Construction delays in privately funded large building projects in Bangladesh
Open accessAbstract
Schedule delay in building construction projects is considered as one of the main reasons for project failure in developing countries. Likewise, privately funded building construction projects in Bangladesh have been suffering due to schedule delays. This study investigated the main causes of delay in privately funded large building projects in Bangladesh. To determine the causes of delay, a structured interview with 70 respondents was conducted with project owners, consultants, and contractors. Using the importance index analysis method, the study identified the critical causes of delays. The ten most important causes are: (1) lack of experienced construction managers; (2) lowest bidder selection; (3) owners’ fund shortage; (4) lack of proper management by the owners; (5) improper planning and scheduling; (6) lack of skilled workers; (7) inaccurate time and cost estimation by the contractors; (8) site constraints; (9) improper progress monitoring and cost control; and (10) contractors’ cash flow problem during construction. Furthermore, Kruskal–Wallis test indicates that there is no significant variation among the three groups of respondents, i.e., owners, consultants, and contractors. The finding of this study is significant for identifying the most important causes of delay in large building projects. It also identifies the responsibility of major stakeholders (i.e., owners, consultants, and contractors) in causing a schedule delay, which helps them to find mitigation measures for the potential delays of upcoming projects in advance. Although this study provides the insight into the causes of delay in privately funded large building projects in Bangladesh, it is also significant for other similar developing countries.
Overview
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
Claims other papers make about this one
Each is checked against this paper’s own text: does it say what the citing paper says it does?
In the citing paper
“Table 1 identifies all the issues involved with public sector projects after investigating various projects/samples from Bangladesh, Denmark, Germany, Hong Kong, India, Malaysia, Myanmar, Nigeria, the Netherlands, the OECD, Pakistan, the Philippines, Singapore, South Korea, Sri Lanka, Taiwan, Thailand, and Vietnam [9,27,34-41].”
From Blockchain Technology: Potential Applications for Public Sector E-Procurement and Project Management (2022) · cites this paper as [36]
In the citing paper
“It has been found that awarding the contract to the lowest bidder is one of the main causes for delaying projects [32,36,54].”
From Blockchain Technology: Potential Applications for Public Sector E-Procurement and Project Management (2022) · cites this paper as [36]
In the citing paper
“Slow inspection is one of the managerial problems and one of the causes of project delays [32,36].”
From Blockchain Technology: Potential Applications for Public Sector E-Procurement and Project Management (2022) · cites this paper as [36]
In the citing paper
“The lowest bidder issue is one of the common and important issues discussed by the different researchers [32,36,41].”
From Blockchain Technology: Potential Applications for Public Sector E-Procurement and Project Management (2022) · cites this paper as [36]
In the citing paper
“A lack of communication between parties is also a barrier to a successful project [36,37,40].”
From Blockchain Technology: Potential Applications for Public Sector E-Procurement and Project Management (2022) · cites this paper as [36]
2 more claims about this paper
Create a free account to see every claim other papers make about this one.
Citations
The citation lists haven’t been fetched yet
References 65 · Cited by 44
Research works printed but not linked: 5
- Amin, A. N. (2014). Housing industry of Bangladesh: Easing the constraints and overcoming the image deficit. Dhaka: Janasharthey Grihonirman.
- Faisal, F., & Ridwan, S. M. (2012). Infrastructure financing through domestic capital market in Bangladesh. World Journal of Social Science, 2(5), 31–41.
- Hameed, A., Abdul, I., Yasmin, N., & Abd, T. (2013). Social and web-based risk assessment technique for time and cost overrun (WRATTCO)—A framework. In International Conference on Innovation, Management and Technology Research, Malaysia, 22–23 September, pp. 1–7.
- Motaleb, O., & Kishk, M. (2010). An Investigation into causes and effects of construction delays in UAE. In Proceeding of 26th Annual ARCOM Conference, 6–8 September 2010, Leeds, UK, pp. 1149–1157.
- Salam, M. A., Staines, H. J., Blackwood, D. J., & Sarkar, S. (2001). Analysis of the relationships between causes of delay in construction projects in Bangladesh. In 17th Annual ARCOM Conference, vol. 1, pp. 619–28.
Metadata
- Authors
- Islam, M. S., & Suhariadi, B. T.
- Affiliations
- Queensland University of Technology (AU)
- Corresponding author
- Islam, Muhammad Saiful
- Venue
- Asian Journal of Civil Engineering
- Published
- 2018-03-28
- Volume
- 19
- Issue
- 4
- Pages
- 415-429
- ISSN
- 1563-0854 (ISSN-L)
- 2522-011X
- OpenAlex
- W2795237383
- Cited by
- 44
- References
- 65
- Citations by year
- 2026: 2 · 2025: 5 · 2024: 6 · 2023: 11 · 2022: 7 · 2021: 4 · 2020: 7 · 2019: 2
- FWCI
- 2.59
- Type
- journal article
- Language
- en
- Open access
- green
- figshare.com
- Licence
- cc-by
- www.springer.com/tdm (tdm)
- Locations
- Asian Journal of Civil Engineering (publishedVersion)
- RMIT Research Repository (RMIT University Library) (submittedVersion)
- Figshare (submittedVersion, cc-by)
- Topics
- Social Sciences › Decision Sciences › Management Science and Operations Research › Construction Project Management and Performance
- Social Sciences › Business, Management and Accounting › Strategy and Management › Value Engineering and Management
- Physical Sciences › Engineering › Building and Construction › BIM and Construction Integration
- Keywords
- construction delays, schedule delays, delay causes, construction management, construction planning and scheduling, cost and time estimation, site constraints, progress monitoring, cost control, contractor cash flow, stakeholder responsibility, Bangladesh
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
How to cite
Cite CoChat for the checks on this page, and the paper for its own findings.
- This page
- CoChat. (2026). Citation check: Construction delays in privately funded large building projects in Bangladesh. https://app.cochat.ai/papers/10.1007/s42107-018-0034-3
- The paper
- Islam, M. S., & Suhariadi, B. T. (2018). Construction delays in privately funded large building projects in Bangladesh. Asian Journal of Civil Engineering. https://doi.org/10.1007/s42107-018-0034-3
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.