A quantitative assessment of the cost and time impact of variation orders on construction projects
Abstract
Purpose Variation orders are a common occurrence in construction projects and their impacts have been studied by various authors. However, the contribution of project variations to construction cost and time overruns is yet to be established. The purpose of this study is to assess the significance of variations as a cause of cost and time overruns. Design/methodology/approach Using a questionnaire survey, responses were obtained from 50 project participants on the causes and effects of project variations. Cost and time data were also collected on 30 completed building projects. The analysis used importance indices and F‐ and t‐tests. The results indicated that variations had a significant effect and accounted for about 79 and 68 per cent of the cost and time overruns, respectively, for the projects studied. Findings The results indicated that variations had a significant effect on project cost and time overruns and accounted for about 79 and 68 per cent of the cost and time overruns, respectively, for the projects studied. Project type and size were found to have no significant effect on the contribution of variations to cost and time overruns. The results also showed that changes in specifications and scope, initiated mostly by project owners and their consultants, were the most prevalent sources of variation. Originality/value The results of this study indicates the cost and time significance of project. This will enable project owners, consultants, contractors and other stakeholders to better understand and appreciate the real impact of variations on project performance.
Overview
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
Claims other papers make about this one
Each is checked against this paper’s own text: does it say what the citing paper says it does?
Accountability and trust are issues involved with project implementation-related problems in developing countries.
“Espousing these views, and an in-depth observation, reveals that accountability and trust are the issues involved with project implementation-related problems in developing countries [11,12].”
From Blockchain Technology: Potential Applications for Public Sector E-Procurement and Project Management (2022) · cites this paper as [11]
Citations
Cites
Construction delays in a fast-growing economy: Comparing Thailand with other economies
Ogunlana, S. O., Promkuntong, K., & Jearkjirm, V. (1996) · International Journal of Project Management · doi:10.1016/0263-7863(95)00052-6 · Cited by 389
An evaluation of construction time performance in the building industry
Chan, D. W. M., & Kumaraswamy, M. M. (1996) · Building and Environment · doi:10.1016/0360-1323(96)00031-5 · Cited by 205
Quantitative Effects of Construction Changes on Labor Productivity
Thomas, H. R., & Napolitan, C. L. (1995) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(1995)121:3(290 · Cited by 192
Impact of Change Orders on Labor Efficiency for Electrical Construction
Hanna, A. S., Russell, J. S., Nordheim, E. V., & Bruggink, M. J. (1999) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(1999)125:4(224 · Cited by 174
Factors affecting housing maintenance cost
El‐Haram, M. A., & Horner, M. W. (2002) · Journal of Quality in Maintenance Engineering · doi:10.1108/13552510210430008 · Cited by 167
System Dynamics Modeling for Project Management
Sterman, J. D. (1992) · Cited by 158
Determinants of rework in building construction projects
Love, P. E. D., & Edwards, D. J. (2004) · Engineering Construction & Architectural Management · doi:10.1108/09699980410547612 · Cited by 140
Quantitative Definition of Projects Impacted by Change Orders
Hanna, A. S., Camlic, R., Peterson, P. A., & Nordheim, E. V. (2002) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2002)128:1(57 · Cited by 131
Dispute resolution management for international construction projects in China
Chan, E. H. W., & Suen, H. C. H. (2005) · Management Decision · doi:10.1108/00251740510593576 · Cited by 127
