Improving Project Budget Estimation Accuracy and Precision by Analyzing Reserves for Both Identified and Unidentified Risks

Kwon, Hyukchun, Kang, Chang Wook·2019·Project Management Journal

Abstract

Project risk is a critical factor in estimating project budget. Previous studies on this topic have only addressed estimation methods that consider project budget reserves against identified risks. As a result, project managers still face the challenge of completing projects within given budgets but without the relevant tools to deal with unidentified risks. This study proposes an approach for estimating reserves for both identified and unidentified risks separately. The study also suggests using the three-point estimation technique and R-value determination for estimating risk costs, which can improve budget accuracy and precision. The construction of residential building projects in South Korea demonstrates the advantages of the proposed approach compared with previous methods.

Overview

Integrity signals

Registry

Crossref · 10.1177/8756972818810963

Cites

Statistics

Recomputing p-values needs the paper’s full text.

Verification

Claims the paper makes

This paper’s full text isn’t openly available, so its claims and self-check weren’t run. The registry and citation checks still apply.

Claims other papers make about this one

Each is checked against this paper’s own text: does it say what the citing paper says it does?

Citations

Cites

No references could be resolved yet.

Research works printed but not linked: 56

  1. 10.1002/pmj.21545 · DOI
  2. 10.1016/S0263-7863(02)00028-5 · DOI · Paper page
  3. 10.1016/j.aej.2012.11.004 · DOI
  4. Baccarini D., 2006, Proceedings of the Australasian University building educators association annual conference 2006: 31st Annual Conference, 11–14 July 2006
  5. 10.1016/j.jss.2008.03.059 · DOI
  6. 10.1061/(ASCE)0742-597X(2007)23:3(140) · DOI
  7. Becker T. V., Jaselskis E. J., El-gafy M. (2014). Improving predictability of construction project outcomes through intentional management of indirect construction costs. Journal of Construction Engineering and Management, 140(6), 401–414. doi: http://dx.doi.org:10.1061/(ASCE) · DOI
  8. Bedarida S., 2012, Cost Engineering-Morgantown, 54, 27
  9. 10.1061/(ASCE)CO.1943-7862.0000225 · DOI
  10. Book S. A., 2007, Allocating risk dollars back to individual cost elements
  11. 10.1002/pmj.21303 · DOI
  12. 10.1016/S0965-9978(01)00036-9 · DOI
  13. 10.3130/jaabe.10.437 · DOI
  14. Chapman C., 2000, Project risk management—The required transformations to become project uncertainty management
  15. 10.1016/j.sepro.2012.01.004 · DOI
  16. Clark D. E., 2001, Cost Engineering, 43, 40
  17. 10.1061/(ASCE)CO.1943-7862.0000160 · DOI
  18. 10.1016/j.ijproman.2006.12.002 · DOI
  19. 10.1061/(ASCE)CO.1943-7862.0000621 · DOI
  20. 10.1016/j.ijproman.2011.10.004 · DOI
  21. 10.1016/j.aej.2014.09.008 · DOI
  22. 10.1016/S0263-7863(98)00078-7 · DOI
  23. 10.1108/13664380910977592 · DOI
  24. 10.1080/01944360208976273 · DOI
  25. 10.1016/S0263-7863(02)00055-8 · DOI
  26. 10.1080/1941658X.2008.10462211 · DOI
  27. 10.1016/j.ijproman.2012.11.001 · DOI
  28. 10.1002/pmj.21512 · DOI
  29. 10.1016/j.eswa.2010.07.061 · DOI
  30. Kasimu M., 2012, Institute of Interdisciplinary Journal of Contemporary Research in Business, 3, 775
  31. Ke Y. J., 2013, Journal of Financial Management of Property and Construction, 1, 6
  32. 10.1016/j.ijproman.2014.01.001 · DOI
  33. Kim G. H., 2004, Building and Environment, 34, 34
  34. 10.1109/52.589239 · DOI
  35. 10.1080/0144619042000326710 · DOI
  36. 10.1016/j.autcon.2007.10.007 · DOI
  37. Nawaz T., 2013, Industrial Engineering Letters, 3, 19
  38. 10.11591/ijaas.v1i1.537 · DOI
  39. Moselhi O., 1997, Risk assessment and contingency estimating
  40. 10.1061/(ASCE)0733-9364(2001)127:3(173) · DOI
  41. Pfleeger S. L., 2006, Software engineering, theory and practice
  42. Project Management Institute (PMI), 2013, A guide to the project management body of knowledge (PMBOK® guide) –
  43. 10.1016/j.ijproman.2006.11.007 · DOI
  44. 10.1016/j.ijproman.2012.04.002 · DOI
  45. Schwartz M., 2010, The Nunn-McCardy act: Background, analysis, and issues for Congress
  46. Smith P., 2014, Social and Behavior Sciences, 119, 485
  47. Smith P. G., 2002, Proactive risk management
  48. Sweis G. H., 2013, Journal of American Science, 9, 134
  49. Tabish S., 2011, Important factors for the success of public construction projects. 2nd International Conference on Construction and Project Management IPEDR (15)
  50. 10.1002/pmj.21325 · DOI
  51. Thomson P. A., 1992, Engineering construction risks
  52. U.S. Government Accountability Office, 2013, Reports to congressional committees, NASA assessment of selected large-scale projects (GAO-13-276SP)
  53. 10.1016/j.ijproman.2012.12.002 · DOI
  54. 10.1002/pmj.21558 · DOI
  55. Xenidis Y., 2013, Social and Behavior Sciences, 74, 478
  56. 10.1016/j.sepro.2011.08.041 · DOI

Cited by

Sorted by citations

Metadata

Authors
Kwon, H., & Kang, C. W.
Affiliations
Hanyang University (KR)
Corresponding author
Kwon, Hyukchun
Venue
Project Management Journal
Published
2018-11-29
Volume
50
Issue
1
Pages
86-100
ISSN
  • 1938-9507 (ISSN-L)
  • 8756-9728
OpenAlex
W2902201766
Cited by
50
References
0
Citations by year
2026: 4 · 2025: 5 · 2024: 18 · 2023: 8 · 2022: 8 · 2021: 3 · 2020: 3 · 2019: 1
FWCI
1.33
Type
journal article
Language
en
Open access
closed
Locations
Project Management Journal (publishedVersion)
Topics
  • Social Sciences › Decision Sciences › Management Science and Operations Research › Construction Project Management and Performance
  • Social Sciences › Economics, Econometrics and Finance › Finance › Capital Investment and Risk Analysis
  • Social Sciences › Business, Management and Accounting › Strategy and Management › Value Engineering and Management
Keywords
project budget estimation, reserve funds, three-point estimation, R-value

About these checks

Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.

Statistics and arithmetic are recomputed, not judged.

Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.

What counts as a claim ›How we measure confidence ›How we check this ›

Are you an author, or do you see a problem with this page? Request a review