0000210 · DOI
- Aven, 2009, Perspectives on risk in a decision-making context—Review and discussion, Saf. Sci., 47, 798, 10.1016/j.ssci.2008.10.008 · DOI
- Rodhi, N.N., Anwar, N., and Wiguna, I.P.A. (2017, January 9–10). A review on disaster risk mitigation in the oil and gas project. Proceedings of the IOP Conference Series: Earth and Environmental Science, the 4th International Seminar on Sustainable Urban Development, Jakarta, Indonesia.
- Chaher, 2016, Facilitate risk management in construction process by using hierarchical risk breakdown structure, Int. J. Sci. Res. Publ., 6, 703
- Choudhry, 2014, Cost and schedule risk analysis of bridge construction in Pakistan: Establishing risk guidelines, J. Constr. Eng. Manag., 140, 04014020, 10.1061/(ASCE)CO.1943-7862.0000857 · DOI
- Tah, 2000, Information modelling for a construction project risk management system, Eng. Constr. Archit. Manag., 7, 107, 10.1108/eb021136 · DOI
- Yildiz, 2014, A knowledge-based risk mapping tool for cost estimation of international construction projects, Autom. Constr., 43, 144, 10.1016/j.autcon.2014.03.010 · DOI
- Kassem, 2019, Using probability impact matrix (PIM) in analyzing risk factors affecting the success of oil and gas construction projects in Yemen, Int. J. Energy Sect. Manag., 14, 527, 10.1108/IJESM-03-2019-0011 · DOI
- Gamil, 2018, Assessment of critical factors contributing to construction failure in Yemen, Int. J. Constr. Manag., 20, 429
- Kassem, 2020, Using relative importance index method for developing risk map in oil and gas construction projects, J. Kejuruter., 32, 85
- Forteza, 2017, Effects of organizational complexity and resources on construction site risk, J. Safety Res., 62, 185, 10.1016/j.jsr.2017.06.015 · DOI
- Salleh, J. (2009). Critical Success Factors of Project Management for Brunei Construction Projects: Improving Project Performance. [Ph.D. Thesis, Queensland University of Technology].
- Chandra, 2015, Structural equation model for investigating risk factors affecting project success in Surabaya, Procedia Eng., 125, 53, 10.1016/j.proeng.2015.11.009 · DOI
- Falamarzi, 2019, A review on existing sensors and devices for inspecting railway infrastructure, J. Kejuruter., 31, 1, 10.17576/jkukm-2019-31(1)-01 · DOI
- Samarah, 2016, Causes and effects of delay in public construction projects in Jordan, Am. J. Eng. Res., 5, 87
- Sambasivan, 2007, Causes and effects of delays in Malaysian construction industry, Int. J. Proj. Manag., 25, 517, 10.1016/j.ijproman.2006.11.007 · DOI
- Kassem, 2020, Structural modelling of internal risk factors for oil and gas construction projects, Int. J. Energy Sect. Manag., 14, 975, 10.1108/IJESM-11-2019-0022 · DOI
- Kassem, 2020, Theoretical review on critical risk factors in oil and gas construction projects in Yemen, Eng. Constr. Archit. Manag., 28, 934, 10.1108/ECAM-03-2019-0123 · DOI
- Njogu, P.M. (2015). Assessment of Effects of Construction Risks on Project Delivery among Contractors in Kenya. [Ph.D. Thesis, Jomo Kenyatta University of Agriculture and Technology]. Available online: http://ir.jkuat.ac.ke/bitstream/handle/123456789/1798/Peter%20MSc%202015.pdf?sequence=1&isAllowed=y.
- Graves, 2000, Qualitative risk assessment, Proj. Manag. Inst., 14, 61
- Mander, 2007, Incremental dynamic analysis applied to seismic financial risk assessment of bridges, Eng. Struct., 29, 2662, 10.1016/j.engstruct.2006.12.015 · DOI
- Hair, 2019, When to use and how to report the results of PLS-SEM, Eur. Bus. Rev., 31, 2, 10.1108/EBR-11-2018-0203 · DOI · Paper page
- Hair, J.F.J., Hult, G.T.M., Ringle, C., and Sarstedt, M. (2014). A Primer on Partial Least Squares Structural Equation Modeling (PLS-SEM), Elsevier.
