From Construction Megaproject Management to Complex Project Management: Bibliographic Analysis
The DOI matches its Crossref record; 71 of the 71 references it cites were found in a registry or an index.
Abstract
The rapid growth of construction megaprojects worldwide has triggered a growing number of papers published in this area in the past two decades, suggesting that construction megaproject management has become an emerging area in the field of construction engineering and management (CEM). This study aims to investigate the status and the trends in megaproject research by conducting a structured literature review. A total of 85 relevant articles identified from eight peer-reviewed CEM journals between 2000 and 2010 were analyzed based on the number of articles published annually, institutional and regional contributions, citations, and categorization of research interests and methodologies. Analysis results indicated that developed countries, such as the United Kingdom, the United States, and Australia, have enjoyed significant advantages in megaproject research because of their greater experience, while megaproject research in developing countries, such as Russia, India, Turkey, and Vietnam, remains weak or lacking. These results also revealed that many theory-based findings have been reported in five subareas; namely, construction and site management, cost and schedule management, risk analysis and management, innovation and utilization of information technology, and leadership and professional development. The subareas of organization and stakeholder management, project planning and procurement, and project monitoring and control remain to be promising domains for future research, particularly in developing countries which have yet to develop a research tradition. Incorporating the complexity theory and institutional theory as the theoretical foundation in these subareas can develop megaproject research further through strengthened global collaboration in the future.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Methodological fit in management field research
Edmondson, A. C., & Mcmanus, S. E. (2007) · Academy of Management Review · doi:10.5465/amr.2007.26586086 · Cited by 3,227
Complexity: The Emerging Science at the Edge of Order and Chaos
Waldrop, M. M., & Stein, D. (1992) · Physics Today · doi:10.1063/1.2809917 · Cited by 2,622 · cited 1×
“…projects originated from complexity 113 theory (Whitty and Maylor 2009), a well-known physical theory developed by the Santa Fe Institute 114 in the 1980s to solve complex real-world cross-discipline problems, such as those in astronomy, 115 biology, and economy (Waldrop 1992; Ziemelis 2001).”
BackgroundMegaprojects and Risk: An Anatomy of Ambition
Flyvbjerg, B., Bruzelius, N., & Rothengatter, W. (2003) · Cambridge University Press eBooks · doi:10.1017/cbo9781107050891 · Cited by 2,415 · cited 4×
“84 The project cost threshold of USD 1 billion is increasingly advocated worldwide as the key 85 criterion for defining a megaproject (Flyvbjerg et al. 2003; van Marrewijk et al. 2008).”
BackgroundInfluentialThe concept of project complexity—a review
Baccarini, D. (1996) · International Journal of Project Management · doi:10.1016/0263-7863(95)00093-3 · Cited by 1,192 · cited 2×
“This theory has been applied to project 116 management since the late 1990s (Baccarini 1996; Williams 2002).”
BackgroundMethodLeadership competency profiles of successful project managers
Müller, R., & Turner, R. (2010) · International Journal of Project Management · doi:10.1016/j.ijproman.2009.09.003 · Cited by 758 · cited 3×
“Relevant papers concentrated on two specific topics, namely, capability assessment 368 (Yasin et al. 2009; Müller and Turner 2010) and professional development (Crawford et al. 2006; 369 Toor and Ogunlana 2009; Frank et al. 2007).”
BackgroundMethodToor, S.-U.-R., & Ogunlana, S. O. (2010) · International Journal of Project Management · doi:10.1016/j.ijproman.2009.05.005 · Cited by 619 · cited 1×
“…414 as interviews, case studies and content analyses, were frequently employed in these studies to 415 explore the theories behind real cases (e.g. von Branconi and Loch 2004; Murtoaro and Kujala 2007; 416 Thomas and Mengel 2008; Ruuska et al. 2009; Toor and Ogunlana 2010; Brady and Davies 2010).”
MethodManaging public–private megaprojects: Paradoxes, complexity, and project design
van Marrewijk, A., Clegg, S. R., Pitsis, T. S., & Veenswijk, M. (2008) · International Journal of Project Management · doi:10.1016/j.ijproman.2007.09.007 · Cited by 518
From Nobel Prize to Project Management: Getting Risks Right
Flyvbjerg, B. (2006) · Project Management Journal · doi:10.1177/875697280603700302 · Cited by 494 · cited 1×
“Specific topics of the identified papers included risk identification 355 (Santoso et al. 2003; Busby and Hughes 2004; de Camprieu et al. 2007; Krane et al. 2010), risk 356 measurement (Molenaar 2005; Sun et al. 2008), and risk control methods (Schexnayder et al. 2004; 357 Flyvbjerg 2006).”