Construction related factors influencing the choice of concrete floor systems
Idrus, A., & Newman, J. B. (2002) · Construction Management and Economics · doi:10.1080/01446190110101218 · Cited by 120
Contracting for major projects: eight business levers for top management
von Branconi, C., & Loch, C. H. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(03)00014-0 · Cited by 94
ASSESSMENT OF BUILDING FAILURES IN NIGERIA: LAGOS AND IBADAN CASE STUDY
Ayininuola, G. M., & Olalusi, O. (2005) · African Journal of Science and Technology · doi:10.4314/ajst.v5i1.15321 · Cited by 72
Construction Project Administration in Practice
Kwakye, A. A. (2016) · Routledge eBooks · doi:10.4324/9781315841595 · Cited by 70
The business environment of the construction industry in Nigeria
Aniekwu, A. N. (1995) · Construction Management and Economics · doi:10.1080/01446199500000052 · Cited by 56
Impact of Change Orders on Small Labor-Intensive Projects
Hanna, A. S., & Gündüz, M. (2004) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2004)130:5(726 · Cited by 56
Fast-Tracking's Impact on Project Change
Ibbs, C. W., Lee, S. A., & Li, M. I. (1998) · Project Management Journal · doi:10.1177/875697289802900405 · Cited by 52
Statistical-Fuzzy Approach to Quantify Cumulative Impact of Change Orders
Hanna, A. S., Lotfallah, W. B., & Lee, M.-J. (2002) · Journal of Computing in Civil Engineering · doi:10.1061/(asce)0887-3801(2002)16:4(252 · Cited by 51
Cost–time performance of public sector housing projects in Nigeria
Okuwoga, A. A. (1998) · Habitat International · doi:10.1016/s0197-3975(98)00014-9 · Cited by 45
Contract Practice for Surveyors
Birchall, S., & Ramus, J. W. (2007) · Routledge eBooks · doi:10.4324/9780080476858 · Cited by 44
Introducing a New Concept and Approach to Modeling Construction
Kartam, S., Ballard, G., & Ibbs, C. W. (1997) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(1997)123:1(89 · Cited by 43
Arain, F. M. (2005) · Project Management Journal · doi:10.1177/875697280503600408 · Cited by 31
An Economic Analysis of the Effect of Delays on Project Costs
Tse, R. Y. C., & Love, P. E. D. (2003) · Journal of Restructuring Finance · doi:10.1142/s1609945103000376 · Cited by 11
Flagged first, then by citations
1 of the 23 references couldn’t be matched to a known paper.
Research works printed but not linked: 16
- Adeyemi, A.Y., Oladapo, A.A. and Akindele, O. (2005), “Balancing globalisation, glocalisation and the sustainable development equation in the Nigerian construction industry”, paper presented at 3rd Postgraduate Conference, Johannesburg, 9‐11 October.
- AfDB/OECD (2004), “African economic outlook”, pp. 247‐60, available at: www.chathamhouse.org.uk/pdf/research/Africa/NIGERIA.pdf.
- Baxendale, A.T. and Schofield, T.J. (1986), “Planning and progressing project variations”, in Langford, D.A. and Retik, A. (Eds), The Organization and Management of Construction: Shaping Theory and Practice, Vol. 2, E&FN SPON, London.
- Cambridge Systematics, Inc. (1998), “Department of transportation, highways and rail programs performance audit”, Report 98‐2, Cambridge Systematics, Inc., Cambridge, MA.
- Elhag, T.M.S. and Boussabaine, A.H. (1999), “Evaluation of construction costs and time attributes”, Proceedings of the 15th ARCOM Conference, Liverpool John Moores University, 15‐17 September, Vol. 2, pp. 473‐80.
- Gbeleyi, S.A. (2002), “An evaluation of the causes and effects of variation on building project execution in Nigeria”, unpublished BSc dissertation, Department of Quantity Surveying, Obafemi Awolowo University, Ile‐Ife.
- Morris, P.W.G. (1998), “Why project management doesn't always make business sense”, Project Management, Vol. 4 No. 1, pp. 12‐16.
- Motete, L., Mbachu, J. and Nkado, R. (2003), “An investigation into material wastages on building sites”, Proceedings of CIDB 1st Postgraduate Conference, Port Elizabeth, South Africa, pp. 288‐95.
- Odeyinka, H.A. and Yusif, A. (1997), “The causes and effects of construction delays on completion cost of housing projects in Nigeria”, Journal of Financial Management of Property and Construction, Vol. 2 No. 3, pp. 31‐44.
