An exact solution approach for disassembly line balancing problem under uncertainty of the task processing times
Open accessThe DOI matches its Crossref record; 15 of the 15 references it cites were found in a registry or an index.
Abstract
The purpose of this work is to efficiently design disassembly lines taking into account the uncertainty of task processing times. The main contribution of the paper is the development of a decision tool that allows decision-makers to choose the best disassembly alternative (process), for an End of Life product (EOL), and assign the corresponding disassembly tasks to the workstations of the line under precedence and cycle time constraints. Task times are assumed to be random variables with known normal probability distributions. The case of presence of hazardous parts is studied and cycle time constraints are to be jointly satisfied with at least a certain probability level, or service level, fixed by the decision-maker. An AND/OR graph is used to model the precedence relationships among tasks. The objective is to minimise the line cost composed of the workstation operation costs and additional costs of workstations handling hazardous parts of the EOL product. To deal with task time uncertainties, lower and upper-bounding schemes using second-order cone programming and approximations with convex piecewise linear functions are developed. The applicability of the proposed solution approach is shown by solving to optimality a set of disassembly problem instances (EOL industrial products) from the literature.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
International Journal of Production Research
HAWKINS, T. H. (1962) · Nature · doi:10.1038/1931144a0 · Cited by 2,111
Ilgin, M. A., & Gupta, S. M. (2010) · Journal of Environmental Management · doi:10.1016/j.jenvman.2009.09.037 · Cited by 1,015 · cited 2×
“Introduction Disassembly lines as disassembly systems play a crucial role in EOL product recovery, mainly reuse, remanufacturing and recycling [1,2].”
BackgroundJournal of Intelligent Manufacturing
(2013) · Journal of Intelligent Manufacturing · doi:10.1007/10845.1572-8145 · Cited by 917
Disassembly line in product recovery
Güngör, A., & Gupta, S. M. (2002) · International Journal of Production Research · doi:10.1080/00207540210135622 · Cited by 288 · cited 4×
“Such a line consists of an ordered sequence of workstations connected by a material handling system which allows the transportation of work-pieces from one workstation to another [1,3].”
BackgroundInfluentialAgrawal, S., & Tiwari, M. K. (2008) · International Journal of Production Research · doi:10.1080/00207540600943985 · Cited by 252 · cited 2×
“A collaborative ant colony metaheuristic for stochastic mixed-model U-shaped DLBP was developed by Agrawal and Tiwari (2008). Task times were assumed to be uncertain with known independent normal probability distributions”
MethodKoc, A., Sabuncuoğlu, İ., & Erel, E. (2009) · IIE Transactions · doi:10.1080/07408170802510390 · Cited by 229 · cited 2×
“Keywords: sustainable manufacturing; disassembly process planning; line design; chance constraints; uncertainty”
BackgroundLinear programming in disassembly/clustering sequence generation
Lambert, A. J. D. (1999) · Computers & Industrial Engineering · doi:10.1016/s0360-8352(99)00162-x · Cited by 196
Özceylan, E., Paksoy, T., & Bektaş, T. (2014) · Transportation Research Part E: Logistics and Transportation Review · doi:10.1016/j.tre.2013.11.001 · Cited by 171
A sample average approximation method for disassembly line balancing problem under uncertainty
Bentaha, M. L., Battaïa, O., & Dolgui, A. B. (2014) · Computers & Operations Research · doi:10.1016/j.cor.2014.05.006 · Cited by 150 · cited 6×
“In (Bentaha, Battaïa, and Dolgui 2014a, 2014b, 2014c; Bentaha et al. 2014), mathematical models for designing this line under uncertainty of task processing times were developed.”
BackgroundMethodInfluentialSelf-citationMulti-objective optimization of stochastic disassembly line balancing with station paralleling
Aydemir-Karadag, A., & Türkbey, O. (2013) · Computers & Industrial Engineering · doi:10.1016/j.cie.2013.03.014 · Cited by 146 · cited 2×
“A genetic algorithm to solve a nonlinear binary bi-objective program was developed in [8] for disassembly line design and balancing under uncertainty of the task times.”
MethodSolving large scale disassembly line balancing problem with uncertainty using reinforcement learning
Tüncel, E., Zeid, A., & Kamarthi, S. V. (2012) · Journal of Intelligent Manufacturing · doi:10.1007/s10845-012-0711-0 · Cited by 143 · cited 2×
“in [16] used a Monte Carlo based reinforcement learning technique to solve the multi-objective DLBP under demand variations of the EOL products.”