BackgroundMega-projects: the changing politics of urban public investment
(2004) · Choice Reviews Online · doi:10.5860/choice.41-3716 · Cited by 485
Preparing project managers to deal with complexity – Advanced project management education
Thomas, J., & Mengel, T. (2008) · International Journal of Project Management · doi:10.1016/j.ijproman.2008.01.001 · Cited by 471 · cited 2×
“…body for megaprojects (Ivory and Alderman 2005; Saynisch 2010), but 378 also improves the capability of professionals managing megaprojects(Thomas and Mengel 2008; 379 Whitty and Maylor 2009).. 380 Categories of Research Methods in Megaproject Research 381 (Please insert Table 9 here) 382…”
BackgroundMethodThe Strategic Management of Large Engineering Projects: Shaping Institutions, Risks, and Governance
Miller, R. L., & Lessard, D. R. (2001) · Cited by 459
Megaprojects: the Changing Politics of Urban Public Investment
(2004) · International Journal of Public Sector Management · doi:10.1108/ijpsm.2004.17.3.275.1 · Cited by 430
Managing high-technology programs and projects
Archibald, R. D. (1976) · Cited by 422
A study on project success factors in large construction projects in Vietnam
Duy Nguyen, L., Ogunlana, S. O., & Thi Xuan Lan, D. (2004) · Engineering, Construction and Architectural Management · doi:10.1108/09699980410570166 · Cited by 415
The Oxford Handbook of Project Management
(2011) · Oxford University Press eBooks · doi:10.1093/oxfordhb/9780199563142.001.0001 · Cited by 339 · cited 1×
“Morris et al. (2011) stressed the importance of the new paradigm of viewing projects as 316 organizations in project management studies and that this new research paradigm is the principal 317 shift of the focus on project management studies.”
BackgroundResearch Trend of Public-Private Partnership in Construction Journals
Ke, Y., Wang, S., Chan, A. P., & Cheung, E. (2009) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2009)135:10(1076 · Cited by 309 · cited 2×
“…Table 6 here) 288 289 Although using citations as a measure of research quality has raised some controversy (Kostoff 290 1998), this method has been increasingly adopted as the key indicator for measuring the quality of 291 papers published in the CEM field (Ke et al. 2009; Hong et al. 2012).”
MethodSelf-citationProblems causing delays in major construction projects in Thailand
Toor, S.-U.-R., & Ogunlana, S. (2008) · Construction Management and Economics · doi:10.1080/01446190801905406 · Cited by 307 · cited 1×
“…aspect was grouped into the following categories: cost overrun analysis (Eden et al. 341 2005; Creedy et al. 2010), delay analysis (Williams 2003; Toor and Ogunlana 2008), optimization 342 and modeling (Wang and Demsetz 2000; Hardie 2001; Liu and Rahbar 2004; Vanhoucke et al. 2005; 343 Touran…”
BackgroundIssues in Front-End Decision Making on Projects
Williams, T., & Samset, K. (2010) · Project Management Journal · doi:10.1002/pmj.20160 · Cited by 290 · cited 1×
“…Beheiry et al. 2006; Zhai et al. 2009; Toor and 331 Ogunlana 2010), decision management (Ng et al. 2004; Jergeas 2008; Genadioand Singh 2010; 332 Williams and Samset 2010), procurement methods (such as design and build, engineering 333 procurement construction and build-operate-transfer) (Tam…”
MethodHoward, G. S., Cole, D. A., & Maxwell, S. E. (1987) · American Psychologist · doi:10.1037//0003-066x.42.11.975 · Cited by 277
Evaluation of Risk Factors Leading to Cost Overrun in Delivery of Highway Construction Projects
Creedy, G. D., Skitmore, M., & Wong, J. K. W. (2010) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000160 · Cited by 242 · cited 2×
“…Yasin et al. 2009), 396 Delphi survey (Dzeng and Wen 2005; Sun et al. 2008), 397 Correlation analysis (Helen et al. 2010), 398 Regression analysis (Creedy et al. 2010), 399 Fuzzy analysis (Zammori et al. 2009; Dzeng and Wem, 2005), 400 Particle swarm optimization (Yang 2007), 401 Markov…”
BackgroundPractitioner development: From trained technicians to reflective practitioners
Crawford, L., Morris, P., Thomas, J., & Winter, M. (2006) · International Journal of Project Management · doi:10.1016/j.ijproman.2006.09.010 · Cited by 237 · cited 1×
“Relevant papers concentrated on two specific topics, namely, capability assessment 368 (Yasin et al. 2009; Müller and Turner 2010) and professional development (Crawford et al. 2006; 369 Toor and Ogunlana 2009; Frank et al. 2007).”