- Oma‐Williams, O.W. (1991), “Reorganising for project management in Nigeria”, The Nigerian Quantity Surveyor, Vol. 13, pp. 5‐8.
- Revay, S.O. (2002), “Coping with extras”, The Revay Report, Vol. 21.
- Smallwood, J. (2000), “Contractor performance: clients' perceptions”, Proceedings of 2nd International Conference on Construction in Developing Countries: Challenges facing the Construction Industry in Developing Countries, Gaborone Botswana, available at: http://buildnet.csir.co.za/cdcproc/docs/2nd_proceedings.html#key (accessed 15‐17 November).
- Ssegawa, J.K., Mfolwe, K.M., Makuke, B. and Kutua, B. (2002), “Construction variations: a scourge or a necessity”, Proceedings of the 1st CIB‐W107 International Conference on Creating a Sustainable Construction Industry in Developing Countries, Cape Town, South Africa, available at www.odsf.co.za/cdcproc/docs/3rd/ssegawa_jk_mfolwe_km.pdf (accessed 11‐13 November).
- Sutrisna, M., Potts, K. and Buckley, K. (2003), “An expert system as a potential decision‐making tool in the valuation of variations”, Proceedings of The RICS Foundation Construction and Building Research Conference (COBRA), 1‐2 September, University of Wolverhampton, Wolverhampton.
- Weisfeld, M. and Ciccozzi, J. (1999), “Software project management software by committee”, Project Management, Vol. 5 No. 1, pp. 30‐6.
- Zaneldin, E. (2005), “Construction claims in the United Arab Emirates: causes, severity, and frequency”, Proceedings of The Sixth Annual UAE University Research Conference, pp ENG 96‐ENG 105, available at: http://195.229.164.112/Conference_6/Proceedings/PDF/Engineering/ENG_12.pdf.
Cited by
Sorted by citations
Significant Factors Causing Cost Overruns in Large Construction Projects in Malaysia
Rahman, I. B. A., Hameed, A., & Karim, A. T. A. (2013) · Journal of Applied Sciences · doi:10.3923/jas.2013.286.293 · Cited by 192
Preliminary Study on Causative Factors Leading to Construction Cost Overrun
Memon, A. H., Rahman, I. B. A., & Azis, A. A. A. (2011) · International Journal of Sustainable Construction Engineering Technology · Cited by 128
Arefazar, Y., Nazari, A., Hafezi, M. R., & Maghool, S. A. H. (2019) · International Journal of Construction Management · doi:10.1080/15623599.2019.1644757 · Cited by 113
Design Changes in Construction Projects – Causes and Impact on the Cost
Aslam, M., Baffoe-Twum, E., & Saleem, F. (2019) · Civil Engineering Journal · doi:10.28991/cej-2019-03091360 · Cited by 89
Key constraints to labour productivity in residential building projects: evidence from Cambodia
Durdyev, S., & Mbachu, J. (2017) · International Journal of Construction Management · doi:10.1080/15623599.2017.1326301 · Cited by 76
Determinants of construction labour productivity in Oman
Jarkas, A. M., Balushi, R. A. A., & Raveendranath, P. K. (2015) · International Journal of Construction Management · doi:10.1080/15623599.2015.1094849 · Cited by 74
An Assessment of Material Waste Disposal Methods in the Nigerian Construction Industry
Ogunmakinde, O. E., Sher, W., & Maund, K. (2019) · Recycling · doi:10.3390/recycling4010013 · Cited by 73
Relationship between Factors of Construction Resources Affecting Project Cost
Rahman, I. B. A., Memon, A. H., & Karim, A. T. A. (2012) · Modern Applied Science · doi:10.5539/mas.v7n1p67 · Cited by 62
Blockchain Technology: Potential Applications for Public Sector E-Procurement and Project Management
Khalfan, M., Azizi, N., Haass, O., Maqsood, T., & Ahmed, I. (2022) · Sustainability · doi:10.3390/su14105791 · Cited by 57
“Espousing these views, and an in-depth observation, reveals that accountability and trust are the issues involved with project implementation-related problems in developing countries [11,12].”
