Waste effectiveness of the construction industry: Understanding the impediments and requisites for improvements
Open accessOverview
The claims and statistics of this paper haven’t been checked yet.
Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.
Claims other papers make about this one
Each is checked against this paper’s own text: does it say what the citing paper says it does?
Lack of design for deconstruction (DfD) intervention at the design stage is a barrier to reuse of building components.
“According to the literature, the lack of such an intervention is a barrier to reuse (Ajayi et al., 2015; Chileshe et al., 2015, 2016b; Dunant et al., 2017; Huuhka and Hakanen, 2015; Tatiya et al., 2017 (among others)).”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Ajayi et al., 2015
Lack of confidence in the quality of reused components negatively affects reuse in new constructions.
“Lack of confidence in the quality of the reused components negatively affects reuse in new constructions (Ajayi et al., 2015; Chileshe et al., 2015, 2016b, 2016a; Shaurette, 2006 (among others)).”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Ajayi et al., 2015
Section 2.2 (Materials Re-Use; page unavailable) describes uses for reclaimed construction materials but does not discuss confidence in their quality. Searches for “confidence,” “quality,” and “reused components” found no passage linking quality concerns to reduced reuse in new construction. (LLM, conf=0.72)
Experimental — accuracy not yet measured
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
The Delphi Technique: Making Sense of Consensus
Hsu, C.-C., & Sandford, B. A. (2007) · University of Massachusetts Amherst · doi:10.7275/pdz9-th90 · Cited by 4,500 · cited 1×
“The technique is a widely used and accepted method of enquiry that is used to achieve convergence of opinion from people within a domain of expertise (Hsu, 2007).”
Flagged first, then by citations
Research works printed but not linked: 46
- Akintoye, 1998, Risk analysis and management of private finance initiative projects, Eng. Constr. Archit. Manage., 5, 9, 10.1108/eb021056 · DOI
- Al-Hajj, 2011, Material waste in the UAE construction industry: main causes and minimization practices, Architect. Eng. Des. Manage., 7, 221
- Baek, 2013, Life cycle carbon dioxide assessment tool for buildings in the schematic design phase, Energy Build., 61, 275, 10.1016/j.enbuild.2013.01.025 · DOI · Paper page
- Barros, 1998, A two-level network for recycling sand: a case study, Eur. J. Oper. Res., 110, 199, 10.1016/S0377-2217(98)00093-9 · DOI
- Begum, 2006, A benefit–cost analysis on the economic feasibility of construction waste minimisation: the case of Malaysia, Resour. Conserv. Recycl., 48, 86, 10.1016/j.resconrec.2006.01.004 · DOI
- Blengini, 2009, Life cycle of buildings, demolition and recycling potential: a case study in Turin, Italy, Build. Environ., 44, 319, 10.1016/j.buildenv.2008.03.007 · DOI
- Browna, 2014, Better the devil you throw: experience and support for pay-as-you-throw waste charges, Environ. Sci. Policy, 38, 132, 10.1016/j.envsci.2013.11.007 · DOI
- Corsten, 2013, The potential contribution of sustainable waste management to energy use and greenhouse gas emission reduction in The Netherlands, Resour. Conserv. Recycl., 77, 13, 10.1016/j.resconrec.2013.04.002 · DOI
- Dahlén, 2010, Pay as you throw strengths and weaknesses of weight-based billing in household waste collection systems in Sweden, Waste Manage., 30, 23, 10.1016/j.wasman.2009.09.022 · DOI
- Dalkey, 1963, An experimental application of the Delphi method to the use of experts, Manage. Sci., 9, 458, 10.1287/mnsc.9.3.458 · DOI · Paper page
- Dantata, 2005, An analysis of cost and duration for deconstruction and demolition of residential buildings in Massachusetts, Resour. Conserv. Recycl., 44, 1, 10.1016/j.resconrec.2004.09.001 · DOI · Paper page
- Durana, 2006, A model for assessing the economic viability of construction and demolition waste recycling – the case of Ireland, Resour. Conserv. Recycl., 46, 302, 10.1016/j.resconrec.2005.08.003 · DOI
