Beyond probability-impact matrices in project risk management: A quantitative methodology for risk prioritisation
Open accessAbstract
The project managers who deal with risk management are often faced with the difficult task of determining the relative importance of the various sources of risk that affect the project. This prioritisation is crucial to direct management efforts to ensure higher project profitability. Risk matrices are widely recognised tools by academics and practitioners in various sectors to assess and rank risks according to their likelihood of occurrence and impact on project objectives. However, the existing literature highlights several limitations to use the risk matrix. In response to the weaknesses of its use, this paper proposes a novel approach for prioritising project risks. Monte Carlo Simulation (MCS) is used to perform a quantitative prioritisation of risks with the simulation software MCSimulRisk. Together with the definition of project activities, the simulation includes the identified risks by modelling their probability and impact on cost and duration. With this novel methodology, a quantitative assessment of the impact of each risk is provided, as measured by the effect that it would have on project duration and its total cost. This allows the differentiation of critical risks according to their impact on project duration, which may differ if cost is taken as a priority objective. This proposal is interesting for project managers because they will, on the one hand, know the absolute impact of each risk on their project duration and cost objectives and, on the other hand, be able to discriminate the impacts of each risk independently on the duration objective and the cost objective.
Overview
AI snapshot
Written from the paper’s full text.
TL;DR
The paper proposes a Monte Carlo simulation-based methodology to prioritise project risks quantitatively by modelling each risk’s probability and impact on duration and cost, instead of using probability-impact matrices. In a real EPC case study, the method produces separate duration and cost rankings that differ from the risk matrix and quantify each risk’s absolute impact.
Key findings
- In the case study, 11 risks were identified (with duration/cost codes R1–R15); R3 was the most important risk for total duration, while R15 was the most important for total cost. R5, initially identified as a duration risk, ranked fourth for cost impact.
- Risks that impacted only cost had zero contribution to project duration; risks that impacted duration also impacted total cost, and this impact could be more significant than that of risks directly affecting cost.
- The proposed quantitative prioritisation yielded a different risk order from the probability-impact matrix. For example, at P95, R3 added 26.330 days, R5 added 750.362 ×1000 monetary units in cost, and R15 added 3,060.927 ×1000 monetary units in cost.
- The method provides absolute impacts on duration and cost independently, allowing managers to prioritise according to whether schedule or cost is the dominant project objective.
Methods
- The proposed method identifies risks, assigns probability and impact distributions, and incorporates them into a Monte Carlo simulation of the project model using the MCSimulRisk software. The methodology describes Bernoulli-type PDFs for stochastic risk events and uniform distributions for epistemic uncertainty; in the case study, risks are modelled with uniform distribution functions.
- The case study is a real-life engineering, procurement and construction project in South America with 32 activities, a planned duration of 300 days, and a planned cost of 30,000 (×1000) monetary units. Each simulation used 20,000 iterations.
- A baseline simulation is run without risks, then one simulation is run per risk. Using a chosen percentile (P95 as value at risk in the case study), the impact of each risk is calculated as the difference between the total duration/cost with that risk and the baseline, and risks are ranked separately for duration and cost.
Limitations
- The paper states that results depend on the accuracy of estimates, including probability distributions, their parameters, and risk aversion parameters; it assumes risks are independent, which may not hold in very complex projects with interrelated risks.
- The paper states that further research is needed on interrelated risks, a sensitivity study across many projects, and implementation in real projects across sectors.
- Evident from the text: the empirical demonstration is a single EPC case study, so generalisability to other project types or sectors is not established.
Model-written summary. Check it against the paper before relying on it.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
8 of 32 cited sources checked · 4 supported · 0 flagged · accuracy not yet measured
- Premisecitation
Existing literature highlights several limitations to use the risk matrix.
“However, the existing literature highlights several limitations to use the risk matrix.”
- Also stated in: § Introduction · boosted
“However, the probability-impact matrix has severe limitations (Goerlandt and Reniers, 2016;Duijm, 2015;Vatanpour et al. 2015;Ball and Watt, 2013;Levine, 2012;Cox, 2008;Cox et al. 2005).”
Quote in the paperSubstantial claim2 of 3 sources checked - Also stated in: § Introduction · boosted
- Premisecitation
Probabilistic representations of uncertainty have been successfully employed with uniform distributions to characterise uncertainty when knowledge is sparse or absent.
“Probabilistic representations of uncertainty have been successfully employed with uniform distributions to characterise uncertainty when knowledge is sparse or absent (Curto et al. 2022;Vanhoucke, 2018;Helton et al. 2006).”
Quote in the paperSubstantial claim1 of 3 sources checked - Premisecitation
Aleatoric risk uncertainty can be modelled using a probability distribution function (PDF), exactly as when modelling activity uncertainty.
“This aleatoric risk uncertainty can be modelled using a probability distribution function (PDF), exactly as we do when modelling activity uncertainty (Acebes et al. 2015(Acebes et al. , 2014)).”
Quote in the paperSubstantial claim1 of 2 sources checked- cites Acebes et al. 2015 source
The case-study table accompanying the Conclusions (page unavailable) says activity durations are modelled as normal distributions. Section 3.2 describes estimating a probability density function from simulated project data, but the copy does not say that aleatoric risk uncertainty itself is modelled with a PDF in the same way as activity uncertainty. (LLM, conf=0.83)
Experimental — accuracy not yet measured - cites Acebes et al. 2014 source
- Findingown data
For the example project, risk R3 is the most important risk for controlling total duration because it contributes the most duration to the project if it exists.
“For the project proposed as an example, we find that risk R3 is the most important one if we wish to control the total duration because it corresponds to the risk that contributes the most duration to the project if it exists.”
Quote in the paperSubstantial claim - Findingown data
The P95 corresponding to cost is 30,339 ×1000 monetary units.
“Similarly, the P95 corresponding to cost is 30,339 ×1000 monetary units.”
Quote in the paperNot a substantial claim
- Findingown data
For the example project, using P95 as VaR yields a total planned cost of 3.12 × 10^7 monetary units.
“In this example, for P95 we obtain a total cost value of 3.12 × 10 7 monetary units.”
Quote in the paperNot a substantial claim - Findingown data
Risks with an impact on the cost of activities do not influence the total duration result.
“From the obtained results, we find that the risks with an impact on the cost of activities do not influence the total duration result.”
Quote in the paperSubstantial claim - Findingnone given
Risks identified to have an impact on duration also impact the cost objective.
“The same is not valid for the risks identified to have an impact on duration because the latter also impacts the cost objective.”
Quote in the paperSubstantial claim - Findingown data
The proposed method yields numerical values for the impact of risks on total duration and cost objectives, independently of one another.
“In our case, we obtain numerical values for the impact of risks on total duration and cost objectives, and independently of one another.”
Quote in the paperSubstantial claim - Findingreasoning
The impact on total cost of risks that impact project duration is more significant than that of a risk that impacts only the activity's cost.
“This impact is more significant than that of a risk that impacts only the activity's cost.”
Quote in the paperSubstantial claim - Findingreasoning
The proposed methodology achieves an independent risk prioritisation in duration impact and project cost impact terms.
“Finally, we achieve an independent risk prioritisation in duration impact and project cost impact terms.”
Quote in the paperSubstantial claim - Findingown data
Risks that impact project duration also impact the total cost target.
“The risks that impact project duration also impact the total cost target.”
Quote in the paperSubstantial claim - Findingown data
For the chosen P95 risk appetite, the planned project duration is 323.43 days.
“For the chosen percentile (P95), which represents our risk appetite for this project, the planned project duration is 323.43 days.”
Quote in the paperNot a substantial claim - Findingown data
The proposed case study reveals that risk prioritisation yields remarkably different results depending on the selected method.
“The proposed case study reveals that risk prioritisation yields remarkably different results depending on the selected method, as our findings confirm.”
Quote in the paperSubstantial claim - Findingown data
For the example project, risk R15 is the most important risk in terms of impact on total project costs.
“On the impact on project costs, we note that risk R15 is the most important.”