BackgroundAnalysis of causes and impact of variation order on educational building projects
Oyewobi, L. O., Jimoh, R. A., Ganiyu, B. O., & Shittu, A. A. (2016) · Journal of Facilities Management · doi:10.1108/jfm-01-2015-0001 · Cited by 52
Effect of Change Orders on Cost and Schedule Overruns of School Building Renovation Projects
Shrestha, P. P., & Zeleke, H. B. (2018) · Journal of Legal Affairs and Dispute Resolution in Engineering and Construction · doi:10.1061/(asce)la.1943-4170.0000271 · Cited by 42
Open innovation in process industries: a lifecycle perspective on development of process equipment
Sjödin, D., Eriksson, P. E., & Frishammar, J. (2011) · International Journal of Technology Management · doi:10.1504/ijtm.2011.042984 · Cited by 44
Ebekozien, A., Aigbavboa, C. O., Thwala, W. D., Aigbedion, M., & Ogbaini, I. F. (2021) · Journal of Engineering Design and Technology · doi:10.1108/jedt-09-2021-0453 · Cited by 37
Asiedu, R. O., Adaku, E., & Owusu‐Manu, D. (2017) · Construction Innovation · doi:10.1108/ci-01-2016-0003 · Cited by 33
An IPD-based incentive mechanism to eliminate change orders in construction projects in China
Ma, J., Ma, Z., & Li, J. (2017) · KSCE Journal of Civil Engineering · doi:10.1007/s12205-017-0957-3 · Cited by 32
Fathi, M., Shrestha, P. P., & Shakya, B. (2019) · Journal of Legal Affairs and Dispute Resolution in Engineering and Construction · doi:10.1061/(asce)la.1943-4170.0000353 · Cited by 29
Variation orders on construction projects: value-adding or waste?
Ndihokubwayo, R., & Haupt, T. C. (2009) · Cited by 29
Investigating the major causes of scope creep in real estate construction projects in Ghana
Amoatey, C. T., & Anson, B. A. (2017) · Journal of Facilities Management · doi:10.1108/jfm-11-2016-0052 · Cited by 28
Managing project scope creep in construction industry
Ajmal, M. M., Khan, M., Gunasekaran, A., & Helo, P. (2021) · Engineering Construction & Architectural Management · doi:10.1108/ecam-07-2020-0568 · Cited by 27
Impact of Design Errors on Variation Cost of Selected Building Project in Nigeria
DOSUMU, O. S., & Aigbavboa, C. O. (2017) · Procedia Engineering · doi:10.1016/j.proeng.2017.08.016 · Cited by 27
Factors leading to design changes in Jordanian construction projects
Gharaibeh, L., Matarneh, S. T., Arafeh, M., & Sweis, G. J. (2020) · International Journal of Productivity and Performance Management · doi:10.1108/ijppm-08-2019-0412 · Cited by 26
Brandstetter, M. C. G. D. O., & Ribeiro, H. R. D. O. E. (2019) · Ambiente Construído · doi:10.1590/s1678-86212020000100362 · Cited by 25
DOSUMU, O. S., & Aigbavboa, C. (2018) · Acta Structilia · doi:10.18820/24150487/as25i1.2 · Cited by 24
Factors affecting the selection of effective cost control techniques in the UK construction industry
Oyegoke, A. S., Powell, R., Ajayi, S. O., Godawatte, G. A. G. R., & Akenroye, T. O. (2021) · Journal of Financial Management of Property and Construction · doi:10.1108/jfmpc-07-2020-0050 · Cited by 21
Govender, K., Nyagwachi, J., Smallwood, J. J., & Allen, C. J. (2018) · International Journal of Sustainable Development and Planning · doi:10.2495/sdp-v13-n1-121-129 · Cited by 20
A Study on Factors Influencing Cost Overrun in High-rise Building Construction across India
