Design issues of using prefabrication in Hong Kong building construction
The DOI matches its Crossref record; 20 of the 20 references it cites were found in a registry or an index.
Abstract
Prefabrication techniques have been adopted for the last two decades in public housing projects in Hong Kong, but the use of prefabrication in the private sector was encouraged only after the implementation of the Joint Practices Notes which promote its use. Although previous studies acknowledge the environmental benefits of using prefabrication, only a few studies have addressed sustainable design concepts (closed‐loop) in the adoption of precast construction. A questionnaire survey was administered to experienced Hong Kong construction professionals, and case studies of recently completed building projects were compiled to ascertain the use of prefabrication with reference to life cycle approach. The findings revealed that prefabrication, combined with modular design and standard components, saved time and construction/design costs, as buildings systems were used across projects. However, in some projects, specific site conditions restricted the use of similar prefabricated building systems across projects. Surprisingly only a few participants addressed life cycle design concepts such as design for deconstruction when adopting precast construction. Also, although it is common knowledge that flexible and demountable prefabricated building systems would result in efficient use of resources, their use is seldom practised in Hong Kong.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Cradle to cradle: remaking the way we make things
(2002) · Choice Reviews Online · doi:10.5860/choice.40-0914 · Cited by 3,829
Sustainable Construction: Green Building Design and Delivery
Kibert, C. J. (2005) · Cited by 1,098
Towards adoption of prefabrication in construction
Tam, V. W. Y., Tam, C. M., Zeng, S. X., & Ng, W. C. Y. (2007) · Building and Environment · doi:10.1016/j.buildenv.2006.10.003 · Cited by 628 · cited 2×
“According to previous studies using case study analysis of recent completed buildings, the standardization of block designs increases project buildability and speed of construction (Chan and Chan, 2002; Tam et al., 2007b; Building Construction Authority, 2008).”
BackgroundJaillon, L., Poon, C. S., & Chiang, Y. H. (2009) · Waste Management · doi:10.1016/j.wasman.2008.02.015 · Cited by 592 · cited 2×
“Prefabrication has been identified as a solution to reduce waste generation during the building design and construction processes (Poon and Jaillon, 2002; Osmani et al ., 2006; Jaillon and Poon, 2008; Jaillon et al ., 2009).”
BackgroundSelf-citationJaillon, L., & Poon, C. S. (2008) · Construction Management and Economics · doi:10.1080/01446190802259043 · Cited by 405 · cited 4×
“Prefabrication has been identified as a solution to reduce waste generation during the building design and construction processes (Poon and Jaillon, 2002; Osmani et al ., 2006; Jaillon and Poon, 2008; Jaillon et al ., 2009).”
BackgroundInfluentialSelf-citationSupports, an alternative to mass housing
Habraken, N. J. (1972) · TU/e Research Portal · Cited by 359
Reducing building waste at construction sites in Hong Kong
Poon, C. S., Yu, A. T. W., & Jaillon, L. (2004) · Construction Management and Economics · doi:10.1080/0144619042000202816 · Cited by 298 · cited 1×
“Timber formwork accounts for about 30% of wastes identified in conventional construction, while wet trades and finishing works account for about 20% (Poon et al ., 2004).”
BackgroundSelf-citationChiang, Y.-H., Hon-Wan Chan, E., & Ka-Leung Lok, L. (2006) · Habitat International · doi:10.1016/j.habitatint.2004.12.004 · Cited by 218 · cited 1×
“Recently completed projects include innovative precast components such as volumetric bathrooms and kitchens (Chiang et al ., 2006; Tam, 2007).”
BackgroundKendall, S., & Teicher, J. (2010) · Spon Press eBooks · doi:10.4324/9780203056769 · Cited by 185 · cited 1×
“The term ‘open building system’ is well known and defines the principles of ordering and combining subsystems by which interference between subsystems is minimized (Kendall and Teicher, 2000; Yashiro, 2003).”