Quote in the paperNot a substantial claim - Findingown data
The order of importance of identified risks differs depending on whether the risk matrix or quantitative prioritisation is used.
“We can see that the order of importance of the identified risks differs depending on our chosen method (risk matrix versus quantitative prioritisation).”
Quote in the paperSubstantial claim - Findingreasoning
With 95% probability the planned project will be completed before 323.43 days.
“In other words, with a 95% probability the planned project will be completed before 323.43 days.”
Quote in the paperSubstantial claim - Findingreasoning
Risks that initially impact a duration objective are more critical for their impact on cost than some risks that directly impact the project's cost (e.g., R5).
“We also see how the risks that initially impact a duration objective are more critical for their impact on cost than others that directly impact the project's cost (e.g.R5).”
Quote in the paperSubstantial claim - Interpretationnone given
The risk prioritisation achieved by applying the proposed methodology is based on quantifying the impacts that risks may have on the duration and cost objectives of the project.
“In addition to the above, the risk prioritisation achieved by applying the proposed methodology is based on quantifying the impacts that risks may have on the duration and cost objectives of the project.”
Quote in the paperSubstantial claim - Interpretationnone given
The novelty proposed in this study incorporates into the project simulation model all the identified risks characterised by their probability and impact values, as well as the set of activities making up the project.
“In contrast, the novelty proposed in this study incorporates into the project simulation model all the identified risks characterised by their probability and impact values, as well as the set of activities making up the project.”
Quote in the paperNot a substantial claim - Interpretationnone given
The literature still does not contain references that use data obtained in a qualitative analysis (probability and impact of each identified risk) to perform a quantitative risk analysis integrated into the project model.
“Although Monte Carlo simulation is widely used in project risk assessments (Tong et al. 2018;Taroun, 2014), as far as we know, the literature still does not contain references that use the data obtained in a qualitative analysis (data related to the probability and impact of each identified risk) to perform a quantitative risk analysis integrated into the project model.”
Quote in the paperSubstantial claim0 of 2 sources checked - Interpretationreasoning
The proposed methodology allows project managers to select the most critical risks by overcoming the problems exhibited by previous methodologies like the probability-impact matrix.
“The proposed methodology allows project managers to select the most critical risks by overcoming the problems exhibited by previous methodologies like the probability-impact matrix.”
Quote in the paperSubstantial claim - Interpretationreasoning
The methodology allows quantified results to be obtained for each risk by differentiating between the project duration objective and its cost objective.
“The methodology allows quantified results to be obtained for each risk by differentiating between the project duration objective and its cost objective.”
Quote in the paperSubstantial claim - Interpretationnone given
The proposed method independently quantifies each risk's impact on the cost and duration objectives.
“We independently quantify each risk's impact on the cost and duration objectives.”
Quote in the paperSubstantial claim - Premisecitation
A Bernoulli distribution function adequately models stochastic uncertainty.
“Moreover, one PDF that adequately models this type of uncertainty is a Bernoulli distribution function (Vose, 2008).”
Quote in the paperSubstantial claim0 of 1 sources checked- cites Vose, 2008
Couldn’t be matched to a paper in Crossref, so it can’t be checked.
- Premisecitation
Increasingly more academics and practitioners are reluctant to resort to risk matrices.
“Since then, increasingly more academics and practitioners are reluctant to resort to risk matrices (Qazi et al. 2021).”
Quote in the paperNot a substantial claim0 of 1 sources checked- cites Qazi et al. 2021 source
- Interpretationreasoning
The proposed methodology provides a quantitative assessment of the impact of each risk, measured by the effect on project duration and total cost.
“With this novel methodology, a quantitative assessment of the impact of each risk is provided, as measured by the effect that it would have on project duration and its total cost.”
Quote in the paperSubstantial claim - Interpretationnone given
One risk is more important than another not only because of its estimated probability and impact but also because the activity it impacts may have a high criticality index (probability of belonging to the project's critical path).
“It seems clear that one risk is more important than another, not only because of the estimation of its probability and impact but also because the activity on which it impacts may have a high criticality index or not (probability of belonging to the project's critical path).”
Quote in the paperSubstantial claim - Interpretationnone given
The proposed methodology offers significant advantages over other risk prioritisation methods and tools, especially the traditional risk matrix.
“This proposed methodology offers significant advantages over other risk prioritisation methods and tools, especially the traditional risk matrix.”
Quote in the paperNot a substantial claim - Interpretationreasoning
The methodology allows establishing prioritisation based on absolute (and not relative) importance for project objectives.
“In this way, with the impact of all the risks, it is possible to establish their prioritisation based on their absolute (and not relative) importance for project objectives.”
Quote in the paperSubstantial claim - Interpretationreasoning
As a result, the paper obtains a quantified prioritisation of each risk that differentiates the importance of each risk according to the impact on cost and duration objectives.
“As a result, we obtain a quantified prioritisation of each risk that differentiates the importance of each risk according to the impact on cost and duration objectives.”
Quote in the paperSubstantial claim - Interpretationnone given
The proposed quantitative method based on MCS provides numerical results of the importance of risks and their impact on total duration and cost objectives.
“For this purpose, we propose a quantitative method based on MCS, which provides us with numerical results of the importance of risks and their impact on total duration and cost objectives.”
Quote in the paperSubstantial claim
- It may state two separate claims as one. 22
- Probably not a substantial claim. 26
It may state two separate claims as one.
InterpretationcitationWith the MCSimulRisk software, the impact of each risk on project duration objectives (quantified in time units) and cost objectives (quantified in monetary units) is determined.
“With the help of the 'MCSimulRisk' simulation software (Acebes et al. 2024;Acebes et al. 2023), this paper determines the impact of each risk on project duration objectives (quantified in time units) and cost objectives (quantified in monetary units).”
Quote in the paperSubstantial claim1 of 2 sources checkedProbably not a substantial claim. The paper’s conclusions may not depend on it.
PremisecitationRisk matrices are widely recognised tools by academics and practitioners in various sectors to assess and rank risks according to likelihood of occurrence and impact on project objectives.
“Risk matrices are widely recognised tools by academics and practitioners in various sectors to assess and rank risks according to their likelihood of occurrence and impact on project objectives.”
- Also stated in: § Introduction · boosted
“Risk matrices emerge as established familiar tools for assessing and ranking risks in many fields and industry sectors (Krisper, 2021;Qazi et al. 2021;Qazi and Simsekler, 2021;Monat and Doremus, 2020;Li et al. 2018).”
Quote in the paperNot a substantial claim1 of 3 sources checked- cites Krisper, 2021 source
The Introduction describes risk matrices as established tools for assessing and ranking risks across many domains and industries. Phase 1 identifies impact and probability (likelihood of occurrence) as common assessment factors. Our copy does not specifically define impact in terms of project objectives, so that qualification is not supported. (LLM, conf=0.82)
Experimental — accuracy not yet measured - cites Qazi et al. 2021 source
- cites Qazi and Simsekler, 2021 source
- Also stated in: § Introduction · boosted
Probably not a substantial claim. The paper’s conclusions may not depend on it. It may state two separate claims as one.
PremisecitationMCS can be invaluable to risk managers and helpful for estimating project durations and costs.
“This technique can be invaluable to risk managers and helpful for estimating project durations and costs (Ali Elfarra and Kaya, 2021).”
Quote in the paperNot a substantial claim1 of 1 sources checked- cites Ali Elfarra and Kaya, 2021 source
The Introduction (page unavailable) says Monte Carlo simulations help estimate confidence levels for electricity costs in wind-energy projects, supporting the cost-estimation part of the claim. It also discusses minimizing investment risk, but does not address risk managers or estimating project durations. The pay-off period in §4.4 is not a project-duration estimate. (LLM, conf=0.86)
Experimental — accuracy not yet measured
Probably not a substantial claim. It may state two separate claims as one.
PremisecitationThe risk matrix is a tool included in the qualitative analysis for risk management and used to analyse, visualise and prioritise risks to make decisions on resources.
“The risk matrix, or probabilityimpact matrix, is a tool included in the qualitative analysis for risk management and used to analyse, visualise and prioritise risks to make decisions on the resources to be employed to combat them (Goerlandt and Reniers, 2016;Duijm, 2015).”