Tayyab, M., Furkhan, M., Rizwan, M., Jameel, M., & Chadee, A. A. (2023) · Journal of Smart Buildings and Construction Technology · doi:10.30564/jsbct.v5i1.5489 · Cited by 19
Causes of project cost overruns within the Ghanaian road construction sector
Chileshe, N., & Berko, P. D. (2010) · Adelaide Research & Scholarship (AR&S) (University of Adelaide) · Cited by 19
An analysis of the impact of variation orders on project performance
Ndihokubwayo, R. (2008) · Cited by 19
Muianga, E. A. D., Granja, A. D., & Ruiz, J. D. A. (2015) · Ambiente Construído · doi:10.1590/s1678-86212015000100008 · Cited by 18
Current practice of variation order management in the Saudi construction industry
Alsuliman, J. A., Bowles, G., & Chen, Z. (2012) · Cited by 18
Do, S. T., Nguyen, V. T., & Nguyen, N. H. (2022) · Engineering Construction & Architectural Management · doi:10.1108/ecam-01-2022-0066 · Cited by 17
Memon, A. H., Rahman, I. B. A., & Azis, A. A. (2013) · UTHM Institutional Repository (Universiti Tun Hussein Onn Malaysia) · Cited by 16
Kim, M.-H., & Lee, E. (2019) · Energies · doi:10.3390/en12122295 · Cited by 15
Changing needs and demand of clients vs ability to pay in architectural industry
Mba, E. J., Okeke, F. O., Igwe, A. E., Ebohon, O. J., & Awe, F. C. (2025) · Journal of Asian Architecture and Building Engineering · doi:10.1080/13467581.2025.2455039 · Cited by 12
Hove, G., & Banjo, A. (2018) · Acta Commercii · doi:10.4102/ac.v18i1.528 · Cited by 14
Evaluating the Causes and Impact of Change Orders on Construction Projects Performance in Oman
Maamari, A. A., & Khan, F. R. (2021) · International Journal of Research in Entrepreneurship and Business Studies · doi:10.47259/ijrebs.215 · Cited by 12
Application of PLS-SEM to Assess the Influence of Construction Resources on Cost Overrun
Rahman, I. B. A., Memon, A. H., Abdullah, N. H., & Azis, A. A. A. (2013) · Applied Mechanics and Materials · doi:10.4028/www.scientific.net/amm.284-287.3649 · Cited by 11
Babatunde, S. O., Awodele, O. A., & Adeniyi, O. (2018) · Journal of Financial Management of Property and Construction · doi:10.1108/jfmpc-07-2017-0025 · Cited by 11
CAUSES OF VARIATION ORDER IN BUILDING AND CIVIL ENGINEERING PROJECTSIN NIGERIA
Muhammad, N. Z., Keyvanfar, A., Majid, M. Z. A., Shafaghat, A., Aliyu, M. M., & Dankaka, N. S. (2015) · Jurnal Teknologi · doi:10.11113/jt.v77.6404 · Cited by 11
Babatunde, S. O., Perera, S., Udeaja, C. E., & Zhou, L. (2014) · International Journal of Architecture Engineering and Construction · doi:10.7492/ijaec.2014.012 · Cited by 11
Cost impacts of variations on building construction projects
Mustapha, Z., Akomah, B. B., Mensah, J. W., & Kottey, S. (2018) · MOJ Civil Engineering · doi:10.15406/mojce.2018.04.00133 · Cited by 10
Management of variations in the public-sector building construction projects in Sri Lanka
Perera, B. A. K. S., Sirimewan, D. C., & Senadeera, A. (2021) · Journal of Engineering Design and Technology · doi:10.1108/jedt-08-2020-0339 · Cited by 10
Babatunde, S. O. (2013) · International Journal of Sustainable Construction Engineering Technology · Cited by 9
Poka-Yoke to minimise variations: a framework for building projects
Nadeeshan Uhanovita, A. C., Ranadewa, K. A. T. O., & Parameswaran, A. (2023) · Construction Innovation · doi:10.1108/ci-12-2022-0343 · Cited by 9
Investigation of Organizational and Regional Perceptions on the Changes in Construction Projects