BackgroundProgrammatic Cost Risk Analysis for Highway Megaprojects
Molenaar, K. R. (2005) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2005)131:3(343 · Cited by 234 · cited 2×
“17 measurement (Molenaar 2005; Sun et al. 2008), and risk control methods (Schexnayder et al.”
BackgroundAnd then came Complex Project Management (revised)
Whitty, S. J., & Maylor, H. (2009) · International Journal of Project Management · doi:10.1016/j.ijproman.2008.03.004 · Cited by 231 · cited 3×
“…(Ivory and Alderman 2005; Saynisch 2010), but 378 also improves the capability of professionals managing megaprojects(Thomas and Mengel 2008; 379 Whitty and Maylor 2009).. 380 Categories of Research Methods in Megaproject Research 381 (Please insert Table 9 here) 382 383 Table 9 shows the…”
BackgroundThe use and misuse of citation analysis in research evaluation
Kostoff, R. N. (1998) · Scientometrics · doi:10.1007/bf02458392 · Cited by 220
The Oxford Handbook of Project Management
Morris, P. W. G., Pinto, J., & Söderlund, J. (2012) · PROJECT MANAGER (IL) · doi:10.3280/pm2012-010013 · Cited by 200
The ranking of construction management journals
Wing, C. K. (1997) · Construction Management and Economics · doi:10.1080/014461997372953 · Cited by 198
Governance Frameworks for Public Project Development and Estimation
Klakegg, O. J., Williams, T., Magnussen, O. M., & Glasspool, H. (2008) · Project Management Journal · doi:10.1002/pmj.20058 · Cited by 194
The core competencies of effective project execution
Lampel, J. (2001) · International Journal of Project Management · doi:10.1016/s0263-7863(01)00042-4 · Cited by 178 · cited 1×
“…and Samset 2010), procurement methods (such as design and build, engineering 333 procurement construction and build-operate-transfer) (Tam 2000; Lampel 2001; Kumaraswamy and 334 Morris 2002; Ling and Lau 2002; Algarni et al. 2007), and contract management (von Branconi and 335 Loch 2004;…”
MethodGovernance regimes for large complex projects
Miller, R., & Hobbs, B. (2005) · Project Management Journal · doi:10.1177/875697280503600305 · Cited by 174 · cited 4×
“Miller and Hobbs (2005) proposed that megaprojects can reconcile the 451 uncertainty through good interaction with the institutional environment.”
BackgroundInfluentialDevelopment and Initial Validation of Sustainable Construction Safety and Health Rating System
Rajendran, S., & Gambatese, J. (2009) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2009)135:10(1067 · Cited by 170
Remington, K., & Pollack, J. (2016) · Routledge eBooks · doi:10.4324/9781315550831 · Cited by 167 · cited 1×
“…are usually characterized 425 by the high internal complexity, such as task complexity (Brockmann and Girmscheid 2007), 426 structural complexity (Remington and Pollack 2008), directional complexity (Remington and 427 Pollack 2008), technical complexity, and organizational complexity (Baccarini…”
BackgroundInstitutional Theory as a Framework for Analyzing Conflicts on Global Projects
Mahalingam, A., & Levitt, R. E. (2007) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2007)133:7(517 · Cited by 166
Zhai, L., Xin, Y., & Cheng, C. (2009) · Project Management Journal · doi:10.1002/pmj.20099 · Cited by 164 · cited 1×
“…these work packages to contractors, including objective and scope 330 management (Ahmad et al. 2003; Nguyen et al. 2004; Beheiry et al. 2006; Zhai et al. 2009; Toor and 331 Ogunlana 2010), decision management (Ng et al. 2004; Jergeas 2008; Genadioand Singh 2010; 332 Williams and Samset…”
BackgroundManaging project culture: The case of Environ Megaproject
van Marrewijk, A. H. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2006.11.004 · Cited by 146 · cited 1×
“…van Marrewijk et al. 2008), communication 322 management (Murtoaro and Kujala 2007; Tai et al. 2009), team management (Dzeng and Wen 2005; 323 van Marrewijk 2007), organizational governance and integration (Berggren et al. 2001; Klakegg et al. 324 2008; Miller and Hobbs 2005), and organizational…”
BackgroundShehu, Z., & Akintoye, A. (2009) · International Journal of Project Management · doi:10.1016/j.ijproman.2009.02.004 · Cited by 132 · cited 2×
“Construction projects operate in the uncertain context 441 because of widespread economic fluctuation (Shehu and Akintoye 2010).”
