Quantifying the causes and costs of rework in construction

Love, Peter E. D., Li, Heng·2000·Construction Management and Economics

Abstract

Very few construction companies and consulting firms in Australia measure their costs of quality. Consequently, it is difficult for them to prove that systems for preventing quality failures are cost-effective. Although the direct costs of a quality system can be quantified with some accuracy (salaries, costs of documentation, audits, etc.), the corresponding benefits are far more difficult to assess. Indeed quality failures have become an endemic feature of the procurement process in construction and invariably lead to time and cost overruns in projects. Thus, in order to improve the performance of projects it is necessary to identify the causes and costs rework. The research presented in this paper quantifies the causes, magnitude and costs of rework experienced in two construction projects that were procured using different contractual arrangements. The causes and costs of rework projects are analysed and discussed. The findings reveal that the cost of rework for the case study projects was 3.15% and 2.40% of their project contract value. Changes initiated by the client and end-user together with errors and omissions in contract documentation were found to be the primary causes of rework. It is recommended that construction companies and consultant firms (particularly design consultants) implement quality management practices as well as place emphasis on coordinating project documentation during the design development process so that the amount of rework in projects can be reduced or even eliminated.

Overview

The claims and statistics of this paper haven’t been checked yet.

Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.

A few free checks a day · papers already verified open instantly · results are public

Integrity signals

Registry

Crossref · 10.1080/01446190050024897

Cites

3 of 3 references verified0 citation errors · 0 not checkable

Statistics

Verification

Claims the paper makes

The claims and statistics of this paper haven’t been checked yet.

Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.

A few free checks a day · papers already verified open instantly · results are public

Self-check

Percentages, sums and reported differences re-computed from the paper’s own numbers.

The self-check needs the paper’s full text.

Citations

Cites

Show all 3 references

Cited by

See all 486

Metadata

Authors
Love, P. E. D., & Li, H.
Venue
Construction Management and Economics
Published
2000-06
Volume
18
Issue
4
Pages
479-490
ISSN
  • 0144-6193 (ISSN-L)
  • 1466-433X
OpenAlex
W2103328477
Cited by
486
References
3
FWCI
7.61
Type
journal article
Language
en
Open access
closed

About these checks

Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.

Statistics and arithmetic are recomputed, not judged.

Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.

What counts as a claim ›How we measure confidence ›How we check this ›

Are you an author, or do you see a problem with this page? Request a review

How to cite

Cite CoChat for the checks on this page, and the paper for its own findings.

This page
CoChat. (2026). Citation check: Quantifying the causes and costs of rework in construction. https://app.cochat.ai/papers/10.1080/01446190050024897
The paper
Love, P. E. D., & Li, H. (2000). Quantifying the causes and costs of rework in construction. Construction Management and Economics. https://doi.org/10.1080/01446190050024897

Data sources

Bibliographic data: Semantic Scholar, OpenAlex, Crossref.

Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).

Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.