İlter, O., & Çelik, T. (2020) · Turkish Journal of Civil Engineering · doi:10.18400/tekderg.595995 · Cited by 9
Effective Framework for Change Order Management Using Analytical Hierarchy Process (AHP)
Gündüz, M., & Khan, O. H. (2018) · Qatar University QSpace (Qatar University) · Cited by 9
Factors Contributing to Delay of Interim Payment in Civil Engineering Projects
Ismail, W. N. W., Adnan, H., Azmi, W. F. W. M., Yusop, N., & Isa, S. S. M. (2023) · International Journal of Technology · doi:10.14716/ijtech.v14i4.3370 · Cited by 8
Causas da variabilidade do tempo de execução dos processos em diferentes sistemas construtivos
Cruz, H. M., Santos, D. D. G., & Mendes, L. A. (2017) · Ambiente Construído · doi:10.1590/s1678-86212018000100209 · Cited by 8
Odubiyi, T. B., Aigbavboa, C. O., & Thwala, W. D. (2019) · IOP Conference Series Materials Science and Engineering · doi:10.1088/1757-899x/640/1/012025 · Cited by 8
Application of Linguistic Clustering to Define Sources of Risks in Technical Projects
Kifokeris, D., & Xenidis, Y. (2017) · ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems Part A Civil Engineering · doi:10.1061/ajrua6.0000938 · Cited by 7
Shugran, A. A., & Ghazali, F. E. M. (2024) · International Journal of Construction Management · doi:10.1080/15623599.2024.2337238 · Cited by 7
Variation Negotiation in PPP Toll-Road Projects: Option Approach
Nguyen, T. A., & Sun, Y. (2021) · Journal of Legal Affairs and Dispute Resolution in Engineering and Construction · doi:10.1061/(asce)la.1943-4170.0000495 · Cited by 7
The Cost Drivers of Infrastructure Projects: Definition, Classification, and Conceptualization
Watton, J., Unterhitzenberger, C., Locatelli, G., & Invernizzi, D. C. (2023) · Journal of Construction Engineering and Management · doi:10.1061/jcemd4.coeng-13411 · Cited by 7
Change Order Management in Nigeria: The Current Context
Kolawole, R. A., Kamau, K., & Munala, G. K. (2015) · Journal of Management Research · doi:10.5296/jmr.v7i5.8457 · Cited by 6
Al-Musleh, A. M. (2011) · OpenGrey (Institut de l'Information Scientifique et Technique) · Cited by 6
Risk assessment of time and cost overrun factors throughout construction project lifecycle
Ismail, I. (2014) · UTHM Institutional Repository (Universiti Tun Hussein Onn Malaysia) · Cited by 6
Alsohiman, N. K., Alattyih, W., & Haider, H. (2023) · CivilEng · doi:10.3390/civileng4040061 · Cited by 5
Ujene, A. O., & Umoh, A. A. (2017) · Journal of Civil Engineering Science and Technology · doi:10.33736/jcest.374.2017 · Cited by 5
Towards a new policy direction for an improved housing delivery system in Nigerian cities
Gbadegesin, J. T. (2018) · Architecture and the Built Environment · doi:10.59490/abe.2018.17.2526 · Cited by 5
Al-Btoosh, J. A. A. (2021) · Journal of Advanced Sciences and Engineering Technologies · doi:10.32441/jaset.04.01.05 · Cited by 5
Qasem, A. (2025) · Buildings · doi:10.3390/buildings15081246 · Cited by 4
Dickson, O. D., & Wanyona, G. (2014) · Cited by 4
Muianga, E. A. D., Granja, A. D., & Ruiz, J. D. A. (2014) · International Conference on Engineering, Project, and Production Management (EPPM) · doi:10.32738/ceppm.201411.0002 · Cited by 4
Ranking delay, cost, quality factors for project success in real estate companies
(2017) · International Journal of Latest Trends in Engineering and Technology · doi:10.21172/1.841.45 · Cited by 3
