A Comparison of Heuristic and Optimum Solutions in Resource-Constrained Project Scheduling

Davis, Edward W., Patterson, James H.·1975·Management Science

Abstract

The problem addressed is that of scheduling the activities of a project network to minimize project duration under conditions of multiple limited resource requirements and availabilities. Various heuristic sequencing rules have been applied to this problem, and the effectiveness of these rules relative to one another has been previously compared in the literature. However, there have been no previous comparisons of the effectiveness of these rules relative to an optimum solution. This paper makes such a comparison of eight different heuristic scheduling rules, including those found most effective in previous research on this problem. Results are presented for a total of eighty-three different multi-resource problems.

Overview

The claims and statistics of this paper haven’t been checked yet.

Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.

A few free checks a day · papers already verified open instantly · results are public

Integrity signals

Registry

Crossref · 10.1287/mnsc.21.8.944

Cites

Statistics

Verification

Claims the paper makes

The claims and statistics of this paper haven’t been checked yet.

Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.

A few free checks a day · papers already verified open instantly · results are public

Self-check

Percentages, sums and reported differences re-computed from the paper’s own numbers.

The self-check needs the paper’s full text.

Citations

Cited by

See all 454

Metadata

Authors
Davis, E. W., & Patterson, J. H.
Venue
Management Science
Published
1975-04
Volume
21
Issue
8
Pages
944-955
ISSN
  • 0025-1909 (ISSN-L)
  • 1526-5501
OpenAlex
W2149521180
Cited by
454
References
0
FWCI
7.42
Type
journal article
Language
en
Open access
closed

About these checks

Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.

Statistics and arithmetic are recomputed, not judged.

Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.

What counts as a claim ›How we measure confidence ›How we check this ›

Are you an author, or do you see a problem with this page? Request a review

How to cite

Cite CoChat for the checks on this page, and the paper for its own findings.

This page
CoChat. (2026). Citation check: A Comparison of Heuristic and Optimum Solutions in Resource-Constrained Project Scheduling. https://app.cochat.ai/papers/10.1287/mnsc.21.8.944
The paper
Davis, E. W., & Patterson, J. H. (1975). A Comparison of Heuristic and Optimum Solutions in Resource-Constrained Project Scheduling. Management Science. https://doi.org/10.1287/mnsc.21.8.944

Data sources

Bibliographic data: Semantic Scholar, OpenAlex, Crossref.

Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).

Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.