- Durmus, 2011, Methodology of deconstruction in architectural education, Procedia Soc. Behav. Sci., 15, 1586, 10.1016/j.sbspro.2011.03.335 · DOI
- Eadie, 2013, BIM implementation throughout the UK construction project lifecycle: an analysis, Autom. Constr., 36, 145, 10.1016/j.autcon.2013.09.001 · DOI
- Ekanayake, 2004, Building waste assessment score: design-based tool, Build. Environ., 39, 851, 10.1016/j.buildenv.2004.01.007 · DOI
- Enshassi, 2009, Delays and cost overruns in the construction projects in the Gaza strip, J. Financial Manage. Property Constr., 14, 126, 10.1108/13664380910977592 · DOI
- Faniran, 1998, Minimizing waste on construction project sites, Eng. Constr. Archit. Manage., 5, 182, 10.1108/eb021073 · DOI
- Formoso, 2002, Material waste in building industry: main causes and prevention, J. Constr. Eng. Manage., 128, 316, 10.1061/(ASCE)0733-9364(2002)128:4(316) · DOI
- Gao, 2001, Energy impacts of recycling disassembly materials in residential buildings, Energy Build., 33, 553, 10.1016/S0378-7788(00)00096-7 · DOI
- Hardie, 2007, The efficacy of waste management plans in Australian commercial construction refurbishment projects, Aust. J. Constr. Econ. Build., 7, 26
- Hodgson, 2011, Great expectations and hard times: the paradoxical experience of the engineer as project manager, Int. J. Project Manage., 29, 374, 10.1016/j.ijproman.2011.01.005 · DOI
- Jaillon, 2009, Quantifying the waste reduction potential of using prefabrication in building construction in Hong Kong, Waste Manage., 29, 309, 10.1016/j.wasman.2008.02.015 · DOI
- Jasper, 1994, Issues in phenomenology for researchers of nursing, J. Adv. Nursing, 19, 309, 10.1111/j.1365-2648.1994.tb01085.x · DOI
- Lu, 2013, Investigating waste reduction potential in the upstream processes of offshore prefabrication construction, Renew. Sustain. Energy Rev., 28, 804, 10.1016/j.rser.2013.08.048 · DOI
- Manfredi, 2009, Landfilling of waste: accounting of greenhouse gases and global warming contributions, Waste Manage. Res., 27, 825, 10.1177/0734242X09348529 · DOI
- Mcdonald, 1998, Implementing a waste management plan during the construction phase of a project: a case study, Constr. Manage. Econ., 16, 71, 10.1080/014461998372600 · DOI
- McGrath, 2001, Waste minimisation in practice, Resour. Conserv. Recycl., 32, 227, 10.1016/S0921-3449(01)00063-5 · DOI
- Osmani, 2012, Construction waste minimization in the UK: current pressures for change and approaches, Procedia Soc. Behav. Sci., 40, 37, 10.1016/j.sbspro.2012.03.158 · DOI
- Osmani, 2008, Architects’ perspectives on construction waste reduction by design, Waste Manage., 28, 1147, 10.1016/j.wasman.2007.05.011 · DOI
- Oyedele, 2012, Avoiding performance failure payment deductions in PFI/PPP projects: model of critical success factors, J. Perform. Constr Facil., 27, 283, 10.1061/(ASCE)CF.1943-5509.0000367 · DOI
- Oyedele, 2014, Use of recycled products in UK construction industry: an empirical investigation into critical impediments and strategies for improvement, Resour. Conserv. Recycl., 93, 23, 10.1016/j.resconrec.2014.09.011 · DOI
- Oyedele, 2013, Reducing waste to landfill in the UK: identifying impediments and critical solutions, World J. Sci. Technol. Sustain. Dev., 10, 131, 10.1108/20425941311323136 · DOI
- Peng, 1997, Strategies for successful construction and demolition waste recycling operations, Constr. Manage. Econ., 15, 49, 10.1080/014461997373105 · DOI
- Poon, 2001, On-site sorting of construction and demolition waste in Hong Kong, Resour. Conserv. Recycl., 32, 157, 10.1016/S0921-3449(01)00052-0 · DOI · Paper page
- Read, 1997, Landfill as a future waste management option in England: the view of landfill operators, Resour. Conserv. Recycl., 20, 183, 10.1016/S0921-3449(97)00017-7 · DOI
- Skumatz, 2008, Pay as you throw in the US: implementation, impacts, and experience, Waste Manage., 28, 2778, 10.1016/j.wasman.2008.03.033 · DOI