Quote in the paperSubstantial claim1 of 2 sources checked- cites Goerlandt and Reniers, 2016 source
- cites Duijm, 2015 source
The Abstract says risk matrices are widely used in risk management and discusses qualitative assessment of likelihood and consequence. It also says they serve as corporate risk acceptance criteria, but the available passages do not say they are used to visualise and prioritise risks or to decide how to allocate resources. (LLM, conf=0.82)
Experimental — accuracy not yet measured
Probably not a substantial claim. The paper’s conclusions may not depend on it. It may state two separate claims as one.
Findingown dataThe case study project comprises 32 activities, divided into three groups: engineering, procurement and construction (EPC).
“The project comprises 32 activities, divided into three groups: engineering, procurement and construction (EPC).”
Quote in the paperNot a substantial claimIt may state two separate claims as one.
Findingown dataRisks that impact project duration also impact total costs, whereas cost-only risks do not impact total project duration.
“Unlike cost risks (which do not impact the total project duration), the risks that can impact project duration also impact total costs.”
Quote in the paperSubstantial claimProbably not a substantial claim. The paper’s conclusions may not depend on it. It may state two separate claims as one.
Findingown dataThe planned project duration is 300 days and has a planned cost of 30,000 (x1000) monetary units.
“Under these conditions, the planned project duration is 300 days and has a planned cost of 30,000 (x1000) monetary units.”
Quote in the paperNot a substantial claimProbably not a substantial claim. The paper’s conclusions may not depend on it.
Findingnone givenThe contribution to total duration of identified risks that impact only cost is zero.
“As expected, the contribution to the total duration of the identified risks that impact only cost is zero.”
Quote in the paperNot a substantial claimIt may state two separate claims as one.
Findingown dataRisk R5 is the fourth most important risk in terms of impact on total project costs, even though it is initially identified as a risk that impacts project duration.
“It is noteworthy that risk R5 is the fourth most important risk in terms of impact on the total project costs, even though it is initially identified as a risk that impacts project duration.”
Quote in the paperNot a substantial claimIt may state two separate claims as one.
FindingreasoningWhen comparing traditional and proposed methods, the risk prioritisation results are entirely different and lead to a distinct ranking.
“When comparing both methods (traditional vs. our proposal), the risk prioritisation results are entirely different and lead to a distinct ranking.”
Quote in the paperNot a substantial claim- Rests on an assumption: The expert panel's identification of risks and their probability and impact estimates are valid and sufficiently accurate for quantitative prioritisation.
- Rests on an assumption: The impact of each risk can be quantified by simulating it individually and subtracting the baseline project duration and cost, without needing to model interactions among risks.
- Rests on an assumption: The chosen numerical ranges for probability and impact levels are appropriate for the case study project.
- Rests on an assumption: The case study project is suitable for illustrating the proposed method and its comparative results.
It may state two separate claims as one.
Findingnone givenRisks R10 to R15 do not impact project duration; if they materialise, their contribution to project duration is nil.
“We note that risks R10 to R15 do not impact project duration.If these risks materialise, their contribution to increase (or decrease, as the case may be) project duration is nil.”
Quote in the paperNot a substantial claimProbably not a substantial claim. The paper’s conclusions may not depend on it. It may state two separate claims as one.
Findingnone givenA VL duration impact is between 0 and 5 days, while the same range (VL) in cost is between 0 and 100 (x1000) monetary units.
“Thus a VL duration impact is between 0 and 5 days, while the same range (VL) in cost is between 0 and 100 (x1000) monetary units.”
Quote in the paperNot a substantial claim- Rests on an assumption: The chosen numerical ranges for probability and impact levels are appropriate for the case study project.
It may state two separate claims as one.
Findingown dataChoosing P80 instead of P95 yields a considerably lower total cost value of 3.03 × 10^7 monetary units and might completely ignore the impact of the risk on total project cost.
“Choosing a lower percentile, e.g.P80, means that the value we can obtain with this choice can be considerably lower (3.03 × 10 7 monetary units), and might completely ignore the impact of the risk on the total project cost.”
Quote in the paperSubstantial claimIt may state two separate claims as one.
Findingown dataThe experts' panel identifies 11 risks, of which nine have the potential to directly impact the project duration objective (R1 to R9), while six may impact the cost objective (R10 to R15).
“It identifies 11 risks, of which nine have the potential to directly impact the project duration objective (R1 to R9), while six may impact the cost objective (R10 to R15).”
Quote in the paperNot a substantial claim- Rests on an assumption: The expert panel's identification of risks and their probability and impact estimates are valid and sufficiently accurate for quantitative prioritisation.
Probably not a substantial claim. The paper may give no reason why it holds.
Interpretationnone givenThe reliability of the proposed method depends mainly on the accuracy of estimates, from identifying risks to modelling the probability and impact of each risk.
“Undoubtedly, the reliability of the proposed method depends mainly on the accuracy of estimates, which starts by identifying risks and ends with modelling the probability and impact of each risk.”
Quote in the paperNot a substantial claimProbably not a substantial claim. The paper’s conclusions may not depend on it. It may state two separate claims as one.
PremisecitationRisk matrices offer a well-defined structure for carrying out a methodical risk assessment, provide a practical justification for ranking and prioritising risks, visually and attractively inform stakeholders.
“Risk matrices offer a well-defined structure for carrying out a methodical risk assessment, provide a practical justification for ranking and prioritising risks, visually and attractively inform stakeholders, among other reasons (Talbot, 2014;Ball and Watt, 2013).”
Quote in the paperNot a substantial claim0 of 2 sources checked- cites Talbot, 2014
Couldn’t be matched to a paper in Crossref, so it can’t be checked.
- cites Ball and Watt, 2013 source
Probably not a substantial claim. The paper’s conclusions may not depend on it. The paper may give no reason why it holds.
Premisenone givenMCS have been recognised as outperforming other methods due to their accessibility, ease of use and simplicity.
“MCS have been recognised as outperforming other methods due to their accessibility, ease of use and simplicity.”
Quote in the paperNot a substantial claimIt may state two separate claims as one.
PremisecitationOntological uncertainty cannot be modelled and is not considered.
“Ontological uncertainty is not considered because it goes beyond the limits of human knowledge and cannot, therefore, be modelled ( Alleman et al. 2018a).”
Quote in the paperSubstantial claim0 of 1 sources checked- cites Alleman et al. 2018a
Couldn’t be matched to a paper in Crossref, so it can’t be checked.
Probably not a substantial claim. The paper’s conclusions may not depend on it.
PremisecitationRisk matrix use is frequent, partly due to its simple application and easy construction compared to alternative risk assessment methods.
“Risk matrix use is frequent, partly due to its simple application and easy construction compared to alternative risk assessment methods (Levine, 2012).”
Quote in the paperNot a substantial claim0 of 1 sources checked- cites Levine, 2012 source
Probably not a substantial claim. It may be too vague to check against evidence.
InterpretationreasoningThe proposed methodology will allow project managers to discover the most relevant project risks so they can focus their control efforts on managing those risks.
“The proposed methodology will allow project managers to discover the most relevant project risks so they can focus their control efforts on managing those risks.”
Quote in the paperNot a substantial claimIt may state two separate claims as one.
PremisecitationThe main criticism of the probability-impact matrix is its failure to consider complex interrelations between various risks and use precise estimates for probability and impact levels.
“The main criticism levelled at this methodology is its failure to consider the complex interrelations between various risks and use precise estimates for probability and impact levels.”
Quote in the paperSubstantial claimIt may state two separate claims as one.
InterpretationreasoningA methodology based on Monte Carlo Simulation avoids using the probability-impact matrix and allows prioritising project risks by evaluating them quantitatively and assessing the impact of risks on project duration and cost objectives.
“To answer this question, this paper proposes a methodology based on Monte Carlo Simulation that avoids using the probability-impact matrix and allows us to prioritise project risks by evaluating them quantitatively, and by assessing the impact of risks on project duration and the cost objectives.”
