Strategy development using TOWS matrix for international project risk management based on prioritization of risk categories
The DOI matches its Crossref record; 3 of the 3 references it cites were found in a registry or an index.
Abstract
Purpose: International projects very commonly experience failure due to various factors at the global level. Especially, large projects at the international level virtually have no chance of meeting scope, time, cost and quality. This fact has been underlined by most of the international surveys and published literature. Effective risk management plays a vital role in preventing projects from failure by implementing appropriate risk response strategies. The success of risk management will be based on the understanding of various risk categories which specifically affect international projects, analysis of their interdependence, prioritize them according to their importance and develop strategies for risk management based on the prioritization. The paper aims to discuss these issues. Design/methodology/approach: This paper represents typical eight risk categories frequently observed in the international projects through literature survey and feedback from project professionals. Interpretive structural modeling (ISM) and Matrice d’Impacts croises-multiplication applique´ an classment (MICMAC) analysis have been used to analyze the interactions among the risk categories and prioritize them. The strategy management tool threats, opportunities, weaknesses and strengths (TOWS) matrix has been used to develop the strategies for effective project risk management. Findings: The analysis represents political risks, contractual and legal risks, cultural risks, and financial and economic risks as the highest priority risk categories, the mitigation of which should be paid the highest attention. The strengths-threats strategy has been applied to develop the strategies by identifying the various internal strengths of project organization to overcome the various threats caused by the eight risk categories observed in international projects. Research limitations/implications: This paper tries to represent the prioritization of international project risk categories which are generic in nature. For any specific international project, the risk categories as well as their prioritization may be slightly varying. The tool used for prioritization; Interpretive structural modeling (ISM) is more suitable for few numbers of variables as it becomes complex as the number of variables increases. The strengths and threats considered for developing strategies using TOWS matrix are based on the feedback from project professionals and may vary according to the nature of project. Originality/value: This paper uses ISM and MICMAC for risk prioritization in international projects and TOWS matrix for developing risk management strategies. This may trigger new opportunities for in-depth research in the risk management strategy development for international projects.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Risk assessment and risk management: Review of recent advances on their foundation
Aven, T. (2016) · European Journal of Operational Research · doi:10.1016/j.ejor.2015.12.023 · Cited by 1,713
The TOWS matrix—A tool for situational analysis
Weihrich, H. (1982) · Long Range Planning · doi:10.1016/0024-6301(82)90120-0 · Cited by 1,178
Eybpoosh, M., Dikmen, I., & Talat Birgonul, M. (2011) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000382 · Cited by 217
Cited by
Rane, S. B., & Thakker, S. V. (2019) · Management of Environmental Quality: An International Journal · doi:10.1108/meq-06-2019-0136 · Cited by 151
Self-citationRane, S. B., Narvel, Y. A. M., & Bhandarkar, B. M. (2019) · Business Process Management Journal · doi:10.1108/bpmj-07-2017-0196 · Cited by 60
Self-citationRisk assessment of construction projects using Monte Carlo simulation
Qazi, A., & Simsekler, M. C. E. (2021) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-03-2020-0097 · Cited by 41
Metadata
- Authors
- Dandage, R. V., Mantha, S. S., & Rane, S. B.
- Venue
- International Journal of Managing Projects in Business
- Publisher
- Emerald
- Published
- 2019-12-02
- Volume
- 12
- Issue
- 4
- Pages
- 1003-1029
- ISSN
- 1753-8378 (ISSN-L)
- OpenAlex
- W2922856306
- Cited by
- 62
- References
- 3
- FWCI
- 5.90
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
How to cite
Cite CoChat for the checks on this page, and the paper for its own findings.
- This page
- CoChat. (2026). Citation check: Strategy development using TOWS matrix for international project risk management based on prioritization of risk categories. https://app.cochat.ai/papers/10.1108/ijmpb-07-2018-0128
- The paper
- Dandage, R. V., Mantha, S. S., & Rane, S. B. (2019). Strategy development using TOWS matrix for international project risk management based on prioritization of risk categories. International Journal of Managing Projects in Business. https://doi.org/10.1108/ijmpb-07-2018-0128
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.