Modelling and assessment of critical risks in BOT road projects

Thomas, A. V., Kalidindi, Satyanarayana N., Ganesh, L. S. · 2006 · Construction Management and Economics

Abstract

Over the years, many private sector participation (PSP) models have been evolved for infrastructure procurement and the Build‐Operate‐Transfer (BOT) model is one of the most common approaches used for the same. Private infrastructure projects under BOT arrangement have a complex risk profile and to a considerable extent, the success of any BOT project is influenced by the degree to which various project risks are managed. The major steps involved in risk management of a project are risk identification, risk assessment and the processes of prioritization and response to the risks. The conventional risk assessment approaches may not be effective in privatized infrastructure projects because of the fact that, they have very long project lifecycle with many country and sector specific risk factors. The assessment of complex risks is often a difficult task when past data on similar risks are not available. In this research, a risk probability and impact assessment framework based on fuzzy‐fault tree and the Delphi method is proposed. The framework includes extensive scenario modelling of critical risks in projects and systematic processing of professional judgement (subjective knowledge) of experts and is developed and demonstrated in the context of critical risks in Indian BOT road projects. Detailed scenario modelling of most critical risks such as traffic revenue risk, delay in land acquisition, demand risk and delay in financial closure are also presented. The proposed risk assessment framework is generic and can be applied with appropriate modifications to suit any complex developmental project where past data is inadequate for risk assessment.

Overview

The claims and statistics of this paper haven’t been checked yet.

Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.

A few free checks a day · papers already verified open instantly · results are public

Integrity signals

Registry

Crossref · 10.1080/01446190500435275

Cites

Statistics

Verification

Claims the paper makes

The claims and statistics of this paper haven’t been checked yet.

Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.

A few free checks a day · papers already verified open instantly · results are public

Self-check

Percentages, sums and reported differences re-computed from the paper’s own numbers.

The self-check needs the paper’s full text.

Citations

Cited by

See all 163

Metadata

Authors
Thomas, A. V., Kalidindi, S. N., & Ganesh, L. S.
Venue
Construction Management and Economics
Published
2006-04
Volume
24
Issue
4
Pages
407-424
ISSN
  • 0144-6193 (ISSN-L)
  • 1466-433X
OpenAlex
W2117936945
Cited by
163
References
0
FWCI
14.50
Type
journal article
Language
en
Open access
closed

About these checks

Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.

Statistics and arithmetic are recomputed, not judged.

Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.

What counts as a claim ›How we measure confidence ›How we check this ›

Are you an author, or do you see a problem with this page? Request a review

How to cite

Cite CoChat for the checks on this page, and the paper for its own findings.

This page
CoChat. (2026). Citation check: Modelling and assessment of critical risks in BOT road projects. https://app.cochat.ai/papers/10.1080/01446190500435275
The paper
Thomas, A. V., Kalidindi, S. N., & Ganesh, L. S. (2006). Modelling and assessment of critical risks in BOT road projects. Construction Management and Economics. https://doi.org/10.1080/01446190500435275

Data sources

Bibliographic data: Semantic Scholar, OpenAlex, Crossref.

Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).

Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.