Urban Infrastructure Development Works in India: Delay and Difficulties in Implementation with Reference to a Water Supply Project
Open accessOverview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Claims other papers make about this one
Each is checked against this paper’s own text: does it say what the citing paper says it does?
In the citing paper
“Table 1 identifies all the issues involved with public sector projects after investigating various projects/samples from Bangladesh, Denmark, Germany, Hong Kong, India, Malaysia, Myanmar, Nigeria, the Netherlands, the OECD, Pakistan, the Philippines, Singapore, South Korea, Sri Lanka, Taiwan, Thailand, and Vietnam [9,27,34-41].”
From Blockchain Technology: Potential Applications for Public Sector E-Procurement and Project Management (2022) · cites this paper as [27]
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Still being checked.
Cited by
Critical causes of time overrun in Indian construction projects and mitigation measures
Prasad, K. V., Vasugi, V., Venkatesan, R., & Bhat, N. S. (2018) · International Journal of Construction Education and Research · doi:10.1080/15578771.2018.1499569 · Cited by 84
Blockchain Technology: Potential Applications for Public Sector E-Procurement and Project Management
Khalfan, M., Azizi, N., Haass, O., Maqsood, T., & Ahmed, I. (2022) · Sustainability · doi:10.3390/su14105791 · Cited by 57
“[27] pointed out that project success focuses on the overall objectives of the project, while project management success focuses on scope of the projects, including the cost, time, and quality.”
BackgroundCauses of Delay in Power Transmission Projects: An Empirical Study
Pall, G. K., Bridge, A., Gray, J., & Skitmore, M. (2019) · Energies · doi:10.3390/en13010017 · Cited by 48
Technological Solutions for Water Sustainability: Challenges and Prospects
Philip, L., Pradeep, T., Bhallamudi, S. M., Bhallamudi, S. M., Philip, L., Balkhi, S. A. A., Karki, B. K., Philip, L., Maliyekkal, S. M., Vijayanandan, A., et al. (2023) · IWA Publishing eBooks · doi:10.2166/9781789063714 · Cited by 30
Critical delay factors in power transmission projects: a structural equation modeling approach
Pall, G. K., Bridge, A., Washington, S. P., Gray, J., & Skitmore, M. (2019) · International Journal of Construction Management · doi:10.1080/15623599.2019.1686835 · Cited by 11
Metadata
- Authors
- Aditya, A. K., Douglass, D. A., & Bhattacharya, M.
- Affiliations
- Government of West Bengal (IN)
- Corresponding author
- Aditya, A. K.
- Venue
- Journal of The Institution of Engineers (India): Series A
- Published
- 2017-09
- Volume
- 98
- Issue
- 3
- Pages
- 349-354
- ISSN
- 2250-2149 (ISSN-L)
- 2250-2157
- OpenAlex
- W2753412015
- Cited by
- 8
- References
- 0
- Citations by year
- 2023: 3 · 2022: 1 · 2021: 1 · 2019: 2 · 2018: 1
- FWCI
- 0.73
- Type
- journal article
- Language
- en
- Open access
- bronze
- doi.org
- Locations
- Journal of The Institution of Engineers (India) Series A (publishedVersion)
- Topics
- Social Sciences › Decision Sciences › Management Science and Operations Research › Construction Project Management and Performance
- Social Sciences › Political Science and International Relations › Water Governance and Infrastructure
- Social Sciences › Business, Management and Accounting › Strategy and Management › Public-Private Partnership Projects
- Keywords
- urban infrastructure development, project delays, water supply projects, cost and schedule overruns, stakeholder coordination
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
How to cite
Cite CoChat for the checks on this page, and the paper for its own findings.
- This page
- CoChat. (2026). Citation check: Urban Infrastructure Development Works in India: Delay and Difficulties in Implementation with Reference to a Water Supply Project. https://app.cochat.ai/papers/10.1007/s40030-017-0214-2
- The paper
- Aditya, A. K., Douglass, D. A., & Bhattacharya, M. (2017). Urban Infrastructure Development Works in India: Delay and Difficulties in Implementation with Reference to a Water Supply Project. Journal of The Institution of Engineers (India): Series A. https://doi.org/10.1007/s40030-017-0214-2
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.