BackgroundAnderson, J., Shiers, D. E., & Sinclair, M. (2002) · Wiley eBooks · doi:10.1002/9780470690666 · Cited by 159 · cited 1×
“Life cycle is an important issue that is well documented in the literature (McDonaugh and Braungart, 2002; Kotaji et al ., 2003; Anderson et al ., 2009).”
Background
Cited by
Ferdous, W., Bai, Y., Ngo, T. D., Manalo, A., & Mendis, P. (2019) · Engineering Structures · doi:10.1016/j.engstruct.2019.01.061 · Cited by 681
Life cycle performance of modular buildings: A critical review
Kamali, M., & Hewage, K. (2016) · Renewable and Sustainable Energy Reviews · doi:10.1016/j.rser.2016.05.031 · Cited by 642
Barriers to promoting prefabricated construction in China: A cost–benefit analysis
Hong, J., Shen, G. Q., Li, Z., Zhang, B., & Zhang, W. (2018) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2017.10.171 · Cited by 503
Project sustainability strategies: A systematic literature review
Aarseth, W., Ahola, T., Aaltonen, K., Økland, A., & Andersen, B. (2017) · International Journal of Project Management · doi:10.1016/j.ijproman.2016.11.006 · Cited by 415
Key constraints and mitigation strategies for prefabricated prefinished volumetric construction
Hwang, B.-G., Shan, M., & Looi, K.-Y. (2018) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2018.02.136 · Cited by 318
Barriers of Implementing Modern Methods of Construction
Rahman, M. M. (2014) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000173 · Cited by 282
Ghisellini, P., Ji, X., Liu, G., & Ulgiati, S. (2018) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2018.05.084 · Cited by 244
Griffiths, S., Sovacool, B. K., Furszyfer Del Rio, D. D., Foley, A. M., Bazilian, M. D., Kim, J., & Uratani, J. M. (2023) · Renewable and Sustainable Energy Reviews · doi:10.1016/j.rser.2023.113291 · Cited by 222
Implementing on-site construction waste recycling in Hong Kong: Barriers and facilitators
Bao, Z., Lee, W. M. W., & Lu, W. (2020) · Science of The Total Environment · doi:10.1016/j.scitotenv.2020.141091 · Cited by 189
“Being one of the most densely populated regions in the globe, the spaces of construction sites in Hong Kong are usually limited (Jaillon and Poon, 2010).”
Barriers to Implementing the Circular Economy in the Construction Industry: A Critical Review
Charef, R., Morel, J.-C., & Rakhshan, K. (2021) · Sustainability · doi:10.3390/su132312989 · Cited by 188
“Specifically, issues related to late communications between the designer and contractor have been identified for RL, SB and PFA, where early collaboration between architects, contractors and manufacturers is required [51].”
BackgroundInfluentialGan, X., Chang, R., & Wen, T. (2018) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2018.07.299 · Cited by 186
Components reuse in the building sector – A systematic review
Rakhshan, K., Morel, J.-C., Alaka, H., & Charef, R. (2020) · Waste Management & Research: The Journal for a Sustainable Circular Economy · doi:10.1177/0734242x20910463 · Cited by 228
Design for Deconstruction in the Design Process: State of the Art
Kanters, J. (2018) · Buildings · doi:10.3390/buildings8110150 · Cited by 127
“Prefabrication will ease the construction of dry joint connections [20].”
BackgroundCharef, R., Lu, W., & Hall, D. (2022) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2022.132421 · Cited by 99
Metadata
- Authors
- Jaillon, L., & Poon, C.
- Venue
- Construction Management and Economics
- Publisher
- Informa UK Limited
- Published
- 2010-10
- Volume
- 28
- Issue
- 10
- Pages
- 1025-1042
- ISSN
- 0144-6193 (ISSN-L)
- 1466-433X
- OpenAlex
- W1964944757
- Cited by
- 189
- References
- 20
- FWCI
- 6.98
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.