Different cost performance: different determinants?
Open accessThe DOI matches its Crossref record; 17 of the 17 references it cites were found in a registry or an index.
Abstract
This paper examines three independent explanatory variables and their relation with cost overrun in order to decide whether this is different for Dutch infrastructure projects compared to worldwide findings. The three independent variables are project type (road, rail, and fixed link projects), project size (measured in terms of estimated costs) and the length of the project implementation phase. For Dutch projects, average cost overrun is 10.6% for rail, 18.6% for roads and 21.7% for fixed links. For project size, small Dutch projects have the largest average percentage cost overruns but in terms of total overrun, large projects have a larger share. The length of the implementation phase and especially the length of the pre-construction phase are important determinants of cost overruns in the Netherlands. With each additional year of pre-construction, percentage cost overrun increases by five percentage points. In contrast, the length of the construction phase has hardly any influence on cost overruns. This is an important contribution to current knowledge about cost overruns, because the period in which projects are most prone to cost overruns is narrowed down considerably, at least in the Netherlands. This means that to determine the causes and cures of overruns one should focus on the period.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Megaprojects and Risk: An Anatomy of Ambition
Flyvbjerg, B., Bruzelius, N., & Rothengatter, W. (2003) · Cambridge University Press eBooks · doi:10.1017/cbo9781107050891 · Cited by 2,415
Self-citationUnderestimating Costs in Public Works Projects:Error or Lie?
Flyvbjerg, B., Holm, M. S., & Buhl, S. (2002) · Journal of the American Planning Association · doi:10.1080/01944360208976273 · Cited by 1,046
Self-citationWorld development report 1994 : infrastructure for development
Lanjouw, P., Besant-Jones, J. E., Estache, A., Kessides, C., Pritchett, L. H., Mody, A., & Ingram, G. K. (1994) · Dépôt institutionnel de l'Université libre de Bruxelles (Université Libre de Bruxelles) · Cited by 937
How common and how large are cost overruns in transport infrastructure projects?
Flyvbjerg, B., Skamris holm, M. K., & Buhl, S. L. (2003) · Transport Reviews · doi:10.1080/01441640309904 · Cited by 783 · cited 4×
“onstruction costs determined at the Time of formal Decision to build (ToD). This is also called the "decision date”, "the time of the decision to proceed," the "go-decision" (Flyvbjerg et al., 2003a). At that moment, cost estimates were often available as data for decision-makers to make an in…”
InfluentialSelf-citationThe Anatomy of Major Projects: A Study of the Reality of Project Management
Morris, P. W. G., & Hough, G. H. (1988) · Medical Entomology and Zoology · Cited by 696
Policy and Planning for Large-Infrastructure Projects: Problems, Causes, Cures
Flyvbjerg, B. (2007) · Environment and Planning B: Planning and Design · doi:10.1068/b32111 · Cited by 521
Self-citationWhat Causes Cost Overrun in Transport Infrastructure Projects?
FLYVBJERG, B., SKAMRIS HOLM, M. K., & BUHL, S. L. (2004) · Transport Reviews · doi:10.1080/0144164032000080494a · Cited by 455
Self-citationCost overruns in road construction—what are their sizes and determinants?
Odeck, J. (2004) · Transport Policy · doi:10.1016/s0967-070x(03)00017-9 · Cited by 385
A Desire Named Streetcar Fantasy and Fact in Rail Transit Planning
Pickrell, D. H. (1992) · Journal of the American Planning Association · doi:10.1080/01944369208975791 · Cited by 321 · cited 1×
“s. By the time of opening, the calculated cost overruns are enormous. That these cost overruns are a severe problem has been shown in previous studies (Flyvbjerg et al., 2003a, 2003b; Merewitz, 1973; Pickrell, 1992; Odeck, 2004; Nijkamp and Ubbels, 1999). From a first study on the cost performance of Dutch projects, i…”
Forecasting: An appraisal for policy-makers and planners
(1979) · Technological Forecasting and Social Change · doi:10.1016/0040-1625(79)90082-9 · Cited by 294
Cited by
Denicol, J., Davies, A., & Krystallis, I. (2020) · Project Management Journal · doi:10.1177/8756972819896113 · Cited by 266
Five things you should know about cost overrun
Flyvbjerg, B., Ansar, A., Budzier, A., Buhl, S., Cantarelli, C., Garbuio, M., Glenting, C., Holm, M. S., Lovallo, D., Lunn, D., et al. (2018) · Transportation Research Part A: Policy and Practice · doi:10.1016/j.tra.2018.07.013 · Cited by 238
“Fourth, we stated in Flyvbjerg et al. (2002: 280, 293) and later papers (Cantarelli et al. 2012a,b,c; Flyvbjerg 2016; Ansar et al. 2017) that, as far as we know, our dataset on cost overrun in large transportation infrastructure projects is the largest of its kind.”
BackgroundResultInfluentialSelf-citationAfzal, F., Yunfei, S., Nazir, M., & Bhatti, S. M. (2021) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-02-2019-0047 · Cited by 172
Love, P. E. D., Ahiaga-Dagbui, D. D., & Irani, Z. (2016) · Transportation Research Part A: Policy and Practice · doi:10.1016/j.tra.2016.08.007 · Cited by 138
“…a much-needed stimulus for theory that can be used to explain cost overrun causation, they still remain a ubiquitous and on-going issue (e.g., Flyvbjerg et al ., 2002; Bordat et al ., 2004; Odeck, 2004; Flyvbjerg et al ., 2005; Flyvbjerg, 2007; Cantarelli et al , 2012a,b,c; Love et al ., 2015b).”
The cost performance and causes of overruns in infrastructure development projects in Asia
Andrić, J. M., Mahamadu, A.-M., Wang, J., Zou, P. X. W., & Zhong, R. (2019) · Journal of Civil Engineering and Management · doi:10.3846/jcem.2019.8646 · Cited by 61
Metadata
- Authors
- Cantarelli, C. C., van Wee, B., Molin, E. J. E., & Flyvbjerg, B.
- Venue
- Transport Policy
- Publisher
- Elsevier BV
- Published
- 2012-07
- Volume
- 22
- Pages
- 88-95
- ISSN
- 0967-070X (ISSN-L)
- OpenAlex
- W3124310067
- Cited by
- 179
- References
- 17
- FWCI
- 11.94
- Type
- journal article
- Language
- en
- Open access
- green
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.