Quote in the paperSubstantial claimIt may state two separate claims as one.
Interpretationown dataThe proposed method provides not only the order of importance of risks but also the magnitude of their impact on the project, as absolute delay or cost overrun.
“We know not only the order of importance of risks (R3, R5, etc.) but also the magnitude of their impact on the project (which is the absolute delay caused by a risk in duration terms or what is the absolute cost overrun generated by a risk in cost terms).”
Quote in the paperSubstantial claimProbably not a substantial claim. The paper’s conclusions may not depend on it.
PremisecitationMCS allow the analysis of opportunities, uncertainties, and threats.
“MCS also allow the analysis of opportunities, uncertainties, and threats (Al-Duais and Al-Sharpi, 2023).”
Quote in the paperNot a substantial claim0 of 1 sources checked- cites Al-Duais and Al-Sharpi, 2023 source
Probably not a substantial claim.
PremisereasoningAll these approaches propose the probability-impact or risk matrix as a technique or tool for prioritising project risks.
“In turn, all these approaches propose the probability-impact or risk matrix as a technique or tool for prioritising project risks.”
Quote in the paperSubstantial claimProbably not a substantial claim. The paper’s conclusions may not depend on it.
PremisecitationQuantitative assessment involves performing a numerical analysis of the joint effect of the identified individual risks and additional sources of uncertainty on the overall project objectives.
“A quantitative assessment involves performing a numerical analysis of the joint effect of the identified individual risks and additional sources of uncertainty on the overall project objectives (Project Management Institute, 2017).”
Quote in the paperNot a substantial claim0 of 1 sources checked- cites Project Management Institute, 2017
Couldn’t be matched to a paper in Crossref, so it can’t be checked.
Probably not a substantial claim.
Premisenone givenIndividual project risks are ranked for further analyses or action with a qualitative assessment by evaluating the probability of their occurrence and potential impact.
“Individual project risks are ranked for further analyses or action with a qualitative assessment by evaluating the probability of their occurrence and potential impact.”
Quote in the paperSubstantial claimProbably not a substantial claim. It may state two separate claims as one.
Premisenone givenThe categorisation of severity of consequences is subjective in uncertainty situations, and assessment of probability, impact and risk ratings depends on subjective interpretations.
“Furthermore, the categorisation of the severity of consequences is subjective in uncertainty situations, and the assessment of probability, impact and risk ratings very much depends on subjective interpretations, which can lead to discrepancies between different users when assessing the same quantitative risks.”
Quote in the paperSubstantial claimProbably not a substantial claim. The paper may give no reason why it holds.
Interpretationnone givenThe results of simulations depend on the estimations of variables, including probability distributions and their parameters and risk aversion parameters.
“First of all, the results of simulations depend on the estimations of variables (probability distributions and their parameters, risk aversion parameters, etc.).”
Quote in the paperNot a substantial claimIt may state two separate claims as one.
PremisecitationRisk matrices can be inaccurate when comparing risks and sometimes assign similar ratings to risks with significant quantitative differences.
“The most critical problems identified in using risk matrices for strategic decision-making are that risk matrices can be inaccurate when comparing risks and they sometimes assign similar ratings to risks with significant quantitative differences.”
Quote in the paperSubstantial claimProbably not a substantial claim. The paper’s conclusions may not depend on it. The paper may give no reason why it holds.
Interpretationnone givenThe more project knowledge available, the more accurate the proposed model is for each uncertainty.
“The more project knowledge available, the more accurate the proposed model is for each uncertainty, regardless of it lying in the number of intervals, their magnitude or the type of probability function (PDF) chosen to model that risk.”
Quote in the paperNot a substantial claimProbably not a substantial claim. The paper’s conclusions may not depend on it.
PremisereasoningAll the aforementioned approaches contain a subprocess related to risk assessment.
“All the aforementioned approaches contain a subprocess related to risk assessment.”
Quote in the paperNot a substantial claimProbably not a substantial claim. It may be too vague to check against evidence. It may state two separate claims as one.
InterpretationreasoningThe proposed methodology overcomes many of the problems of previous methodologies but still has some limitations for future research.
“The methodology we propose in this paper overcomes many of the problems of previous methodologies, but still has some limitations for future research to deal with.”
Quote in the paperNot a substantial claimProbably not a substantial claim. The paper’s conclusions may not depend on it.
PremisecitationIn project management, the P80 percentile is sometimes chosen as the most appropriate percentile to measure risk appetite.
“However in project management, the P80 percentile is sometimes chosen as the most appropriate percentile to measure risk appetite (Kwon and Kang, 2019;Traynor and Mahmoodian, 2019;Lorance and Wendling, 2001).”
Quote in the paperNot a substantial claim0 of 3 sources checkedProbably not a substantial claim. The paper’s conclusions may not depend on it.
PremisecitationIn financial terms, it is traditional to choose a P95 percentile as risk appetite.
“In financial terms, it is traditional to choose a P95 percentile as risk appetite (Chen and Peng, 2018;Joukar and Nahmens, 2016;Gatti et al. 2007;Kuester et al. 2006;Giot and Laurent, 2003).”
Quote in the paperNot a substantial claim0 of 3 sources checkedIt may state two separate claims as one.
InterpretationreasoningThe methodology allows differentiation of critical risks according to their impact on project duration, which may differ if cost is taken as a priority objective.
“This allows the differentiation of critical risks according to their impact on project duration, which may differ if cost is taken as a priority objective.”
Quote in the paperSubstantial claimProbably not a substantial claim. The paper may give no reason why it holds.
Interpretationnone givenThe assumption that risks are independent is reasonable for most projects.
“This is a reasonable assumption for most projects.”
Quote in the paperNot a substantial claim- The authors state this as an assumption: Risks are independent.
Probably not a substantial claim. The paper may give no reason why it holds.
InterpretationreasoningThe contribution or effect of a particular risk can be estimated by including it in simulation and computing its impact on project cost and duration.
“Secondly, as risks are assumed to be independent, the contribution or effect of a particular risk can be estimated by including it in simulation and by computing its impact on project cost and duration.”
Quote in the paperNot a substantial claim- The authors state this as an assumption: Risks are independent.
Probably not a substantial claim. The paper’s conclusions may not depend on it. The paper may give no reason why it holds.
Interpretationnone givenIn some very complex projects, risks can be related to one another.
“In some very complex projects, however, risks can be related to one another.”
Quote in the paperNot a substantial claimIt may state two separate claims as one.
Interpretationnone givenThe probability-impact matrix presents particular problems and offers erroneous and contradictory results.
“However, we also study how this risk matrix presents particular problems and offers erroneous and contradictory results.”
Quote in the paperNot a substantial claim
The paper relies on this without support.
The expert panel's identification of risks and their probability and impact estimates are valid and sufficiently accurate for quantitative prioritisation.
“To do this, the experts' panel meets, analyses all the project documentation.Based on their personal experience with other similar projects and after consulting all the involved stakeholders, it provides a list of risks (see Table 3).”
“Having analysed the project and consulted the involved stakeholders, the team determines the project's different probability and impact levels (duration and cost).”
The paper relies on this without support.
The impact of each risk can be quantified by simulating it individually and subtracting the baseline project duration and cost, without needing to model interactions among risks.
“To do so, we subtract the original value of the total project expected duration and costs (excluding all risks) from the total duration and costs of the simulation in which we include the risk we wish to quantify (Eq.5).”
The paper relies on this without support.
The chosen numerical ranges for probability and impact levels are appropriate for the case study project.
“The estimation of these ranges depends on the project budget, the estimated project duration, and the team's experience in assigning the different numerical values to each range.”
The paper relies on this without support.
The case study project is suitable for illustrating the proposed method and its comparative results.
“In this section, we use a real-life project to illustrate how to apply the proposed method for quantitative risk prioritisation purposes.”
The authors state this as an assumption.
Risks are independent.
“Secondly, as risks are assumed to be independent, the contribution or effect of a particular risk can be estimated by including it in simulation and by computing its impact on project cost and duration.”
The authors state this as an assumption.
