An Analytical Network Process model for risks prioritisation in megaprojects
Open accessThe DOI matches its Crossref record; 57 of the 57 references it cites were found in a registry or an index.
Abstract
Megaprojects are complex and expensive projects that often involve social, technical, economic, environmental and political (STEEP) challenges to project management. Despite these challenges, project owners and financiers continue to invest large sums of money in megaprojects that run high risks of being over schedule and over budget. While some degree of cost and schedule risks are considered during project planning, the challenge of modelling risks interactions and impacts on project performance still remains. To tackle this technical problem, this research adopted the Analytical Network Process and combined it with a new Risk Priority Index as an innovative approach to model risks analytically based on data collected from the Edinburgh Tram Network project at the construction phase. The approach provides an interactive way for developers to prioritise risks across the project supply network and to initiate timely mitigation strategies against significant cost and time consequences of STEEP risks on megaproject performance.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Fundamentals of Decision Making and Priority Theory With the Analytic Hierarchy Process
Saaty, T. L. (2000) · Medical Entomology and Zoology · Cited by 2,635
Megaprojects and Risk: An Anatomy of Ambition
Flyvbjerg, B., Bruzelius, N., & Rothengatter, W. (2003) · Cambridge University Press eBooks · doi:10.1017/cbo9781107050891 · Cited by 2,415
What you Should Know about Megaprojects and Why: An Overview
Flyvbjerg, B. (2014) · Project Management Journal · doi:10.1002/pmj.21409 · Cited by 1,582 · cited 1×
“…development become complex and characterised by a number of uncertainties that can influence the project negatively, e.g see (Brookes, 2015; Dimitriou, 2014; Flyvbjerg, 2014; Flyvbjerg et al., 2003a; Mentis, 2015; Priemus, 2014; Renuka et al., 2014; Spirkova, 2014; Van de Graaf and Sovacool, 2014).”
BackgroundSaaty, T. L. (2005) · Medical Entomology and Zoology · Cited by 1,129
Underestimating Costs in Public Works Projects:Error or Lie?
Flyvbjerg, B., Holm, M. S., & Buhl, S. (2002) · Journal of the American Planning Association · doi:10.1080/01944360208976273 · Cited by 1,046
Ericsson's proactive supply chain risk management approach after a serious sub‐supplier accident
Norrman, A., & Jansson, U. (2004) · International Journal of Physical Distribution & Logistics Management · doi:10.1108/09600030410545463 · Cited by 1,037
Frimpong, Y., Oluwoye, J., & Crawford, L. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00055-8 · Cited by 796
How common and how large are cost overruns in transport infrastructure projects?
Flyvbjerg, B., Skamris holm, M. K., & Buhl, S. L. (2003) · Transport Reviews · doi:10.1080/01441640309904 · Cited by 783
Saaty, T. L., & Vargas, L. G. (2013) · International Series in Operations Research & Management Science · doi:10.1007/978-1-4614-7279-7 · Cited by 668
Evaluation of stakeholder influence in the implementation of construction projects
Olander, S., & Landin, A. (2005) · International Journal of Project Management · doi:10.1016/j.ijproman.2005.02.002 · Cited by 632
Cited by
Qazi, A., Quigley, J., Dickson, A., & Kirytopoulos, K. (2016) · International Journal of Project Management · doi:10.1016/j.ijproman.2016.05.008 · Cited by 294
Denicol, J., Davies, A., & Krystallis, I. (2020) · Project Management Journal · doi:10.1177/8756972819896113 · Cited by 266
Afzal, F., Yunfei, S., Nazir, M., & Bhatti, S. M. (2021) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-02-2019-0047 · Cited by 172
The front-end of projects: a systematic literature review and structuring
Williams, T., Vo, H., Samset, K., & Edkins, A. (2019) · Production Planning & Control · doi:10.1080/09537287.2019.1594429 · Cited by 145
Risk assessment of construction projects using Monte Carlo simulation
Qazi, A., & Simsekler, M. C. E. (2021) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-03-2020-0097 · Cited by 41
Metadata
- Authors
- Boateng, P., Chen, Z., & Ogunlana, S. O.
- Venue
- International Journal of Project Management
- Publisher
- Elsevier BV
- Published
- 2015-11
- Volume
- 33
- Issue
- 8
- Pages
- 1795-1811
- ISSN
- 0263-7863 (ISSN-L)
- OpenAlex
- W2184170249
- Cited by
- 172
- References
- 57
- FWCI
- 9.98
- Type
- journal article
- Language
- en
- Open access
- green
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.