Characteristics of the Construction Industry in Developing Countries and Its Implications for Health and Safety: An Exploratory Study in Ghana
Open accessThe DOI matches its Crossref record; 24 of the 24 references it cites were found in a registry or an index.
Abstract
From both practical and theoretical perspectives, understanding the health and safety (H&S) implications of the characteristics and foundation upon which the construction industry in developing countries is built and operates is essential for H&S management within the industry. While many studies have provided evidence of factors affecting construction H&S in developing countries, none has fully considered the H&S implications of the industry’s characteristics. The current study thus examined how the peculiar characteristics of the construction industry in developing countries impact on the industry’s H&S management. Data were collected using questionnaire surveys from construction industry professionals in Ghana. Nine distinct characteristics were identified and ranked, as well as their relationships and statistical significance determined through correlation and analysis of variance (ANOVA), respectively. The findings showed that these characteristics of the construction industry in developing countries, particularly the lack of skilled and educated workforce, reliance on labour intensive methods and lack of single regulatory authority, present huge challenges to the management of H&S. Accordingly, this research recommended strategic interventions which are tailored towards the context of the industry’s characteristics. With the construction industry in developing countries exhibiting similar characteristics, the findings of this research can serve as a framework for country-specific study. The study contributes to the broader H&S performance improvement research in developing countries by throwing light on the characteristics of the industry that pose challenges to H&S performance.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Structural Equation Modeling With AMOS: Basic Concepts, Applications, and Programming, Third Edition
Byrne, B. M. (2016) · doi:10.4324/9781315757421 · Cited by 4,653
Byrne, B. M. (2013) · doi:10.4324/9780203805534 · Cited by 4,016
Occupational risk assessment in construction industry – Overview and reflection
Pinto, A., Nunes, I. L., & Ribeiro, R. A. (2011) · Safety Science · doi:10.1016/j.ssci.2011.01.003 · Cited by 432 · cited 1×
“[54] reinforced this point by stating that the financial fragility and instability of small contractors can impede the extent to which good H&S practices can be adopted.”
BackgroundGlobal estimates of occupational accidents
Hämäläinen, P., Takala, J., & Saarela, K. L. (2006) · Safety Science · doi:10.1016/j.ssci.2005.08.017 · Cited by 417 · cited 1×
“[12] asserted that the rates of occupational accidents in these developing countries are unacceptably high and predict that the rates will increase parallelly with the pace of industrialisation.”
BackgroundViability of Designing for Construction Worker Safety
Gambatese, J., Behm, M., & Hinze, J. (2005) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2005)131:9(1029 · Cited by 319 · cited 1×
“The traditional system typically defines the roles, responsibilities and liabilities of different players involved in a construction project [64].”
BackgroundCosts of occupational injuries in construction in the United States
Waehrer, G. M., Dong, X. S., Miller, T., Haile, E., & Men, Y. (2007) · Accident Analysis & Prevention · doi:10.1016/j.aap.2007.03.012 · Cited by 294
Subcontractor perspectives on supply chain alliances
Dainty, A. R. J., Briscoe, G. H., & Millett, S. J. (2001) · Construction Management and Economics · doi:10.1080/01446190110089727 · Cited by 291
Anaman, K. A., & Osei‐Amponsah, C. (2007) · Construction Management and Economics · doi:10.1080/01446190701411208 · Cited by 179 · cited 1×
“Other studies have established that significant relationships exist in one way or another between the rate of growth of the construction industry and the rate of macroeconomic growth of developing countries [2].”
BackgroundLowest price or value? Investigation of UK construction clients' tender selection process
Wong, C. H., Holt, G. D., & Cooper, P. A. (2000) · Construction Management and Economics · doi:10.1080/014461900433050 · Cited by 177 · cited 1×
“Besides, lowest price is not the best approach to achieve the overall lowest cost upon project completion [37].”
BackgroundArocena, P., & Núñez, I. (2010) · International Small Business Journal Researching Entrepreneurship · doi:10.1177/0266242610363521 · Cited by 149 · cited 1×
“In another vein, it is acknowledged that small contractors generally do not manage H&S risks as effectively as larger contractors [49] and, consequently, suffer higher risks of occupational accidents than larger firms [23,50].”
BackgroundAn integrated framework for concurrent life-cycle design and construction
Evbuomwan, N. F. O., & Anumba, D. O. C. (1998) · Advances in Engineering Software · doi:10.1016/s0965-9978(98)00024-6 · Cited by 147 · cited 1×
“There is a lack of interaction between consultants/designers and contractors during the design and construction phase, and this set-up often affects project outcomes during the construction phase such as increased project complexity, rework, cost and time overruns as well as safety concerns [62].”