Project teams are sufficient experts to make rational estimations based on experience and previous knowledge.
“Methodologies for improving estimations are beyond the scope of this research; we assume project teams are sufficient experts to make rational estimationsbased on experience and previous knowledge.”
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
Each contradiction between two passages listed here was confirmed by an independent check.
A duration risk has zero reported cost impact
MinorTable 4 reports that R3 increases project duration by 26.330 days but has a cost impact of 0.000. This contradicts the conclusion that risks affecting project duration also affect total cost.
“| R3 | B | A 0.12 | 2 | 349.76 | 26.330 | 1 | 30,339.32 | 0.000 | 14 | |”
“The risks that impact project duration also impact the total cost target.”
Citations
Cites
What's Wrong with Risk Matrices?
Anthony (Tony)Cox, L. (2008) · Risk Analysis · doi:10.1111/j.1539-6924.2008.01030.x · Cited by 704
Value-at-Risk Prediction: A Comparison of Alternative Strategies
Kuester, K. (2005) · Journal of Financial Econometrics · doi:10.1093/jjfinec/nbj002 · Cited by 628
Recommendations on the use and design of risk matrices
Duijm, N. J. (2015) · Safety Science · doi:10.1016/j.ssci.2015.02.014 · Cited by 443
Value-at-Risk vs. Conditional Value-at-Risk in Risk Management and Optimization
Sarykalin, S., Serraino, G., & Uryasev, S. (2008) · doi:10.1287/educ.1080.0052 · Cited by 430
1,1‐Dicyano‐4‐[4‐(diethylamino)phenyl]buta‐1,3‐dienes: Structure–Property Relationships
Tancini, F., Wu, Y., Schweizer, W. B., Gisselbrecht, J., Boudon, C., Jarowski, P. D., Beels, M. T. R., Biaggio, I., & Diederich, F. (2012) · European Journal of Organic Chemistry · doi:10.1002/ejoc.201200111 · Cited by 408
Towards a better modelling and assessment of construction risk: Insights from a literature review
Taroun, A. (2014) · International Journal of Project Management · doi:10.1016/j.ijproman.2013.03.004 · Cited by 387
Markowski, A. S., & Mannan, M. S. (2008) · Journal of Hazardous Materials · doi:10.1016/j.jhazmat.2008.03.055 · Cited by 306
Market risk in commodity markets: a VaR approach
Giot, P., & Laurent, S. (2003) · Energy Economics · doi:10.1016/s0140-9883(03)00052-5 · Cited by 263
Some extensions on risk matrix approach
Ni, H., Chen, A., & Chen, N. (2010) · Safety Science · doi:10.1016/j.ssci.2010.04.005 · Cited by 242
Project risk analysis and management—PRAM the generic process
Chapman, C. B. (1997) · International Journal of Project Management · doi:10.1016/s0263-7863(96)00079-8 · Cited by 217
Some Limitations of Qualitative Risk Rating Systems
Cox, L. A., Babayev, D. A., & Huber, W. (2005) · Risk Analysis · doi:10.1111/j.1539-6924.2005.00615.x · Cited by 205
Epistemic uncertainty quantification techniques including evidence theory for large-scale structures
Bae, H., Grandhi, R. V., & Canfield, R. A. (2004) · Computers & Structures · doi:10.1016/j.compstruc.2004.03.014 · Cited by 198
A new approach for project control under uncertainty. Going back to the basics
Acebes, F., Pajares, J., Galán, J. M., & López-Paredes, A. (2014) · International Journal of Project Management · doi:10.1016/j.ijproman.2013.08.003 · Cited by 165
Self-citationFurther Thoughts on the Utility of Risk Matrices
Ball, D. J., & Watt, J. (2013) · Risk Analysis · doi:10.1111/risa.12057 · Cited by 152
The construction dust-induced occupational health risk using Monte-Carlo simulation
Tong, R., Cheng, M., Zhang, L., Liu, M., Yang, X., Li, X., & Yin, W. (2018) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2018.02.286 · Cited by 151
On the assessment of uncertainty in risk diagrams
Goerlandt, F., & Reniers, G. (2016) · Safety Science · doi:10.1016/j.ssci.2015.12.001 · Cited by 148
Assessing and managing important risks
Ward, S. (1999) · International Journal of Project Management · doi:10.1016/s0263-7863(98)00051-9 · Cited by 138
Qazi, A. J., Shamayleh, A., El-Sayegh, S. M., & Formaneck, S. D. (2020) · Sustainable Cities and Society · doi:10.1016/j.scs.2020.102576 · Cited by 125
Stochastic earned value analysis using Monte Carlo simulation and statistical learning techniques
Acebes, F., Pereda, M., Poza, D., Pajares, J., & Galán, J. M. (2015) · International Journal of Project Management · doi:10.1016/j.ijproman.2015.06.012 · Cited by 120
Self-citationSensitivity analysis in conjunction with evidence theory representations of epistemic uncertainty
Helton, J. C., Johnson, J. D., Oberkampf, W. L., & Sallaberry, C. J. (2006) · Reliability Engineering & System Safety · doi:10.1016/j.ress.2005.11.055 · Cited by 112
Improving risk matrices: the advantages of logarithmically scaled axes
Levine, E. S. (2012) · Journal of Risk Research · doi:10.1080/13669877.2011.634514 · Cited by 100
From Risk Matrices to Risk Networks in Construction Projects
Qazi, A. J., & Dikmen, İ. (2019) · IEEE Transactions on Engineering Management · doi:10.1109/tem.2019.2907787 · Cited by 100
The Risk of Using Risk Matrices
Thomas, P. J., Bratvold, R. B., & Bickel, J. E. (2014) · SPE Economics & Management · doi:10.2118/166269-pa · Cited by 84
On the origin of PCDS – (Probability consequence diagrams)
Ale, B. J. M., Burnap, P., & Slater, D. (2014) · Safety Science · doi:10.1016/j.ssci.2014.09.003 · Cited by 80
Risk Matrix Integrating Risk Attitudes Based on Utility Theory
Ruan, X., Yin, Z., & Frangopol, D. M. (2015) · Risk Analysis · doi:10.1111/risa.12400 · Cited by 75
How to Design Rating Schemes of Risk Matrices: A Sequential Updating Approach
Li, J., Bao, C., & Wu, D. (2017) · Risk Analysis · doi:10.1111/risa.12810 · Cited by 75
Measuring Value‐at‐Risk in Project Finance Transactions
Gatti, S., Rigamonti, A., Saita, F., & Senati, M. (2007) · European Financial Management · doi:10.1111/j.1468-036x.2006.00288.x · Cited by 69
Engineering and contracting projects: A value at risk based approach to portfolio balancing
Caron, F., Fumagalli, M., & Rigamonti, A. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2007.01.016 · Cited by 63
A unique Markov chain Monte Carlo method for forecasting wind power utilizing time series model
Al-Duais, F. S., & Al-Sharpi, R. S. (2023) · Alexandria Engineering Journal · doi:10.1016/j.aej.2023.05.019 · Cited by 63
Management of construction cost contingency covering upside and downside risks
Eldosouky, I. A., Ibrahim, A. H., & Mohammed, H. E.-D. H. (2014) · Alexandria Engineering Journal · doi:10.1016/j.aej.2014.09.008 · Cited by 62
A new approach for quantitative risk analysis
Creemers, S., Demeulemeester, E., & de Vonder, S. V. (2013) · Annals of Operations Research · doi:10.1007/s10479-013-1355-y · Cited by 55
Logarithmic scales in ecological data presentation may cause misinterpretation
Menge, D. N. L., MacPherson, A. C., Bytnerowicz, T. A., Quebbeman, A. W., Schwartz, N. B., Taylor, B. N., & Wolf, A. A. (2018) · Nature Ecology & Evolution · doi:10.1038/s41559-018-0610-7 · Cited by 55
Lemmens, S. M. P., van Balen, V. A. L., Röselaers, Y. C. M., Scheepers, H. C. J., & Spaanderman, M. E. A. (2022) · BMC Health Services Research · doi:10.1186/s12913-022-07484-7 · Cited by 52
Kwon, H., & Kang, C. W. (2019) · Project Management Journal · doi:10.1177/8756972818810963 · Cited by 50
Structural safety–issues and progress
Elms, D. G. (2004) · Progress in Structural Engineering and Materials · doi:10.1002/pse.176 · Cited by 47
The risk matrix: uncertain results?