- Solís-Guzmán, 2009, A Spanish model for quantification and management of construction waste, Waste Manage., 29, 2542, 10.1016/j.wasman.2009.05.009 · DOI · Paper page
- Tam, 2005, Use of prefabrication to minimize construction waste – a case study approach, Int. J. Constr. Manage., 5, 91
- Tam, 2008, On the effectiveness in implementing a waste-management-plan method in construction, Waste Manage., 28, 1072, 10.1016/j.wasman.2007.04.007 · DOI
- Tam, 2007, Towards adoption of prefabrication in construction, Build. Environ., 42, 3642, 10.1016/j.buildenv.2006.10.003 · DOI
- Teo, 2001, A theory of waste behaviour in the construction industry, Constr. Manage. Econ., 19, 741, 10.1080/01446190110067037 · DOI
- Treolar, 2003, An analysis of factors influencing waste minimisation and use of recycled materials for the construction of residential buildings, Manage. Environ. Qual. Int. J., 14, 134, 10.1108/14777830310460432 · DOI
- Wimpenny, 2000, Interviewing in phenomenology and grounded theory: is there a difference, J. Adv. Nursing, 31, 1485, 10.1046/j.1365-2648.2000.01431.x · DOI · Paper page
- Yeheyis, 2013, An overview of construction and demolition waste management in Canada: a lifecycle analysis approach to sustainability, Clean Technol. Environ. Policy, 15, 81, 10.1007/s10098-012-0481-6 · DOI · Paper page
- Yuan, 2013, Critical management measures contributing to construction waste management: evidence from construction projects in China, Project Manage. J., 44, 101, 10.1002/pmj.21349 · DOI
- Yuan, 2012, A dynamic model for assessing the effects of management strategies on the reduction of construction and demolition waste, Waste Manage., 32, 521, 10.1016/j.wasman.2011.11.006 · DOI · Paper page
Cited by
Sorted by citations
Akinade, O. O., Oyedele, L. O., Ajayi, S. O., Bilal, M., Alaka, H. A., Owolabi, H. A., Bello, S. A., Jaiyeoba, B. E., & Kadiri, K. O. (2017) · Waste Management · doi:10.1016/j.wasman.2016.08.017 · Cited by 270
Self-citationComponents reuse in the building sector – A systematic review
Rakhshan, K., Morel, J.-C., Alaka, H., & Charef, R. (2020) · Waste Management & Research: The Journal for a Sustainable Circular Economy · doi:10.1177/0734242x20910463 · Cited by 167
“Ajayi et al. (2015) suggest that by integrating DfD during the design stage of a building, the recovery of building components for reuse would be facilitated.”
BackgroundSelf-citationAlhawamdeh, M., Ferriz-Papi, J. A., & Lee, A. (2024) · Sustainability · doi:10.3390/su16146014 · Cited by 33
Metadata
- Authors
- Ajayi, S. O., Oyedele, L. O., Bilal, M., Akinade, O. O., Alaka, H. A., Owolabi, H. A., & Kadiri, K. O.
- Affiliations
- University of the West of England (GB)
- Obafemi Awolowo University (NG)
- Corresponding author
- Oyedele, Lukumon O.
- Venue
- Resources, Conservation and Recycling
- Publisher
- Elsevier BV
- Published
- 2015-09
- Volume
- 102
- Pages
- 101-112
- ISSN
- 0921-3449 (ISSN-L)
- OpenAlex
- W1175199023
- Cited by
- 282
- References
- 1
- Citations by year
- 2026: 32 · 2025: 38 · 2024: 32 · 2023: 31 · 2022: 31 · 2021: 31 · 2020: 25 · 2019: 26 · 2018: 14 · 2017: 9 · 2016: 11 · 2015: 1
- FWCI
- 15.88
- Type
- journal article
- Language
- en
- Open access
- Locations
- Resources Conservation and Recycling (publishedVersion)
- Leeds Beckett Repository (Leeds Beckett University) (submittedVersion)
- UWE Research Repository (UWE Bristol) (submittedVersion, cc-by-nc-nd)
- RePEc: Research Papers in Economics (submittedVersion)
- Topics
- Physical Sciences › Engineering › Building and Construction › Recycled Aggregate Concrete Performance
- Physical Sciences › Engineering › Building and Construction › Sustainable Building Design and Assessment
- Social Sciences › Business, Management and Accounting › Strategy and Management › Sustainable Supply Chain Management
- Keywords
- construction and demolition waste, construction waste management, waste reduction, landfill waste, end-of-pipe treatment, building information modeling, waste management costs, waste management regulation
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review