A Matlab-Based Educational Tool for Quantitative Risk Analysis
Overview
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
Claims other papers make about this one
Each is checked against this paper’s own text: does it say what the citing paper says it does?
With the MCSimulRisk software, the impact of each risk on project duration objectives (quantified in time units) and cost objectives (quantified in monetary units) is determined.
“With the help of the 'MCSimulRisk' simulation software (Acebes et al. 2024;Acebes et al. 2023), this paper determines the impact of each risk on project duration objectives (quantified in time units) and cost objectives (quantified in monetary units).”
From Beyond probability-impact matrices in project risk management: A quantitative methodology for risk prioritisation (2024) · cites this paper as Acebes et al. 2023
Citations
Cites
No references could be resolved yet.
Research works printed but not linked: 3
- International Organization for Standardization. ISO 31000: 2018 Risk management – Guidelines, vol. 2 (2018)
- Rezaie, K., Amalnik, M.S., Gereie, A., Ostadi, B., Shakhseniaee, M.: Using extended Monte Carlo simulation method for the improvement of risk management: consideration of relationships between uncertainties. Appl. Math. Comput. 190, 1492–1501 (2007). https://doi.org/10.1016/j.amc.2007.02.038 · DOI
- Hillson, D.: How risky is your project – and what are you doing about it ? PMI Global Congress Proceedings - Phoenix, Arizona, USA, pp. 1–10 (2014).
Cited by
Sorted by citations
Acebes, F., González-Varona, J. M., López-Paredes, A., & Pajares, J. (2024) · Humanities and Social Sciences Communications · doi:10.1057/s41599-024-03180-5 · Cited by 74
Self-citation
Metadata
- Authors
- Acebes, F., De Antón, J., Villafáñez, F., & Poza, D.
- Affiliations
- Universidad de Valladolid (ES)
- Corresponding author
- Acebes, F.
- Venue
- Lecture Notes on Data Engineering and Communications Technologies
- Publisher
- Springer International Publishing
- Published
- 2023
- Pages
- 42-46
- ISSN
- 2367-4512 (ISSN-L)
- 2367-4520
- OpenAlex
- W4360914454
- Cited by
- 6
- References
- 0
- Citations by year
- 2026: 2 · 2025: 1 · 2024: 2 · 2023: 1
- FWCI
- 2.88
- Type
- conference paper
- Language
- en
- Open access
- closed
- Licence
- Locations
- Lecture notes on data engineering and communications technologies (publishedVersion)
- Topics
- Social Sciences › Decision Sciences › Management Science and Operations Research › Construction Project Management and Performance
- Social Sciences › Economics, Econometrics and Finance › Finance › Capital Investment and Risk Analysis
- Social Sciences › Decision Sciences › Management Science and Operations Research › Simulation Techniques and Applications
- Keywords
- quantitative risk analysis, project risk management, Monte Carlo simulation, project management education, educational software, MATLAB application
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review