BackgroundDimensions of distance in a project network: Exploring Olkiluoto 3 nuclear power plant project
Ruuska, I., Artto, K. A., Aaltonen, K., & Lehtonen, P. (2008) · International Journal of Project Management · doi:10.1016/j.ijproman.2008.09.003 · Cited by 130
Safety Risk Identification and Assessment for Beijing Olympic Venues Construction
Sun, Y., Fang, D., Wang, S., Dai, M., & Lv, X. (2007) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(2008)24:1(40 · Cited by 130 · cited 2×
“…of the following: 395 Empirical survey (e.g. Müller and Turner 2010; Santoso et al. 2003; Yasin et al. 2009), 396 Delphi survey (Dzeng and Wen 2005; Sun et al. 2008), 397 Correlation analysis (Helen et al. 2010), 398 Regression analysis (Creedy et al. 2010), 399 Fuzzy analysis (Zammori et al.…”
BackgroundModeling Cost Escalation in Large Infrastructure Projects
Touran, A., & López, R. (2006) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2006)132:8(853 · Cited by 119 · cited 3×
“…2003; Toor and Ogunlana 2008), optimization 342 and modeling (Wang and Demsetz 2000; Hardie 2001; Liu and Rahbar 2004; Vanhoucke et al. 2005; 343 Touran and Lopez 2006; Bonnal et al. 2006; Yang 2007; Zammori et al. 2009), and performance 344 management (Walker and Shen 2002; Yang et al. 2006).”
BackgroundMethodCoordination and control in project‐based work: digital objects and infrastructures for delivery
Whyte, J. K., & Lobo, S. (2010) · Construction Management and Economics · doi:10.1080/01446193.2010.486838 · Cited by 117 · cited 1×
“…involved IT application issues in 361 different phases and aspects of megaproject management, including design management (Harty and 362 Whyte 2010; Whyte and Lobo 2010), communication management (Thorpe and Mead 2001; 363 Underwood and Watson 2003; Rowlinson 2007), and workflow and process…”
BackgroundProject management topic coverage in journals
Themistocleous, G., & Wearne, S. H. (2000) · International Journal of Project Management · doi:10.1016/s0263-7863(99)00030-7 · Cited by 117 · cited 1×
“Megaproject research interests 311 involve nine topics suggested by Themistocleous and Wearne (2000)(Table 8).”
BackgroundPartnering in major contracts: Paradox and metaphor
Alderman, N., & Ivory, C. J. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2007.01.002 · Cited by 117 · cited 2×
“…Ogunlana 2002; 320 Leung et al. 2004; Helm and Reminton 2005; Ruuska et al. 2009), project partnership (Cathcart 2003; 321 Anderson Jr. et al. 2006; Alderman and Ivory 2007; van Marrewijk et al. 2008), communication 322 management (Murtoaro and Kujala 2007; Tai et al. 2009), team management (Dzeng…”
BackgroundCan Project Management Learn Anything from Studies of Failure in Complex Systems?
Ivory, C. J., & Alderman, N. (2005) · Project Management Journal · doi:10.1177/875697280503600302 · Cited by 111 · cited 3×
“…this theory to megaproject research, pointing out that it not only contributes to the 377 establishment of a knowledge body for megaprojects (Ivory and Alderman 2005; Saynisch 2010), but 378 also improves the capability of professionals managing megaprojects(Thomas and Mengel 2008; 379…”
BackgroundThe futures of construction: a critical review of construction future studies
Harty, C. F., Goodier, C. I., Soetanto, R., Austin, S. A., Dainty, A., & Price, A. D. F. (2007) · Construction Management and Economics · doi:10.1080/01446190600879117 · Cited by 110
From hero to hubris – Reconsidering the project management of Heathrow’s Terminal 5
Brady, T., & Davies, A. C. (2009) · International Journal of Project Management · doi:10.1016/j.ijproman.2009.11.011 · Cited by 108 · cited 2×
“Only three papers on 373 this topic were identified: Brady and Davies (2010), Edum-Fotwe et al. (2004), and Jaafari (2007).”