MethodTask-failure-driven rebalancing of disassembly lines
Altekin, F. T., & Akkan, C. (2011) · International Journal of Production Research · doi:10.1080/00207543.2011.616915 · Cited by 139 · cited 1×
“A MIP based predictive-reactive approach to deal with task failures was also developed in [17] for DLBP aiming to maximize the profit generated by a disassembly line.”
MethodThe stochastic U-line balancing problem: A heuristic procedure
Chiang, W., & Urban, T. L. (2005) · European Journal of Operational Research · doi:10.1016/j.ejor.2004.10.031 · Cited by 100 · cited 2×
“…developed to solve stochastic U-type assembly line balancing problem: genetic algorithm (Baykasoğlu and Özbakır 2007), a two-phase hybrid heuristic (Chiang and Urban 2006), a beam search-based method (Erel, Sabuncuoglu, and Sekerci 2005), and an exact solution approach based on a piecewise linear…”
BackgroundMethodTripathi, M., Agrawal, S., Pandey, M. K., Shankar, R., & Tiwari, M. K. (2008) · Robotics and Computer-Integrated Manufacturing · doi:10.1016/j.rcim.2008.02.004 · Cited by 99 · cited 2×
“To deal with task time uncertainties, lower and upper-bounding schemes using second-order cone programming and approximations with convex piecewise linear functions are developed.”
MethodDealing with uncertainty in disassembly line design
Bentaha, M. L., Battaïa, O., Dolgui, A. B., & Hu, S. J. (2014) · CIRP Annals · doi:10.1016/j.cirp.2014.03.004 · Cited by 78 · cited 3×
“In (Bentaha, Battaïa, and Dolgui 2014a, 2014b, 2014c; Bentaha et al. 2014), mathematical models for designing this line under uncertainty of task processing times were developed.”
BackgroundMethodSelf-citation
Cited by
Design, management and control of demanufacturing and remanufacturing systems
Tolio, T., Bernard, A., Colledani, M., Kara, S., Seliger, G., Duflou, J., Battaia, O., & Takata, S. (2017) · CIRP Annals · doi:10.1016/j.cirp.2017.05.001 · Cited by 277
Disassembly line balancing problem: a review of the state of the art and future directions
Özceylan, E., Kalayci, C. B., Güngör, A., & Gupta, S. M. (2019) · International Journal of Production Research · doi:10.1080/00207543.2018.1428775 · Cited by 220
“…2014e, 2014c, 2015b); Habibi et al. (2014) Flashlight 7/10 Time Paksoy et al. (2013); Özceylan and Paksoy (2014b, 2014c); Özceylan, Paksoy, and Bektaş (2014); Bentaha, Battaïa, and Dolgui (2015a); Mete et al. (2016b) Piston and connecting rod 16/25 Time, revenue, hazardous Bentaha et al. (2013a,…”
BackgroundMethodInfluentialDisassembly Sequence Planning: A Survey
Guo, X., Zhou, M., Abusorrah, A., Alsokhiry, F., & Sedraoui, K. (2021) · IEEE/CAA Journal of Automatica Sinica · doi:10.1109/jas.2020.1003515 · Cited by 217
Modelling green and lean supply chains: An eco-efficiency perspective
Carvalho, H., Govindan, K., Azevedo, S. G., & Cruz-Machado, V. (2017) · Resources, Conservation and Recycling · doi:10.1016/j.resconrec.2016.09.025 · Cited by 188
Guo, X., Zhang, Z., Qi, L., Liu, S., Tang, Y., & Zhao, Z. (2022) · IEEE Transactions on Automation Science and Engineering · doi:10.1109/tase.2021.3133601 · Cited by 169
“1 and 2 show a ballpoint pen [36] and a hand light [37], respectively, and their AND/OR graphs are depicted in Fig.”
Background
Metadata
- Authors
- Bentaha, M. L., Battaïa, O., & Dolgui, A.
- Venue
- International Journal of Production Research
- Publisher
- Informa UK Limited
- Published
- 2014-09-25
- Volume
- 53
- Issue
- 6
- Pages
- 1807-1818
- ISSN
- 0020-7543 (ISSN-L)
- 1366-588X
- OpenAlex
- W1996513145
- Cited by
- 181
- References
- 15
- FWCI
- 21.98
- Type
- journal article
- Language
- en
- Open access
- green
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.