Change Order Management Factors in Building Projects in Northern Nigeria
Kolawole, R. A., Peter, K. K., & Munala, G. K. (2015) · Asian Social Science · doi:10.5539/ass.v12n1p223 · Cited by 3
Analysis of the category of variation order in x project at XYZ ltd
Suprapto, A. A., & Wiguna, I. P. A. (2020) · IOP Conference Series Materials Science and Engineering · doi:10.1088/1757-899x/930/1/012021 · Cited by 3
Mashamba, M. T., Kanakana-Katumba, M., & Maladzhi, R. W. (2023) · The South African Journal of Industrial Engineering · doi:10.7166/34-4-2898 · Cited by 3
Cloud Computing – Architecture, Platform and Security Issues: A Survey
Alam, M. S. B. (2017) · World Scientific News · Cited by 3
Impact of variation on project delivery in Oyo state, Nigeria
Bello, A. M., & Saka, A. B. (2017) · Leeds Beckett Repository (Leeds Beckett University) · Cited by 3
Comparative Study of Price Variations of Basic Civil Engineering Construction Materials
Oginni, F. A., Ogunbiyi, M. A., & Balogun, S. O. (2014) · Energy and Environment Research · doi:10.5539/eer.v4n3p50 · Cited by 2
Albtoosh, H. A. M., & Alkhamis, T. M. (2021) · American Journal of Industrial and Business Management · doi:10.4236/ajibm.2021.114021 · Cited by 2
Waste reduction through lean and agile thinking - the case of variation orders
Ndihokubwayo, R. (2010) · Cited by 2
Alsuliman, J. A. (2014) · Cited by 2
Shimete, M., & Wall, K. (2017) · UpSpace Institutional Repository (University of Pretoria) · Cited by 2
Omotayo, T. (2017) · University of Salford Institutional Repository (University of Salford) · doi:10.13140/rg.2.2.19422.77121 · Cited by 2
Benefits and barriers for poka-yoke implementation to minimise variations in construction projects
Uhanovita, A. C. N., Ranadewa, K. A. T. O., & Parameswaran, A. (2023) · FARU Journal · doi:10.4038/faruj.v10i1.181 · Cited by 1
Hashemifar, A., Feili, A., Ahadi, N., & Sorooshian, S. (2025) · Springer proceedings in business and economics · doi:10.1007/978-981-96-4116-1_13 · Cited by 1
Impact of Variation Orders on Construction Project Cost and Time
Msiska, U., Mashwama, N. X., & Thwala, D. (2022) · International Conference on Industrial Engineering and Operations Management (IEOM) · doi:10.46254/af03.20220033 · Cited by 1
Controlling the Risk of Construction Delay in the Middle East: State-of-the-Art Review
Motaleb, O. H., & Kishk, M. (2015) · Journal of Civil Engineering and Architecture · doi:10.17265/1934-7359/2015.05.002 · Cited by 1
Adindu, C. C., Yisa, S. N., Yusuf, S. O., Makinde, J. K., & Kamilu, A. M. (2020) · Journal of Art Architecture and Built Environment · doi:10.32350/jaabe.31.01 · Cited by 1
Benefits of Using Confidence Intervals in Reports of Project Cost Overrun
Mejía, G., Bohórquez-Castellanos, J. J., & Rivera, T. E. (2020) · ASCE Construction Research Congress (CRC) · doi:10.1061/9780784482889.075 · Cited by 1
Impact of Change Orders on Construction Project Performance
Shrivastav, S., & Kansal, R. (2015) · Recent Trends in Civil Engineering & Technology
Quantitative Analysis of the Effects of Variations in Public Building Projects
Mhando, Y. B., Mlinga, R. S., & Alinaitwe, H. M. (2017) · International Journal of Construction Engineering and Management
Change management capability assessment model for construction organizations