BackgroundMethodToor, S., & Ogunlana, S. O. (2009) · Engineering Construction & Architectural Management · doi:10.1108/09699980910951663 · Cited by 103 · cited 1×
“Relevant papers concentrated on two specific topics, namely, capability assessment 368 (Yasin et al. 2009; Müller and Turner 2010) and professional development (Crawford et al. 2006; 369 Toor and Ogunlana 2009; Frank et al. 2007).”
BackgroundContracting for major projects: eight business levers for top management
von Branconi, C., & Loch, C. H. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(03)00014-0 · Cited by 96
Build-Operate-Transfer in Infrastructure Projects in the United States
Algarni, A. M., Arditi, D., & Polat, G. (2007) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2007)133:10(728 · Cited by 95 · cited 1×
“…methods (such as design and build, engineering 333 procurement construction and build-operate-transfer) (Tam 2000; Lampel 2001; Kumaraswamy and 334 Morris 2002; Ling and Lau 2002; Algarni et al. 2007), and contract management (von Branconi and 335 Loch 2004; Badenfelt 2008; Rose and Manley 2010).”
MethodWalker, D. H. T., & Shen, Y. J. (2002) · Construction Management and Economics · doi:10.1080/01446190110089691 · Cited by 93
Helm, J., & Remington, K. (2005) · Project Management Journal · doi:10.1177/875697280503600306 · Cited by 93
Projects, pathogens and incubation periods
Busby, J. S., & Hughes, E. J. (2003) · International Journal of Project Management · doi:10.1016/j.ijproman.2003.09.002 · Cited by 91 · cited 1×
“Specific topics of the identified papers included risk identification 355 (Santoso et al. 2003; Busby and Hughes 2004; de Camprieu et al. 2007; Krane et al. 2010), risk 356 measurement (Molenaar 2005; Sun et al. 2008), and risk control methods (Schexnayder et al. 2004; 357 Flyvbjerg 2006).”
BackgroundEmerging Hybrid Practices in Construction Design Work: Role of Mixed Media
Harty, C. F., & Whyte, J. K. (2009) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000146 · Cited by 90
Berggren, C., Söderlund, J., & Anderson, C. (2001) · Project Management Journal · doi:10.1177/875697280103200306 · Cited by 86 · cited 1×
“…and Kujala 2007; Tai et al. 2009), team management (Dzeng and Wen 2005; 323 van Marrewijk 2007), organizational governance and integration (Berggren et al. 2001; Klakegg et al. 324 2008; Miller and Hobbs 2005), and organizational learning and innovation (Lê and Brønn 2007; 325 Winch 2000).”
BackgroundLingard, H. C., Francis, V., & Turner, M. (2010) · Construction Management and Economics · doi:10.1080/01446193.2010.480977 · Cited by 85 · cited 4×
“…management (Chua and Goh 347 2005; Rajendran and Gambatese 2009), labor and construction productivity (Elhakeem and Hegazy 348 2005; Aziz 2008; Helen et al. 2010), quality and material management (Ibn-Homaid 2002; Keeling 349 2003), and construction technology and management (Attar et al.…”
BackgroundMethodInfluentialA fuzzy multi-criteria approach for critical path definition
Zammori, F., Braglia, M., & Frosolini, M. (2008) · International Journal of Project Management · doi:10.1016/j.ijproman.2008.03.006 · Cited by 83 · cited 2×
“…2003; Toor and Ogunlana 2008), optimization 342 and modeling (Wang and Demsetz 2000; Hardie 2001; Liu and Rahbar 2004; Vanhoucke et al. 2005; 343 Touran and Lopez 2006; Bonnal et al. 2006; Yang 2007; Zammori et al. 2009), and performance 344 management (Walker and Shen 2002; Yang et al. 2006).”