Peace, C. (2017) · Policy and Practice in Health and Safety · doi:10.1080/14773996.2017.1348571 · Cited by 47
Impact of aleatoric, stochastic and epistemic uncertainties on project cost contingency reserves
Curto, D., Acebes, F., González-Varona, J. M., & Poza, D. (2022) · International Journal of Production Economics · doi:10.1016/j.ijpe.2022.108626 · Cited by 47
Self-citationCan Public Health Risk Assessment Using Risk Matrices Be Misleading?
Vatanpour, S., Hrudey, S., & Dinu, I. (2015) · International Journal of Environmental Research and Public Health · doi:10.3390/ijerph120809575 · Cited by 46
Sutherland, H. E. A., Recchia, G. L., Dryhurst, S., & Freeman, A. L. J. (2021) · Risk Analysis · doi:10.1111/risa.13822 · Cited by 44
Mean-conditional value at risk model for the stochastic project scheduling problem
Rezaei, F., Najafi, A. A., & Ramezanian, R. (2020) · Computers & Industrial Engineering · doi:10.1016/j.cie.2020.106356 · Cited by 43
Appropriate budget contingency determination for construction projects: State-of-the-art
Ammar, T., Abdel-Monem, M. S., & El-Dash, K. M. (2023) · Alexandria Engineering Journal · doi:10.1016/j.aej.2023.07.035 · Cited by 43
Risk Assessment in Bridge Construction Projects in Iran Using Monte Carlo Simulation Technique
Naderpour, H., Kheyroddin, A., & Mortazavi, S. (2019) · Practice Periodical on Structural Design and Construction · doi:10.1061/(asce)sc.1943-5576.0000450 · Cited by 42
Risk assessment of construction projects using Monte Carlo simulation
Qazi, A., & Simsekler, M. C. E. (2021) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-03-2020-0097 · Cited by 41
Votto, R. G., Ho, L. L., & Berssaneti, F. T. (2020) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001765 · Cited by 39
Time and cost contingency management using Monte Carlo simulation
Traynor, B. A., & Mahmoodian, M. (2019) · Australian Journal of Civil Engineering · doi:10.1080/14488353.2019.1606499 · Cited by 37
Data Analytics for Engineering and Construction Project Risk Management
Damnjanovic, I. D., & Reinschmidt, K. F. (2019) · Risk, systems and decisions · doi:10.1007/978-3-030-14251-3 · Cited by 37
Frank, M. V. (1999) · Reliability Engineering & System Safety · doi:10.1016/s0951-8320(99)00002-2 · Cited by 36
A TOPSIS—Risk Matrix and Monte Carlo Expert System for Risk Assessment in Engineering Projects
Koulinas, G. K., Demesouka, O. E., Sidas, K. A., & Koulouriotis, D. E. (2021) · Sustainability · doi:10.3390/su132011277 · Cited by 35
Risk management standards for project management
Řeháček, P. (2017) · International Journal of ADVANCED AND APPLIED SCIENCES · doi:10.21833/ijaas.2017.06.001 · Cited by 26
Problems with Risk Matrices Using Ordinal Scales
Krisper, M. (2021) · arXiv · doi:10.48550/arxiv.2103.05440 · Cited by 26
Ali Elfarra, M., & Kaya, M. (2021) · Alexandria Engineering Journal · doi:10.1016/j.aej.2021.02.027 · Cited by 25
Votto, R. G., Ho, L. L., & Berssaneti, F. T. (2020) · Computers & Industrial Engineering · doi:10.1016/j.cie.2020.106691 · Cited by 19
Proto, R., Recchia, G. L., Dryhurst, S., & Freeman, A. L. J. (2023) · Risk Analysis · doi:10.1111/risa.14091 · Cited by 16
The Data-Driven Project Manager
Vanhoucke, M. (2018) · doi:10.1007/978-1-4842-3498-3 · Cited by 11
Introducing an Entrepreneurial Project Management Model
Mbiru, J., Wickham, & Ayentimi, D. T. (2020) · UTAS Research Repository · doi:10.19255/jmpm02210 · Cited by 8
Estimation of the Escalation Factor in Construction Projects Using Value at Risk
Joukar, A., & Nahmens, I. (2016) · Construction Research Congress 2016 · doi:10.1061/9780784479827.234 · Cited by 6
A Matlab-Based Educational Tool for Quantitative Risk Analysis
Acebes, F., De Antón, J., Villafáñez, F., & Poza, D. (2023) · Lecture Notes on Data Engineering and Communications Technologies · doi:10.1007/978-3-031-27915-7_8 · Cited by 6
Self-citationValue-at-Risk Model Analysis of Taiwanese High-Tech Facility Construction
Chen, P.-H., & Peng, T.-T. (2017) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000585 · Cited by 5
Análisis cuantitativo de riesgos utilizando "MCSimulRisk" como herramienta didáctica
Acebes Senovilla, F., Curto Lorenzo, D., De Antón Heredero, J., & Villafáñez Cardeñoso, F. (2024) · Dirección y Organización · doi:10.37610/dyo.v0i82.662 · Cited by 5
Self-citationQuantitative Analysis of Project Risks
Caron, F. (2013) · SpringerBriefs in applied sciences and technology · doi:10.1007/978-88-470-5244-4_14 · Cited by 3
Flagged first, then by citations
Research works printed but not linked: 11
- Alleman GB, Coonce TJ, Price RA (2018a) Increasing the probability of program succes with continuous risk management. Coll Perform Manag, Meas N. 4:27–46
- Alleman GB, Coonce TJ, Price RA (2018b) What is Risk? Meas N. 01(1):25–34
- Chapman CB, Ward S (2003) Project Risk Management: Processes, Techniques and Insights (John Wiley and Sons, Ed.; 2nd ed.). Chichester
- European Commission. (2023) Project Management Methodology. Guide 3.1 (European Union, Ed.). Publications Office of the European Union
- International Organization for Standardization. (2018). ISO 31000:2018 Risk management – Guidelines (Vol. 2)
- Kerzner H (2022) Project Management. A Systems Approach to Planning, Scheduling, and Controlling (Inc. John Wiley & Sons, Ed.; 13th Editi)
- Lorance RB, Wendling RV (2001) Basic techniques for analyzing and presentation of cost risk analysis. Cost Eng 43(6):25–31
- Project Management Institute. (2017) A Guide to the Project Management Body of Knowledge: PMBoK(R) Guide. Sixth Edition (6th ed.). Project Management Institute Inc
- Project Management Institute. (2021) A Guide to the Project Management Body of Knowledge: PMBoK(R) Guide. Seventh Edition (7th ed.). Project Management Institute, Inc
- Simon P, Hillson D, Newland K (1997) PRAM Project Risk Analysis and Management Guide (P. Simon, D. Hillson, & K. Newland, Eds.). Association for Project Management
- Vose, D (2008). Risk Analysis: a Quantitative Guide (3rd ed.). Wiley
Cited by
Sorted by citations
Tian, K., Zhu, Z., Mbachu, J., Moorhead, M., & Ghanbaripour, A. N. (2025) · Journal of Risk Research · doi:10.1080/13669877.2025.2512080 · Cited by 23
Unlocking the potential of project portfolio: value-oriented interactive risk management
Bai, L., Zhang, L., Zhang, L., Shao, K., & Luo, X. (2025) · Humanities and Social Sciences Communications · doi:10.1057/s41599-025-05296-8 · Cited by 21
Xu, Y., Lü, H., Yağcı, A. L., Zhu, Y., Liu, D., Wang, Q., Xu, H., Pan, Y., & Su, J. (2024) · Agricultural Water Management · doi:10.1016/j.agwat.2024.109122 · Cited by 18