Arowosegbe, A. A. (2016)
Las variaciones en los contratos de construcción: precisiones sobre su noción y causas
Rebaza, W. H. V. (2018) · IUS ET VERITAS · doi:10.18800/iusetveritas.201802.003
Subsídios ao gerenciamento de risco na contratação de obras públicas
de Oliveira, M., Marchiori, F. F., Brandstetter, M. C. G. D. O., & Ribeiro, H. R. D. O. E. (2021) · Simpósio Brasileiro de Gestão e Economia da Construção/Anais do ... Simpósio Brasileiro de Gestão e Economia da Construção · doi:10.46421/sibragec.v12i00.483
Impact of Variation on the Cost Performance of Public Building Projects in Birnin Kebbi, Nigeria
Muhammad, U., Jimoh, A. A. K., Kebbi, U. M. B., & Abdullahi, H. (2021) · International Journal of Innovative Research and Development · doi:10.24940/ijird/2021/v10/i11/nov21041
Consultant’s Role in Minimizing The Occurance of Variation Order
Ismail, N., Aziz, T. N. H. T. A., Zain, N. M., Shuib, M. N., & Hasbullah, M. N. (2022) · International Journal of Academic Research in Business and Social Sciences · doi:10.6007/ijarbss/v12-i11/14479
Causes and Effects of Variation Orders on Building Construction Projects in Kingdom of Bahrain
mannai, N. A., & ASuliman, S. M. (2021) · International Journal of Science and Research (IJSR) · doi:10.21275/sr201108112857
O'Rourke, J. T., Coughlan, C., Spillane, J. P., & Bradley, J. (2025) · Springer eBooks · doi:10.1007/978-3-031-73947-7_17
Rifu, S. P., Ghuzdewan, T. A., & Nugroho, A. S. B. (2025) · Jurnal Locus Penelitian dan Pengabdian · doi:10.58344/locus.v4i12.4843
Key Factors Leading to Disputes in the Final Account Closing of Construction Projects in Malaysia
Othman, M. K. F., Judi, S. S., Ismail, Z., Rais, S. L. A., & Pheng, L. S. (2025) · Journal of Construction in Developing Countries · doi:10.21315/jcdc.2025.30.s1.1
Amadi Kelechi, A., & Ihuah Paulinus, W. (2025) · MOJ Ecology & Environmental Sciences · doi:10.15406/mojes.2025.10.00365
Awodele, I. A., Ramabodu, M., & Olatunde, N. A. (2026) · African Journal of Inter/Multidisciplinary Studies · doi:10.66756/ajims.v8i2.2988
Metadata
- Authors
- Oladapo, A. A.
- Affiliations
- University of KwaZulu-Natal (ZA)
- Corresponding author
- Oladapo, A.A.
- Venue
- Journal of Engineering, Design and Technology
- Publisher
- Emerald
- Published
- 2007-04-03
- Volume
- 5
- Issue
- 1
- Pages
- 35-48
- ISSN
- 1726-0531 (ISSN-L)
- OpenAlex
- W2074309917
- Cited by
- 93
- References
- 23
- Citations by year
- 2026: 1 · 2025: 5 · 2024: 1 · 2023: 7 · 2022: 4 · 2021: 10 · 2020: 5 · 2019: 7 · 2018: 9 · 2017: 16 · 2016: 2 · 2015: 7 · 2014: 6 · 2013: 4 · 2012: 2
- FWCI
- 1.91
- Type
- journal article
- Language
- en
- Open access
- closed
- Locations
- Journal of Engineering Design and Technology (publishedVersion)
- Topics
- Social Sciences › Decision Sciences › Management Science and Operations Research › Construction Project Management and Performance
- Social Sciences › Business, Management and Accounting › Strategy and Management › Value Engineering and Management
- Physical Sciences › Engineering › Building and Construction › BIM and Construction Integration
- Keywords
- change orders, construction cost overruns, construction time overruns, specification changes, scope changes, project performance, construction projects
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review