- Sarstedt, 2017, Partial least squares structural equation modelling, Handb. Mark. Res., 26, 1
- Zhao, 2018, Risk paths in BIM adoption: Empirical study of China, Eng. Constr. Archit. Manag., 25, 1170, 10.1108/ECAM-08-2017-0169 · DOI
- Kloppers, C., and Hirst, R. (2010, January 4). Conducting labour risk audits and implementing a labour risk management programme in order to create and maintain labour stability. Proceedings of the Middle East Health, Safety, Security, and Environment Conference and Exhibition, Manama, Bahrain. · DOI
- Rahman, 2013, Modeling causes of cost overrun in large construction projects with partial least square SEM approach constructions perspective, Res. J. Appl. Sci. Eng. Technol., 5, 1963, 10.19026/rjaset.5.4736 · DOI
- Randhawa, 2017, The moderating effect of project risk mitigation strategies on the relationship between delay factors and construction project performance, J. Sci. Technol. Policy Manag., 21, 191
- Kassem, 2020, Assessment of the effect of external risk factors on the success of an oil and gas construction project, Eng. Constr. Archit. Manag., 27, 2767, 10.1108/ECAM-10-2019-0573 · DOI
- Kim, 2016, A sample size calculator for SMART pilot studies, SIAM Undergrad. Res. Online, 9, 229, 10.1137/15S014058 · DOI
- Sekaran, U., and Bougie, R. (2019, February 14). Research Methods for Business: A Skill-Building Approach. Available online: https://books.google.com.my/books?hl=en&lr=&id=Ko6bCgAAQBAJ&oi=fnd&pg=PA19&dq=Sekaran,+U.,+%26+Bougie,+R.+(2010).+Research+Methods+for+Business:+A+Skill+Building+Approach.+London:+Wiley.&ots=2B2LT4LZmL&sig=Ag9yzsNyyO2IMHXG1su5pfbY5eM&redir_esc=y#v=onepage.
- Xiong, 2014, Examining the influence of participant performance factors on contractor satisfaction: A structural equation model, Int. J. Proj. Manag., 32, 482, 10.1016/j.ijproman.2013.06.003 · DOI
- Famiyeh, 2017, Major causes of construction time and cost overruns: A case of selected educational sector projects in Ghana, J. Eng. Des. Technol., 15, 181
- Kassem, 2019, Evaluation of risk factors affecting on oil and gas construction projects in Yemen, Int. J. Eng. Technol., 8, 6, 10.14419/ijet.v8i1.2.24864 · DOI
- Deng, 2018, Identifying micro variables contributing to political risks in international construction projects, Eng. Constr. Archit. Manag., 25, 317, 10.1108/ECAM-02-2017-0042 · DOI
- Hulland, 1999, Use of partial least squares (PLS) in strategic management research: A review of four recent studies, Strateg. Manag. J., 20, 195, 10.1002/(SICI)1097-0266(199902)20:2<195::AID-SMJ13>3.0.CO;2-7 · DOI · Paper page
- Kock, 2016, Hypothesis testing with confidence intervals and P values in PLS-SEM, Int. J. E-Collab., 12, 1
- Henseler, 2009, The use of partial least squares path modeling in international marketing, Adv. Int. Mark., 20, 277
- Hussain, S., Fangwei, Z., Siddiqi, A.F., Ali, Z., and Shabbir, M.S. (2018). Structural equation model for evaluating factors affecting quality of social infrastructure projects. Sustainability, 10. · DOI
- Henseler, 2013, Goodness-of-fit indices for partial least squares path modeling, Comput. Stat., 28, 565, 10.1007/s00180-012-0317-1 · DOI
- Kassem, 2018, Evaluation of risk factors affecting time and cost of construction projects in Yemen, Int. J. Eng. Technol., 8, 168
- Jarkas, 2015, Major construction risk factors considered by general contractors in Qatar, Eur. J. Mark., 24, 41
- Antah, F.H., Khoiry, M.A., Nizam, K., Maulud, A., and Abdullah, A. (2021). Perceived usefulness of airborne LiDAR technology in road design and management: A review. Sustainability, 13. · DOI
- Dosumu, 2017, Causes of errors in construction contract documents in southwestern Nigeria, J. Constr. Bus. Manag., 1, 11
- Li, 2018, Evaluating the risk of natural gas pipeline operation management in intuitionistic fuzzy linguistic environments, Math. Probl. Eng., 2018, 1
- Kassem, 2019, Risk factors in oil and gas construction projects in developing countries: A case study, Int. J. Energy Sect. Manag., 13, 846, 10.1108/IJESM-11-2018-0002 · DOI