Tansel, B. (2025) · International Journal of Disaster Risk Reduction · doi:10.1016/j.ijdrr.2025.105883 · Cited by 11
Risk Management Practices in the Purchasing System of an Automotive Company
Tereso, A., Santos, C. A., & Faria, J. (2025) · Systems · doi:10.3390/systems13060444 · Cited by 5
System dynamics analysis of development risks in emerging eVTOL aircraft
Wu, Y., Zhang, S., Ni, X., & Li, X. (2025) · Expert Systems with Applications · doi:10.1016/j.eswa.2025.130363 · Cited by 4
Mitigating Engineering Phase Delays in EPC Projects: Monte Carlo Simulation Method with Project XYZ
Sihombing, L. B., & Prabowo, B. N. (2025) · ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems Part A Civil Engineering · doi:10.1061/ajrua6.rueng-1390 · Cited by 3
Research progress and prospects of risk assessment methods for oil and gas development
Zhang, X., Lin, Y., Lai, F., & Wang, H. (2025) · Geoenergy Science and Engineering · doi:10.1016/j.geoen.2025.213992 · Cited by 3
Zeriouh, K., Amara, M., Zeriouh, S., & Amara, S. (2024) · Journal of corporate governance insurance and risk management · doi:10.56578/jcgirm110402 · Cited by 2
Comparing Traditional and Graphical Risk Matrices: A Case Study in Healthcare
Kutej, A., Raß, S., & Alexandrowicz, R. W. (2025) · Risk Analysis · doi:10.1111/risa.70104 · Cited by 2
Timalsina, S., Zhang, C., & Pal, U. K. (2026) · Journal of Loss Prevention in the Process Industries · doi:10.1016/j.jlp.2026.105921 · Cited by 2
Analysis of risks affecting the operation and maintenance of wastewater treatment plant systems
Sidky, M. B., Issa, U. H., Hassan, M. S., & ALI, M. G. S. (2026) · Journal of Engineering and Applied Science · doi:10.1186/s44147-025-00786-7 · Cited by 2
Managing the unpredictable: strategies for effective fashion product development
Parker-Strak, R., Studd, R., & Doyle, S. A. (2026) · Journal of Fashion Marketing and Management · doi:10.1108/jfmm-11-2024-0450 · Cited by 2
Banera, J., Maj, M., & Musa, A. H. (2025) · Buildings · doi:10.3390/buildings15132254 · Cited by 1
Quantitative assessment of RAM driven risk matrix of offset printing machine
Pal, A. K., & Kar, A. (2025) · Maintenance Reliability and Condition Monitoring · doi:10.21595/marc.2025.25026 · Cited by 1
Methods for Minimizing Risks in Investments in High-Tech Projects
Azatyan, M. (2025) · Universal Library of business and economics. · doi:10.70315/uloap.ulbec.2025.0203006 · Cited by 1
Chadee, A. A., Seecharan, L. S., & Martin, H. G. (2025) · Sustainability · doi:10.3390/su17188203 · Cited by 1
Occurrence and Hazard Ranking of Microplastics in Owabi Headworks in the Ashanti Region of Ghana
Kyere, O. A., Alhassan, M., Kwaansa‐Ansah, E. E., & Ababio, B. A. (2025) · Water Air & Soil Pollution · doi:10.1007/s11270-025-08810-5 · Cited by 1
Tyozenda, A. J., & Tsetim, J. T. (2025) · Risk Management Magazine · doi:10.47473/2020rmm0162 · Cited by 1
Analysing Financial Risks Inherent in the Iraqi Construction Sector Using Probability–Impact Matrix
Dishar, M. M. (2026) · Journal of Engineering · doi:10.31026/j.eng.2026.01.08 · Cited by 1
Adrinata, R. (2026) · International Transfer Pricing Journal · doi:10.59403/36pg483 · Cited by 1
Cost Risk Factors in Construction Projects: A Contractor’s Perspective
Belihu, K. T., Woldesenbet, A. K., Shiferaw, A. T., Wubet, W. A., Yehualaw, M. D., & Taffese, W. Z. (2026) · Information · doi:10.3390/info17030226 · Cited by 1
Taibi, Y., Müller, A., Bellingrath, S., Neuhaus, C. A., & Metzler, Y. A. (2026) · Frontiers in Psychology · doi:10.3389/fpsyg.2026.1753317 · Cited by 1
Quantitative risk prioritization. A new risk-based approach to prioritize project risks
Acebes, F., González-Varona, J. M., López‐Paredes, A., & Pajares, J. (2026) · Annals of Operations Research · doi:10.1007/s10479-026-07252-4 · Cited by 1
Self-citationYungratog, S., Goerlandt, F., Punurai, W., Kim, H., Liu, Y., & Thammaboosadee, S. (2026) · IEEE Access · doi:10.1109/access.2026.3698084 · Cited by 1
Adoption of Building Information Modeling (BIM) to Improve Urban Construction in Bangladesh
Jany, M. R., Karim, R., Shirin, M. S., Hossain, M. S., Jami, R. H., & Uddin, M. M. (2026) · American Journal of Civil Engineering and Constructions · doi:10.54536/ajcec.v2i2.7679 · Cited by 1
Zagia, F., Kajewski, S. L., Omrani, S., Motamedisedeh, O., & Rose, T. M. (2026) · Buildings · doi:10.3390/buildings16163209 · Cited by 1
Thai-Phuong, T., Phuong, N. P., & Son, L. N. (2025) · International Journal of Basic and Applied Sciences · doi:10.14419/vq93sy72 · Cited by 1
Quantifying Values: The Problem of AI RiskPreprint
Sass, R., Novelli, C., & Zio, E. (2026) · SSRN Electronic Journal · doi:10.2139/ssrn.6140546 · Cited by 1
Resilience in Service Supply Chains
Pereira, C. R., & Yurt, Ö. (2024) · Springer eBooks · doi:10.1007/978-3-031-68244-5_4
Proposed Approach to Assessing the Marginal Risks of Alcoholic Beverages in the Context Of SDG
Matevosyan, A. V., Grigoryan, A. Z., Matevosyan, M. H., Israyelyan, S., Harutyunyan, L., & Sughyan, N. (2025) · Journal of Lifestyle and SDGs Review · doi:10.47172/2965-730x.sdgsreview.v5.n03.pe05152
Bahri, A. S., Sugiarto, S., Hendratono, T., Palupi, S., Amelia, R., & Jason, J. (2025) · Journal of Tourism Sustainability · doi:10.35313/jtospolban.v5i2.159
Rahmawati, D. N., Suryadi, E., Hadijah, H. S., & Rasto, R. (2025) · Dinasti International Journal of Economics Finance & Accounting · doi:10.38035/dijefa.v6i5.5272
Molotsi, T. K., & Mokgolo, M. M. (2025) · doi:10.25159/unisarxiv/000158.v1
Chernenko, Y., Semko, I., & Mysnyk, L. (2025) · Актуальні питання економічних наук · doi:10.5281/zenodo.15507279
Cholakkal, B. B. (2025) · Osuva (University of Vaasa)
Ihsan, T., Hendri, A. K., Silvia, S., & Maulidya, A. (2025) · J TI UNDIP JURNAL TEKNIK INDUSTRI · doi:10.14710/jati.20.3.186-196
Svanström, V. (2025) · Digitala vetenskapliga arkivet (Diva) (Karlstad University)
Вадимівна, К. Є. (2024) · eKNUTSHIR
Dourado, M. L., Silva, R. A. E., Castro, M. C., Peterka, C. R. L., Kluge, C. R., de Castro, D. P., & Lima, J. B. P. (2026) · Memórias do Instituto Oswaldo Cruz · doi:10.1590/0074-02760250152
Prayogo, Y. D. N., & Pramesti, N. P. (2026) · Civil and Sustainable Urban Engineering · doi:10.53623/csue.v6i1.938
Ontology-Driven Dynamic Probabilistic Time-Risk Intelligence for In-situ PC ProductionPreprint
Lim, J., & Kim, S. (2026) · SSRN Electronic Journal · doi:10.2139/ssrn.6411322
Yanque, R. I. E., & Pacompia, A. P. (2025) · Universidad Peruana de Ciencias Aplicadas (UPC) · doi:10.19083/tesis/686777
Gyulasaryan, M. R., Matevosyan, A. V., Matevosyan, M. H., & Grigoryan, A. Z. (2026) · Studies in computational intelligence · doi:10.1007/978-3-032-13565-0_10
