Improving Project Budget Estimation Accuracy and Precision by Analyzing Reserves for Both Identified and Unidentified Risks
Abstract
Project risk is a critical factor in estimating project budget. Previous studies on this topic have only addressed estimation methods that consider project budget reserves against identified risks. As a result, project managers still face the challenge of completing projects within given budgets but without the relevant tools to deal with unidentified risks. This study proposes an approach for estimating reserves for both identified and unidentified risks separately. The study also suggests using the three-point estimation technique and R-value determination for estimating risk costs, which can improve budget accuracy and precision. The construction of residential building projects in South Korea demonstrates the advantages of the proposed approach compared with previous methods.
Overview
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
Claims other papers make about this one
Each is checked against this paper’s own text: does it say what the citing paper says it does?
In project management, the P80 percentile is sometimes chosen as the most appropriate percentile to measure risk appetite.
“However in project management, the P80 percentile is sometimes chosen as the most appropriate percentile to measure risk appetite (Kwon and Kang, 2019;Traynor and Mahmoodian, 2019;Lorance and Wendling, 2001).”
From Beyond probability-impact matrices in project risk management: A quantitative methodology for risk prioritisation (2024) · cites this paper as Kwon and Kang, 2019
Citations
Cites
No references could be resolved yet.
Research works printed but not linked: 56
- 10.1002/pmj.21545 · DOI
- 10.1016/S0263-7863(02)00028-5 · DOI · Paper page
- 10.1016/j.aej.2012.11.004 · DOI
- Baccarini D., 2006, Proceedings of the Australasian University building educators association annual conference 2006: 31st Annual Conference, 11–14 July 2006
- 10.1016/j.jss.2008.03.059 · DOI
- 10.1061/(ASCE)0742-597X(2007)23:3(140) · DOI
- Becker T. V., Jaselskis E. J., El-gafy M. (2014). Improving predictability of construction project outcomes through intentional management of indirect construction costs. Journal of Construction Engineering and Management, 140(6), 401–414. doi: http://dx.doi.org:10.1061/(ASCE) · DOI
- Bedarida S., 2012, Cost Engineering-Morgantown, 54, 27
- 10.1061/(ASCE)CO.1943-7862.0000225 · DOI
- Book S. A., 2007, Allocating risk dollars back to individual cost elements
- 10.1002/pmj.21303 · DOI
- 10.1016/S0965-9978(01)00036-9 · DOI
- 10.3130/jaabe.10.437 · DOI
- Chapman C., 2000, Project risk management—The required transformations to become project uncertainty management
- 10.1016/j.sepro.2012.01.004 · DOI
- Clark D. E., 2001, Cost Engineering, 43, 40
- 10.1061/(ASCE)CO.1943-7862.0000160 · DOI
- 10.1016/j.ijproman.2006.12.002 · DOI
- 10.1061/(ASCE)CO.1943-7862.0000621 · DOI
- 10.1016/j.ijproman.2011.10.004 · DOI
- 10.1016/j.aej.2014.09.008 · DOI
- 10.1016/S0263-7863(98)00078-7 · DOI
- 10.1108/13664380910977592 · DOI
- 10.1080/01944360208976273 · DOI
- 10.1016/S0263-7863(02)00055-8 · DOI
- 10.1080/1941658X.2008.10462211 · DOI
- 10.1016/j.ijproman.2012.11.001 · DOI
- 10.1002/pmj.21512 · DOI
- 10.1016/j.eswa.2010.07.061 · DOI
- Kasimu M., 2012, Institute of Interdisciplinary Journal of Contemporary Research in Business, 3, 775
- Ke Y. J., 2013, Journal of Financial Management of Property and Construction, 1, 6
- 10.1016/j.ijproman.2014.01.001 · DOI
- Kim G. H., 2004, Building and Environment, 34, 34
- 10.1109/52.589239 · DOI
- 10.1080/0144619042000326710 · DOI
- 10.1016/j.autcon.2007.10.007 · DOI
- Nawaz T., 2013, Industrial Engineering Letters, 3, 19
- 10.11591/ijaas.v1i1.537 · DOI
- Moselhi O., 1997, Risk assessment and contingency estimating
- 10.1061/(ASCE)0733-9364(2001)127:3(173) · DOI
- Pfleeger S. L., 2006, Software engineering, theory and practice
- Project Management Institute (PMI), 2013, A guide to the project management body of knowledge (PMBOK® guide) –
- 10.1016/j.ijproman.2006.11.007 · DOI
- 10.1016/j.ijproman.2012.04.002 · DOI
- Schwartz M., 2010, The Nunn-McCardy act: Background, analysis, and issues for Congress
- Smith P., 2014, Social and Behavior Sciences, 119, 485
- Smith P. G., 2002, Proactive risk management
- Sweis G. H., 2013, Journal of American Science, 9, 134
- Tabish S., 2011, Important factors for the success of public construction projects. 2nd International Conference on Construction and Project Management IPEDR (15)
- 10.1002/pmj.21325 · DOI
- Thomson P. A., 1992, Engineering construction risks
- U.S. Government Accountability Office, 2013, Reports to congressional committees, NASA assessment of selected large-scale projects (GAO-13-276SP)
- 10.1016/j.ijproman.2012.12.002 · DOI
- 10.1002/pmj.21558 · DOI
- Xenidis Y., 2013, Social and Behavior Sciences, 74, 478
- 10.1016/j.sepro.2011.08.041 · DOI
Cited by
Sorted by citations
Acebes, F., González-Varona, J. M., López-Paredes, A., & Pajares, J. (2024) · Humanities and Social Sciences Communications · doi:10.1057/s41599-024-03180-5 · Cited by 74
Metadata
- Authors
- Kwon, H., & Kang, C. W.
- Affiliations
- Hanyang University (KR)
- Corresponding author
- Kwon, Hyukchun
- ORCID
- Kang, Chang Wook
- Venue
- Project Management Journal
- Publisher
- SAGE Publications
- Published
- 2018-11-29
- Volume
- 50
- Issue
- 1
- Pages
- 86-100
- ISSN
- 1938-9507 (ISSN-L)
- 8756-9728
- OpenAlex
- W2902201766
- Cited by
- 50
- References
- 0
- Citations by year
- 2026: 4 · 2025: 5 · 2024: 18 · 2023: 8 · 2022: 8 · 2021: 3 · 2020: 3 · 2019: 1
- FWCI
- 1.33
- Type
- journal article
- Language
- en
- Open access
- closed
- Locations
- Project Management Journal (publishedVersion)
- Topics
- Social Sciences › Decision Sciences › Management Science and Operations Research › Construction Project Management and Performance
- Social Sciences › Economics, Econometrics and Finance › Finance › Capital Investment and Risk Analysis
- Social Sciences › Business, Management and Accounting › Strategy and Management › Value Engineering and Management
- Keywords
- project budget estimation, reserve funds, three-point estimation, R-value
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review