Risk assessment of construction projects using Monte Carlo simulation
Abstract
Purpose: This paper aims to develop a process for prioritizing project risks that integrates the decision-maker's risk attitude, uncertainty about risks both in terms of the associated probability and impact ratings, and correlations across risk assessments. Design/methodology/approach: This paper adopts a Monte Carlo Simulation-based approach to capture the uncertainty associated with project risks. Risks are prioritized based on their relative expected utility values. The proposed process is operationalized through a real application in the construction industry. Findings: The proposed process helped in identifying low-probability, high-impact risks that were overlooked in the conventional risk matrix-based prioritization scheme. While considering the expected risk exposure of individual risks, none of the risks were located in the high-risk exposure zone; however, the proposed Monte Carlo Simulation-based approach revealed risks with a high probability of occurrence in the high-risk exposure zone. Using the expected utility-based approach alone in prioritizing risks may lead to ignoring few critical risks, which can only be captured through a rigorous simulation-based approach. Originality/value: Monte Carlo Simulation has been used to aggregate the risk matrix-based data and disaggregate and map the resulting risk profiles with underlying distributions. The proposed process supported risk prioritization based on the decision-maker's risk attitude and identified low-probability, high-impact risks and high-probability, high-impact risks.
Overview
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
Claims other papers make about this one
Each is checked against this paper’s own text: does it say what the citing paper says it does?
Increasingly more academics and practitioners are reluctant to resort to risk matrices.
“Since then, increasingly more academics and practitioners are reluctant to resort to risk matrices (Qazi et al. 2021).”
From Beyond probability-impact matrices in project risk management: A quantitative methodology for risk prioritisation (2024) · cites this paper as Qazi et al. 2021
Risk matrices are widely recognised tools by academics and practitioners in various sectors to assess and rank risks according to likelihood of occurrence and impact on project objectives.
“Risk matrices are widely recognised tools by academics and practitioners in various sectors to assess and rank risks according to their likelihood of occurrence and impact on project objectives.”
From Beyond probability-impact matrices in project risk management: A quantitative methodology for risk prioritisation (2024) · cites this paper as Qazi and Simsekler, 2021
Risk matrices are widely recognised tools by academics and practitioners in various sectors to assess and rank risks according to likelihood of occurrence and impact on project objectives.
“Risk matrices are widely recognised tools by academics and practitioners in various sectors to assess and rank risks according to their likelihood of occurrence and impact on project objectives.”
From Beyond probability-impact matrices in project risk management: A quantitative methodology for risk prioritisation (2024) · cites this paper as Qazi et al. 2021
Citations
Cites
No references could be resolved yet.
Research works printed but not linked: 40
- 2019, A review of artificial intelligence based risk assessment methods for capturing complexity-risk interdependencies: cost overrun in construction projects, International Journal of Managing Projects in Business
- 2017, Improving risk characterisations in practical situations by highlighting knowledge aspects, with applications to risk matrices, Reliability Engineering and System Safety, 167, 42, 10.1016/j.ress.2017.05.006 · DOI
- 2020, How to determine the largest global and national risks: review and discussion, Reliability Engineering and System Safety, 199
- 2020, Modeling and analyzing factors affecting project delays using an integrated social network-fuzzy MICMAC approach, Engineering Management Journal, 32, 26, 10.1080/10429247.2019.1656595 · DOI
- 2014, Managing quality in projects: an empirical study, International Journal of Project Management, 32, 178, 10.1016/j.ijproman.2013.02.003 · DOI
- 2015, An Analytical Network Process model for risks prioritisation in megaprojects, International Journal of Project Management, 33, 1795, 10.1016/j.ijproman.2015.08.007 · DOI
- 2014, A quantitative framework for managing project value, risk, and opportunity, IEEE Transactions on Engineering Management, 61, 583, 10.1109/TEM.2014.2326986 · DOI
- 2017, Critical factors impacting the performance of mega-projects, Engineering Construction and Architectural Management, 24, 920, 10.1108/ECAM-05-2016-0117 · DOI
- 2019, Fuzzy Bayesian schedule risk network for offshore wind turbine installation, Ocean Engineering, 188
- 2019, Strategy development using TOWS matrix for international project risk management based on prioritization of risk categories, International Journal of Managing Projects in Business, 12, 1003, 10.1108/IJMPB-07-2018-0128 · DOI
- 2018, Effects of risk attitude and controllability assumption on risk ratings: observational study on international construction project risk assessment, Journal of Management in Engineering, 34
- 2015, Recommendations on the use and design of risk matrices, Safety Science, 76, 21, 10.1016/j.ssci.2015.02.014 · DOI · Paper page
- 2008, Risk assessment and allocation in the UAE construction industry, International Journal of Project Management, 26, 431, 10.1016/j.ijproman.2007.07.004 · DOI · Paper page
- 2017, Measuring the impact of lean construction practices on project duration and variability: a simulation-based study on residential buildings, Journal of Civil Engineering and Management, 23, 241