BackgroundAnalysis of the Front-End Loading of Alberta Mega Oil Sands Projects
Jergeas, G. F. (2008) · Project Management Journal · doi:10.1002/pmj.20080 · Cited by 79 · cited 2×
“…(Ahmad et al. 2003; Nguyen et al. 2004; Beheiry et al. 2006; Zhai et al. 2009; Toor and 331 Ogunlana 2010), decision management (Ng et al. 2004; Jergeas 2008; Genadioand Singh 2010; 332 Williams and Samset 2010), procurement methods (such as design and build, engineering 333 procurement…”
MethodThe selection of sharing ratios in target cost contracts
Badenfelt, U. (2008) · Engineering Construction & Architectural Management · doi:10.1108/09699980810842061 · Cited by 70 · cited 1×
“…methods (such as design and build, engineering 333 procurement construction and build-operate-transfer) (Tam 2000; Lampel 2001; Kumaraswamy and 334 Morris 2002; Ling and Lau 2002; Algarni et al. 2007), and contract management (von Branconi and 335 Loch 2004; Badenfelt 2008; Rose and Manley 2010).”
MethodDemystifying stakeholders' commitment and its impacts on construction projects
Leung, M., Chong, A. M. L., Ng, S. T., & Cheung, M. C. K. (2004) · Construction Management and Economics · doi:10.1080/0144619042000300736 · Cited by 63 · cited 1×
“…organizational and disciplinary domains to 319 improve megaproject performance, including stakeholder management (Awakul and Ogunlana 2002; 320 Leung et al. 2004; Helm and Reminton 2005; Ruuska et al. 2009), project partnership (Cathcart 2003; 321 Anderson Jr. et al. 2006; Alderman and Ivory…”
BackgroundPerforming complex project crashing analysis with aid of particle swarm optimization algorithm
Yang, I. (2006) · International Journal of Project Management · doi:10.1016/j.ijproman.2006.11.001 · Cited by 59
Categorizing Risks in Seven Large Projects—Which Risks Do the Projects Focus On?
Krane, H. P., Rolstadås, A., & Olsson, N. O. E. (2010) · Project Management Journal · doi:10.1002/pmj.20154 · Cited by 52 · cited 1×
“Specific topics of the identified papers included risk identification 355 (Santoso et al. 2003; Busby and Hughes 2004; de Camprieu et al. 2007; Krane et al. 2010), risk 356 measurement (Molenaar 2005; Sun et al. 2008), and risk control methods (Schexnayder et al. 2004; 357 Flyvbjerg 2006).”
BackgroundPoisson Model of Construction Incident Occurrence
Chua, D. K. H., & Goh, Y. M. (2005) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2005)131:6(715 · Cited by 44 · cited 2×
“19 Particle swarm optimization (Yang 2007), 401 Markov analysis (Hardie, 2001), 402 Integer programming analysis (Rajendran and Gambatese 2009), 403 Loss causation analysis (Chua and Goh 2005), 404 Nomograph theory (Elhakeem and Hegazy 2005), 405”
BackgroundProject and program diagnostics: A systemic approach
Jaafari, A. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2007.05.008 · Cited by 44 · cited 1×
“Only three papers on 373 this topic were identified: Brady and Davies (2010), Edum-Fotwe et al. (2004), and Jaafari (2007).”
BackgroundEvaluating project teaming strategies for construction of Taipei 101 using resource-based theory
Dzeng, R., & Wen, K.-S. (2005) · International Journal of Project Management · doi:10.1016/j.ijproman.2005.02.004 · Cited by 42 · cited 2×
“…studies consisted of the following: 395 Empirical survey (e.g. Müller and Turner 2010; Santoso et al. 2003; Yasin et al. 2009), 396 Delphi survey (Dzeng and Wen 2005; Sun et al. 2008), 397 Correlation analysis (Helen et al. 2010), 398 Regression analysis (Creedy et al. 2010), 399 Fuzzy…”
BackgroundInnovativeness in British and French construction: the evidence from Transmanche-Link
Winch, G. (2000) · Construction Management and Economics · doi:10.1080/014461900433096 · Cited by 36 · cited 1×
“…and Kujala 2007; Tai et al. 2009), team management (Dzeng and Wen 2005; 323 van Marrewijk 2007), organizational governance and integration (Berggren et al. 2001; Klakegg et al. 324 2008; Miller and Hobbs 2005), and organizational learning and innovation (Lê and Brønn 2007; 325 Winch 2000).”