Laos, L. S. C., Inga, C. A. L., & Pacoticona, Y. A. P. (2025) · Repositorio Académico UPC (Universidad Peruana de Ciencias Aplicadas)
Jones, L. A. (2026) · IGI Global eBooks · doi:10.4018/979-8-2600-1021-1.ch001
Frantzova, A., Ivanov, P., Dobrev, N., Berov, B., & Кrastanov, M. (2026) · Geologica Balcanica · doi:10.52321/geolbalc.55.1.13
Tseng, W., Huang, J., Kuo, Y.-C., Lo, S.-C., Huang, A.-C., & Tseng, Y. (2026) · Climate Services · doi:10.1016/j.cliser.2026.100658
Predictive Risk Assessment and Automated Mitigation Planning
Arora, U., & Khurana, R. (2026) · Advances in computational intelligence and robotics book series · doi:10.4018/979-8-2600-1756-2.ch008
Making AI Risk Assessment More Objective: Addressing Sociotechnical Challenges
Murphy, M., & Matthews, V. (2026) · Proceedings of IASEAI Conference · doi:10.1609/iaseai.v2i1.43043
Iniesta, M. B., & Lostumbo, M. A. (2026) · Lecture notes in computer science · doi:10.1007/978-3-032-21811-7_21
Damayanti, I., Riptanti, E. W., & Handayani, S. M. (2026) · International Journal of Research and Review · doi:10.52403/ijrr.20260620
Estudio de los factores higiénicos biológicos en recicladores de Oaxaca
Cruz-Hernández, H. D., & Beltrán, E. D. (2026) · Medicina y Seguridad del Trabajo · doi:10.4321/s0465-546x2026000200005
Victor, E. C., & Sanusi, F. A. (2026) · Computer and Information Science · doi:10.5539/cis.v19n2p60
Escalation instability in probability-impact matrices: evidence from capital projects
Meyer, W. G. (2026) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-02-2026-0086
Sanusi, F. A., Victor, E. C., Okorie, G. C., & Boye, F. O. (2026) · International Journal Of Engineering And Computer Science · doi:10.18535/ijecs.v15i07.5555
Iran’s Development of Criminal Foreign Policy Capabilities in the United States From 2013–2020
Harr, S. J. (2026) · Digital Commons (Liberty University)
A Risk-Based Conceptual Framework for Well Design Decision-Making in Data-Poor Marginal Fields
Omotayo, B. G., Kolade, O., Akande, O. S., Adeleke, V. A., Babatunde, O. M., Otuneye, C. D., Ojo, S. D., & Oladunjoye, O. V. (2026) · SPE Nigeria Annual International Conference and Exhibition · doi:10.2118/235179-ms
Mitigating Schedule and Cost Overrun Risks in EPC Projects Using Monte Carlo Simulation in Ikeja
Adeodu, A. O., Ojo, T., & Ogunbiyi, M. E. (2026) · ABUAD Journal of Engineering Research and Development (AJERD) · doi:10.53982/ajerd.2026.0902.19-j
Caro, J. D. P., & Contreras, H. F. G. (2026) · Biblioteca Digital Minerva EAN
Viivästymisriskien tunnistaminen ja käsittely ohjelmistokehityksessä
Kauranen, E. (2026) · Aaltodoc (Aalto University)
Agile Risk Management Model Based on the Internet of Things Using a System Dynamics Approach
Far, J. B., Dehnavi, H. D., Sadeghian, A., & Rabbani, M. (2026) · Digital Transformation and Administration Innovation · doi:10.61838/dtai.261
AI-Driven Risk Management Optimization for Economic Resilience and Crisis Recovery
Vetriselvi, G., Kumar, V. V., Ghamande, M. V., Vijayakumar, A., Nandal, N., Thulasimani, T., & Bhoopathy, V. (2026) · Advances in computational intelligence and robotics book series · doi:10.4018/979-8-3373-7267-9.ch005
Bermeo, E. F. M. (2026) · Revista Venezolana de Gerencia · doi:10.52080/rvgluz.31.116.19
BAGIO, L. (2026) · DSpace (Federal University of Santa Catarina)
Gestão de Riscos em Sistemas de Informação: estudo aplicado ao HUC
Santos, M. O. (2025) · Portuguese National Funding Agency for Science, Research and Technology (RCAAP Project by FCT)
Овчинская, Я. И. (2026) · Vestnik of the Plekhanov Russian University of Economics · doi:10.21686/2413-2829-2026-5-225-235
Setiyawan, B., & Nursyamsiah, S. (2026) · Indonesian Interdisciplinary Journal of Sharia Economics (IIJSE) · doi:10.31538/iijse.v9i2.8619
Aulia, N. N. (2026) · UMM Institutional Repository (University of Maine at Machias)
MIGRASI SISTEM IT INTERNAL PT. WARSOON MAJU BERSAMA DARI INFRASTRUKTUR ON-PREMISE KE CLOUD COMPUTING
Rizqi, M., Irawan, A., Hidayat, W., Najmi, R. A., Laksana, A. S., & Nursodiq, A. (2025) · OKTAL : Jurnal Ilmu Komputer dan Sains
Позняк, Р. В. (2026) · Scientific Notes of Lviv University of Business and Law · doi:10.66556/2663-0117.51.pozniak-r
Gutierrez, G., Ali, G. G., & Tarawneh, C. M. (2026) · Journal of Infrastructure Systems · doi:10.1061/jitse4.iseng-3018
Mishra, B. A. R. (2026) · International Journal of Advanced Research in Science Communication and Technology · doi:10.48175/ijarsct-40547
Metadata
- Authors
- Acebes, F., González-Varona, J. M., López-Paredes, A., & Pajares, J.
- Affiliations
- Universidad de Valladolid (ES)
- Universidad de Málaga (ES)
- Corresponding author
- Acebes, F.
- Venue
- Humanities and Social Sciences Communications
- Published
- 2024-05-24
- Volume
- 11
- Issue
- 1
- ISSN
- 2055-1045 (ISSN-L)
- 2662-9992
- OpenAlex
- W4398764709
- Cited by
- 74
- References
- 60
- Citations by year
- 2026: 42 · 2025: 27 · 2024: 5
- FWCI
- 16.67
- Type
- journal article
- Language
- en
- Open access
- gold
- doi.org
- Locations
- Humanities and Social Sciences Communications (publishedVersion, cc-by)
- Hispana (publishedVersion, cc-by-nc-nd)
- RePEc: Research Papers in Economics (submittedVersion)
- arXiv (Cornell University) (submittedVersion, cc-by-nc-nd)
- Repositorio Institucional de la Universidad de Málaga (University of Málaga) (submittedVersion, cc-by)
- University of Valladolid Documentary Repository (University of Valladolid) (submittedVersion, cc-by-nc-nd)
- DOAJ (DOAJ: Directory of Open Access Journals) (submittedVersion, cc-by-sa)
- arXiv (Cornell University)
- Funders
- European Regional Development Fund
- Topics
- Social Sciences › Decision Sciences › Management Science and Operations Research › Construction Project Management and Performance
- Social Sciences › Economics, Econometrics and Finance › Finance › Capital Investment and Risk Analysis
- Social Sciences › Decision Sciences › Management Science and Operations Research › Resource-Constrained Project Scheduling
- Keywords
- project risk management, risk prioritization, risk matrix, Monte Carlo simulation, project duration, project cost, risk impact assessment, critical risks
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
A language model drew the claims from the paper on 2026-11-07, under version 3 of the claim definition (model deepseek-v4.1-flash, prompt extract-v3).
A second model labelled each claim on 2026-11-07 (model jev-1.13-20260917, definition revision gold-guideline-v0.2).
Cited sources are checked with a language model’s help (gpt-6-sol).
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review