- 2018, Project governance, project performance, and the mediating role of project quality and project management risk: an agency theory perspective, Engineering Management Journal, 30, 274, 10.1080/10429247.2018.1503038 · DOI
- 2009, Structuring the prediction model of project performance for international construction projects: a comparative analysis, Expert Systems with Applications, 36, 1961, 10.1016/j.eswa.2007.12.048 · DOI
- 2010, Categorizing risks in seven large projects—which risks do the projects focus on?, Project Management Journal, 41, 81, 10.1002/pmj.20154 · DOI
- 2020, Risk assessment using a new consulting process in fuzzy AHP, Journal of Construction Engineering and Management, 146
- 2019, A hybrid approach for quantitative assessment of construction projects risks: the case study of poor quality concrete, Computers and Industrial Engineering, 131, 306, 10.1016/j.cie.2019.03.045 · DOI
- 2015, Quantifying the complexity of transportation projects using the fuzzy analytic hierarchy process, International Journal of Project Management, 33, 1364, 10.1016/j.ijproman.2015.02.007 · DOI
- 2003, Applying utility theory to risk management, Project Management Journal, 34, 26, 10.1177/875697280303400304 · DOI
- 2020, Risk matrix driven supply chain risk management: adapting risk matrix based tools to modelling interdependent risks and risk appetite, Computers and Industrial Engineering
- 2019, From risk matrices to risk networks in construction projects, IEEE Transactions on Engineering Management
- 2019, Analysing causal relationships between delay factors in construction projects, International Journal of Managing Projects in Business
- 2015, Risk matrix integrating risk attitudes based on utility theory, Risk Analysis, 35, 1437, 10.1111/risa.12400 · DOI
- SA, 2009, Risk Management: Principles and Guidelines (AS/NZS ISO 31000: 2009)
- 2010, Fuzzy Monte Carlo simulation and risk assessment in construction, Computer-Aided Civil and Infrastructure Engineering, 25, 238, 10.1111/j.1467-8667.2009.00632.x · DOI
- 2014, Quality vs risk: an investigation of their relationship in software development projects, International Journal of Project Management, 32, 1073, 10.1016/j.ijproman.2013.11.001 · DOI
- 2008, Failure mode and effects analysis (FMEA) in the context of risk management in new product development, International Journal of Quality and Reliability Management, 25, 899, 10.1108/02656710810908061 · DOI
- 2018, Design for patient safety: a systems-based risk identification framework, Ergonomics, 61, 1046, 10.1080/00140139.2018.1437224 · DOI
- 2011, International projects proposal analysis: risk assessment using radial maps, Project Management Journal, 42, 62, 10.1002/pmj.20237 · DOI
- 2014, Towards a better modelling and assessment of construction risk: insights from a literature review, International Journal of Project Management, 32, 101, 10.1016/j.ijproman.2013.03.004 · DOI · Paper page
- 2019, Delay risk assessment of repetitive construction projects using line-of-balance scheduling and Monte Carlo simulation, Journal of Construction Engineering and Management, 145
- 2018, The construction dust-induced occupational health risk using Monte-Carlo simulation, Journal of Cleaner Production, 184, 598, 10.1016/j.jclepro.2018.02.286 · DOI · Paper page
- 2014, The impact of uncertainty and ambiguity related to iteration and overlapping on schedule of product development projects, International Journal of Project Management, 32, 827, 10.1016/j.ijproman.2013.10.010 · DOI
- 2019, Improved decision model for evaluating risks in construction projects, Journal of Construction Engineering and Management, 145
- 2019, A bayesian networks approach to estimate engineering change propagation risk and duration, IEEE Transactions on Engineering Management, 67, 869
- 2014, A knowledge-based risk mapping tool for cost estimation of international construction projects, Automation in Construction, 43, 144, 10.1016/j.autcon.2014.03.010 · DOI
- 2016, Selecting risk response strategies considering project risk interdependence, International Journal of Project Management, 34, 819, 10.1016/j.ijproman.2016.03.001 · DOI
- 2007, Understanding the key risks in construction projects in China, International Journal of Project Management, 25, 601, 10.1016/j.ijproman.2007.03.001 · DOI
Cited by
Sorted by citations
Acebes, F., González-Varona, J. M., López-Paredes, A., & Pajares, J. (2024) · Humanities and Social Sciences Communications · doi:10.1057/s41599-024-03180-5 · Cited by 74
Metadata
- Authors
- Qazi, A., & Simsekler, M. C. E.
- Affiliations
- American University of Sharjah (AE)
- Khalifa University of Science and Technology (AE)
- Venue
- International Journal of Managing Projects in Business
- Publisher
- Emerald
- Published
- 2021-02-12
- Volume
- 14
- Issue
- 5
- Pages
- 1202-1218
- ISSN
- 1753-8378 (ISSN-L)
- OpenAlex
- W3130298214
- Cited by
- 41
- References
- 0
- Citations by year
- 2026: 15 · 2025: 12 · 2024: 5 · 2023: 4 · 2022: 4 · 2021: 1
- FWCI
- 1.94
- Type
- journal article
- Language
- en
- Open access
- closed
- Locations
- International Journal of Managing Projects in Business (publishedVersion)
- Topics
- Social Sciences › Decision Sciences › Management Science and Operations Research › Construction Project Management and Performance
- Social Sciences › Economics, Econometrics and Finance › Finance › Capital Investment and Risk Analysis
- Social Sciences › Decision Sciences › Management Science and Operations Research › Multi-Criteria Decision Making
- Keywords
- construction risk, risk prioritization, Monte Carlo simulation, expected utility, risk preferences, risk matrix, risk exposure, risk probability and impact, risk correlation
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review