What Causes Cost Overrun in Transport Infrastructure Projects?
Open accessAbstract
Results from the first statistically significant study of the causes of cost escalation in transport infrastructure projects are presented. The study is based on a sample of 258 rail, bridge, tunnel and road projects worth US$90 billion. The focus is on the dependence of cost escalation on: (1) the length of the project‐implementation phase, (2) the size of the project and (3) the type of project ownership. First, it was found, with very high statistical significance, that cost escalation was strongly dependent on the length of the implementation phase. The policy implications are clear: decision‐makers and planners should be highly concerned about delays and long implementation phases because they translate into risks of substantial cost escalations. Second, projects have grown larger over time, and for bridges and tunnels larger projects have larger percentage cost escalations. Finally, by comparing the cost escalation for three types of project ownership—private, state‐owned enterprise and other public ownership—it was shown that the oft‐seen claim that public ownership is problematic and private ownership effective in curbing cost escalation is an oversimplification. The type of accountability appears to matter more to cost escalation than type of ownership.
Overview
The claims and statistics of this paper haven’t been checked yet.
Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Big decisions, big risks. Improving accountability in mega projects
Bruzelius, N., Flyvbjerg, B., & Rothengatter, W. (2002) · Transport Policy · doi:10.1016/s0967-070x(02)00014-8 · Cited by 220
Cited by
Flyvbjerg, B. (2008) · European Planning Studies · doi:10.1080/09654310701747936 · Cited by 438
Self-citationRETRACTED: Inaccuracy in Traffic Forecasts
Flyvbjerg, B., Skamris Holm, M. K., & Buhl, S. L. (2006) · Transport Reviews · doi:10.1080/01441640500124779 · Cited by 220
Self-citationRetractedAfzal, F., Yunfei, S., Nazir, M., & Bhatti, S. M. (2021) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-02-2019-0047 · Cited by 172
Park, Y., & Papadopoulou, T. C. (2012) · Built Environment Project and Asset Management · doi:10.1108/20441241211280873 · Cited by 91
The cost performance and causes of overruns in infrastructure development projects in Asia
Andrić, J. M., Mahamadu, A.-M., Wang, J., Zou, P. X. W., & Zhong, R. (2019) · Journal of Civil Engineering and Management · doi:10.3846/jcem.2019.8646 · Cited by 61
Metadata
- Authors
- FLYVBJERG, B., SKAMRIS HOLM, M. K., & BUHL, S. L.
- Venue
- Transport Reviews
- Publisher
- Informa UK Limited
- Published
- 2004-01
- Volume
- 24
- Issue
- 1
- Pages
- 3-18
- ISSN
- 0144-1647 (ISSN-L)
- 1464-5327
- OpenAlex
- W2156351434
- Cited by
- 455
- References
- 1
- FWCI
- 9.43
- Type
- journal article
- Language
- en
- Open access
- green
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
How to cite
Cite CoChat for the checks on this page, and the paper for its own findings.
- This page
- CoChat. (2026). Citation check: What Causes Cost Overrun in Transport Infrastructure Projects? https://app.cochat.ai/papers/10.1080/0144164032000080494a
- The paper
- FLYVBJERG, B., SKAMRIS HOLM, M. K., & BUHL, S. L. (2004). What Causes Cost Overrun in Transport Infrastructure Projects? Transport Reviews. https://doi.org/10.1080/0144164032000080494a
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.