BackgroundReconciling construction innovation and standardisation on major projects
Edum‐Fotwe, F. T., Gibb, A., & Benford‐Miller, M. (2004) · Engineering Construction & Architectural Management · doi:10.1108/09699980410558566 · Cited by 36 · cited 1×
“Only three papers on 373 this topic were identified: Brady and Davies (2010), Edum-Fotwe et al. (2004), and Jaafari (2007).”
BackgroundInstitutional effects on project arrangement: high‐speed rail projects in China and Taiwan
Chi, C. S. F., & Javernick‐Will, A. N. (2011) · Construction Management and Economics · doi:10.1080/01446193.2011.569734 · Cited by 32 · cited 2×
“Only recently has institutional analysis been increasingly advocated as the main tool 455 to examine the contextual effect on the management of megaprojects (e.g., Grigg, 2005; 456 Mahalingam et al. 2007; Chi and Javernick-Will, 2011).”
BackgroundBrockmann, C., & Girmscheid, G. (2007) · Repository for Publications and Research Data (ETH Zurich) · doi:10.3929/ethz-a-005997850 · Cited by 26 · cited 3×
“Brockmann and Girmscheid (2007) further categorized the 129 complexity of megaprojects into three groups: task, social, and cultural complexity.”
BackgroundLinking experience and learning: application to multi‐project building environments
Lê, M. A. T., & Brønn, C. (2007) · Engineering Construction & Architectural Management · doi:10.1108/09699980710731272 · Cited by 25 · cited 2×
“324 2008; Miller and Hobbs 2005), and organizational learning and innovation (Lê and Brønn 2007; 325 Winch 2000).”
BackgroundTRANSPORTATION AT THE MILLENNIUM: In Search of a Megaproject Lens
Haynes, W. (2002) · Review of Policy Research · doi:10.1111/j.1541-1338.2002.tb00265.x · Cited by 22 · cited 1×
“These items are sometimes used 90 interchangeably with “megaproject” (Haynes 2002).”
MethodFrank, M., Zwikael, O., & Boasson, M. (2007) · Project Management Journal · doi:10.1002/pmj.20004 · Cited by 17 · cited 2×
“2009; Müller and Turner 2010) and professional development (Crawford et al. 2006; 369 Toor and Ogunlana 2009; Frank et al. 2007).”
BackgroundAziz, A. A. (2008) · Construction Management and Economics · doi:10.1080/01446190801918748 · Cited by 17 · cited 2×
“…included safety management (Chua and Goh 347 2005; Rajendran and Gambatese 2009), labor and construction productivity (Elhakeem and Hegazy 348 2005; Aziz 2008; Helen et al. 2010), quality and material management (Ibn-Homaid 2002; Keeling 349 2003), and construction technology and management (Attar…”
BackgroundBoersma, K., Kingma, S. F., & Veenswijk, M. B. (2007) · Project Management Journal · doi:10.1177/875697280703800208 · Cited by 4 · cited 1×
“…and aspects of megaproject management, including design management (Harty and 362 Whyte 2010; Whyte and Lobo 2010), communication management (Thorpe and Mead 2001; 363 Underwood and Watson 2003; Rowlinson 2007), and workflow and process management (Badir et al. 364 2003; Boersma et al. 2007).”
Background
Cited by
Zheng, X., Le, Y., Chan, A. P. C., Hu, Y., & Li, Y. (2016) · International Journal of Project Management · doi:10.1016/j.ijproman.2016.06.005 · Cited by 329
Self-citationHe, Q., Luo, L., Hu, Y., & Chan, A. P. C. (2015) · International Journal of Project Management · doi:10.1016/j.ijproman.2014.07.009 · Cited by 243
Self-citationSankaran, S., Müller, R., & Drouin, N. (2020) · Systems Research and Behavioral Science · doi:10.1002/sres.2744 · Cited by 35
Halder, A. (2024) · Innovative Infrastructure Solutions · doi:10.1007/s41062-024-01521-6 · Cited by 10
Metadata
- Authors
- Hu, Y., Chan, A. P. C., Le, Y., & Jin, R.-Z.
- Venue
- Journal of Management in Engineering
- Published
- 2015-07
- Volume
- 31
- Issue
- 4
- ISSN
- 0742-597X (ISSN-L)
- 1943-5479
- OpenAlex
- W1996145333
- Cited by
- 221
- References
- 71
- FWCI
- 6.80
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.