- Luo, 2010, Assessment of fiscal terms of international petroleum contracts, Pet. Explor. Dev., 37, 756, 10.1016/S1876-3804(11)60009-8 · DOI
- Ali, K.N., Alhajlah, H.H., and Kassem, M.A. (2022). Collaboration and Risk in Building Information Modelling (BIM): A Systematic Literature Review. Buildings, 12. · DOI
- Ofori, 2016, Construction in developing countries, Constr. Manag. Econ., 25, 1, 10.1080/01446190601114134 · DOI
- Rahman, 2021, Factors influencing the quality of Environmental Impact Assessment Report in Malaysia, Malays. J. Soc. Space, 1, 155
- Goetz, E., and Shenoi, S. (2008). Reducing Risk in Oil and Gas Production Operations. Critical Infrastructure Protection, Springer. ICCIP 2007. IFIP International Federation for Information Processing. · DOI
- Li, X., Wang, C., Kassem, M.A., Alhajlah, H.H., and Bimenyimana, S. (2022). Evaluation Method for Quality Risks of Safety in Prefabricated Building Construction Using SEM–SDM Approach. Int. J. Environ. Res. Public Health, 19. · DOI
- Hirst, 2010, Undertaking a $4Bn dollar LNG project in a high risk security context and achieving exemplary safety performance, Soc. Pet. Eng. SPE Int. Conf. Heal. Saf. Environ. Oil Gas Explor. Prod., 1, 669
- Baghdadi, 2015, Saudi Arabian aviation construction projects: Identification of risks and their consequences, Procedia Eng., 123, 32, 10.1016/j.proeng.2015.10.054 · DOI
- Ali, Z., Zhu, F., and Hussain, S. (2018). Identification and assessment of uncertainty factors that influence the transaction cost in public sector construction projects in Pakistan. Buildings, 8. · DOI
- Myakenkaya, 2014, Similarities and differences of the war and projects. Winning strategies, Procedia Soc. Behav. Sci., 119, 314, 10.1016/j.sbspro.2014.03.036 · DOI
- Sultan, 2018, Political instability and the informal construction sector in, Int. J. Civ. Eng. Technol., 9, 1228
- Alaghbari, 2017, Factors affecting construction labour productivity in Yemen, Int. J. Constr. Manag., 3599, 1
- Ahmad, 2013, Evaluation of risk factors affecting time and cost of construction projects in Yemen, Int. J. Manag., 4, 168
- Derakhshanalavijeh, 2017, Cost overrun in construction projects in developing countries, gas-oil industry of Iran as a case study, J. Civ. Eng. Manag., 23, 125, 10.3846/13923730.2014.992467 · DOI
- Algahtany, 2016, Introducing a new risk management model to the Saudi Arabian construction industry, Procedia Eng., 145, 940, 10.1016/j.proeng.2016.04.122 · DOI
- Siang, 2012, Implemention of risk management in the Malaysian construction industry, J. Surv. Constr. Prop., 3, 15
- Iacob, 2014, Risk management and evaluation and qualitative method within, Ecoforum J., 3, 10
- Assaf, 2006, Causes of delay in construction, J. Proj. Manag., 24, 349
Metadata
- Authors
- Kassem, M. A.
- Affiliations
- University of Technology Malaysia (MY)
- Corresponding author
- Kassem, Mukhtar A.
- ORCID
- Kassem, Mukhtar A.
- Venue
- Gases
- Publisher
- MDPI AG
- Published
- 2022-05-09
- Volume
- 2
- Issue
- 2
- Pages
- 33-60
- ISSN
- 2673-5628 (ISSN-L)
- OpenAlex
- W4229459718
- Cited by
- 36
- References
- 1
- Citations by year
- 2026: 11 · 2025: 6 · 2024: 6 · 2023: 11 · 2022: 2
- FWCI
- 3.31
- Type
- journal article
- Language
- en
- Open access
- gold
- doi.org
- Licence
- Locations
- Gases (publishedVersion, cc-by)
- DOAJ (DOAJ: Directory of Open Access Journals) (submittedVersion, cc-by-sa)
- Funders
- Universiti Teknologi Malaysia (UTM) Research Grant Vot (J130000.7113.05E79)
- Topics
- Social Sciences › Decision Sciences › Management Science and Operations Research › Construction Project Management and Performance
- Social Sciences › Economics, Econometrics and Finance › Finance › Capital Investment and Risk Analysis
- Physical Sciences › Engineering › Building and Construction › BIM and Construction Integration
- Keywords
- risk management, construction project success, risk factors, project management, political risk, economic risk, security risks, Yemen
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review