BackgroundGyekye, S. A., & Salminen, S. T. (2008) · Safety Science · doi:10.1016/j.ssci.2007.12.007 · Cited by 132
Durdyev, S., Mohamed, S., Lay, M. L., & Ismail, S. B. (2017) · Construction Economics and Building · doi:10.5130/ajceb.v17i4.5596 · Cited by 119 · cited 1×
“[18] studied key factors affecting construction safety performance in developing countries by taking evidence from Cambodia.”
BackgroundAn investigation into the impact of culture on construction project performance
Ankrah, N. A. (2007) · OpenGrey (Institut de l'Information Scientifique et Technique) · Cited by 117
Holmes, N., Lingard, H. C., Yesilyurt, Z., & Munk, F. D. (1999) · Journal of Safety Research · doi:10.1016/s0022-4375(99)00020-1 · Cited by 116 · cited 1×
“In another vein, it is acknowledged that small contractors generally do not manage H&S risks as effectively as larger contractors [49] and, consequently, suffer higher risks of occupational accidents than larger firms [23,50].”
BackgroundKheni, N. A. (2008) · OpenGrey (Institut de l'Information Scientifique et Technique) · Cited by 114
Fostering a Strong Construction Safety Culture
Zou, P. X. W. (2010) · Leadership and Management in Engineering · doi:10.1061/(asce)lm.1943-5630.0000093 · Cited by 109
Wang, M., Sun, J., Du, H., & Wang, C. (2018) · Advances in Civil Engineering · doi:10.1155/2018/6580375 · Cited by 84
Self-citationTracing the African Project Failure Syndrome: the significance of 'ubuntu'
Rwelamila, P. D., Talukhaba, A. A., & Ngowi, A. B. (1999) · Engineering Construction & Architectural Management · doi:10.1108/eb021122 · Cited by 77
Awarding Construction Contracts on Multicriteria Basis in China
Shen, L., Li, Q. M., Drew, D., & Shen, Q. (2004) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2004)130:3(385 · Cited by 77 · cited 1×
“However, despite its popularity, there is a counterargument that shows the problems with using the traditional procurement method, including time-consuming, discourage innovation, decreased buildability and the fragmentation of the project teams [33,34].”
BackgroundHon, C. K. H., Chan, A. P. C., & Yam, M. C. H. (2011) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000497 · Cited by 73 · cited 1×
“For these small firms, business survival is their top priority, and therefore, H&S issues are not of great concern [55].”
BackgroundHUMAN CAPITAL THEORY: IMPLICATIONS FOR THE GHANAIAN CONSTRUCTION INDUSTRY DEVELOPMENT
Fugar, F. D. K., Ashiboe-Mensah, N. A., & Adinyira, E. (2013) · Journal of Construction Project Management and Innovation · doi:10.36615/jcpmi.v3i1.37 · Cited by 61 · cited 1×
“Similarly, the lack of training for these workers on H&S matters worsens the situation [69].”
BackgroundThe Case for a Construction Industry Council in Ghana
Ofori-Kuragu, J. K., Owusu‐Manu, D., & Ayarkwa, J. (2016) · Journal of Construction in Developing Countries · doi:10.21315/jcdc2016.21.2.7 · Cited by 35 · cited 1×
“professionals tend to operate independently [57].”
Potential difficulties in applying the Pay for Safety Scheme (PFSS) in construction projects
Choi, T. N. Y., Chan, D. W. M., & Chan, A. P. C. (2011) · Accident Analysis & Prevention · doi:10.1016/j.aap.2011.04.015 · Cited by 29 · cited 1×
“For instance, buying personal protective equipment (PPE) and employing safety officers on projects invariably means additional costs [52], but with the size and capital of these small contractors, the resources and facilities to enable safe construction are not readily available [52,53].”
Background
Cited by
Improving Safety Performance of Construction Workers through Learning from Incidents
Chan, A. P. C., Guan, J., Choi, T. N. Y., Yang, Y., Wu, G., & Lam, E. (2023) · International Journal of Environmental Research and Public Health · doi:10.3390/ijerph20054570 · Cited by 55
“The temporary nature and specificity of the work sites demonstrate how the construction industry behaves differently and has unique characteristics [5].”
Background
Metadata
- Authors
- Boadu, E. F., Wang, C. C., & Sunindijo, R. Y.
- Venue
- International Journal of Environmental Research and Public Health
- Publisher
- MDPI AG
- Published
- 2020-06-09
- Volume
- 17
- Issue
- 11
- Pages
- 4110
- ISSN
- 1660-4601 (ISSN-L)
- OpenAlex
- W3035224601
- Cited by
- 198
- References
- 24
- FWCI
- 21.27
- Type
- journal article
- Language
- en
- Open access
- gold
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.