Improving construction supply chain collaboration and performance: a lean construction pilot project
The DOI matches its Crossref record; 1 of the 1 references it cites were found in a registry or an index.
Abstract
Purpose: Improving construction supply chain collaboration and performance is central for achieving short‐term business objectives as well as long‐term competitive advantage. Lean thinking is an approach that has been adopted in many different industrial settings as a means for improving supply chain performance. In the project‐based construction industry, lean thinking has, however, not yet been widely adopted. The purpose of this paper is to increase the understanding of how various aspects of lean thinking can be implemented in a construction project and how they affect supply chain actors and their performance. Design/methodology/approach: Action research was performed in a case study of a lean construction pilot project. Empirical data were collected through three surveys and follow‐up workshops, document studies, and interviews of 12 project participants. Findings: The findings show that many of the lean‐related aspects identified in the literature review were utilized in the pilot project. These aspects have mostly focused on increasing the cooperation among supply chain actors, for which reason the pilot project is very similar to a partnering project. Hence, much work remains in order to obtain full‐fledged lean construction, but the pilot project may serve as a starting point for continuous improvements and development of lean construction in future projects. Research limitations/implications: The research results are based on one empirical case study for which reasonable generalisations could be made, albeit cautiously. Practical implications: The frame of reference can serve as an illustration of important aspects and core elements of lean construction and the case study findings show how various lean related aspects can be implemented and how they affect supply chain actors and their performance in a construction project context. Originality/value: The action research approach based on both qualitative and quantitative data collection in a lean construction pilot project provides a valuable opportunity to study both the process of implementing lean construction and its outcomes.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Pratt, M. G. (2009) · Academy of Management Journal · doi:10.5465/amj.2009.44632557 · Cited by 1,625
Cited by
A Systematic Literature Review on Recent Lean Research: State‐of‐the‐art and Future Directions
Danese, P., Manfè, V., & Romano, P. (2018) · International Journal of Management Reviews · doi:10.1111/ijmr.12156 · Cited by 345
Implementation of lean practices in the construction industry: A systematic review
Babalola, O., Ibem, E. O., & Ezema, I. C. (2019) · Building and Environment · doi:10.1016/j.buildenv.2018.10.051 · Cited by 270
Ogunbiyi, O., Goulding, J. S., & Oladapo, A. (2014) · Construction Innovation · doi:10.1108/ci-08-2012-0045 · Cited by 200
“Similarly, JIT has been identified as a major component of lean construction concept with the overall objective of ensuring that the correct quantities of materials are delivered to the exact location as at when needed (Eriksson, 2010).”
BackgroundPartnering in engineering projects: Four dimensions of supply chain integration
Eriksson, P. E. (2015) · Journal of Purchasing and Supply Management · doi:10.1016/j.pursup.2014.08.003 · Cited by 182
“, 2006; Johnsen, 2009) and many partnering arrangements mainly involve high managerial levels (Eriksson, 2010).”
BackgroundInfluentialZhang, L., Cao, T., & Wang, Y. (2018) · International Journal of Project Management · doi:10.1016/j.ijproman.2017.08.014 · Cited by 173
“, 2014), but also foster harmonious working relationships and important affective states crucial to long-term steady development (Eriksson, 2010; Chiocchio et al., 2011; Meng, 2012).”
BackgroundInfluential
Metadata
- Authors
- Erik Eriksson, P.
- Venue
- Supply Chain Management: An International Journal
- Publisher
- Emerald
- Published
- 2010-08-10
- Volume
- 15
- Issue
- 5
- Pages
- 394-403
- ISSN
- 1359-8546 (ISSN-L)
- OpenAlex
- W1996851732
- Cited by
- 246
- References
- 1
- FWCI
- 21.47
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.