Assessment of Production Costs in Toyota Production System Simulation Based on Makespan
Open accessAbstract
This study examines the impact of makespan on production costs by comparing the Toyota Production System through simulations with three scheduling algorithms.
AI snapshot
Written from the paper’s full text.
TL;DR
This simulation study compares Initial, Simulated Annealing, and Tabu Search scheduling in a Toyota Production System setting across three demand levels, tracking makespan, total production cost, and unit cost. It reports a time–cost trade-off, with metaheuristics showing better unit-cost economies at higher demand but higher total costs, while the makespan direction is internally inconsistent between the narrative and tables.
Key findings
- For demands of 186, 216, and 246 units, Simulated Annealing and Tabu Search produced identical results. Their total production costs were higher than the Initial Method: $245,229 vs $237,377; $283,881 vs $276,350; and $322,534 vs $315,323, an increase of roughly 2.3–3.3%.
- Unit costs moved in opposite directions: the Initial Method rose from $1,276 to $1,282, while Simulated Annealing/Tabu Search fell from $1,318 to $1,311, which the paper interprets as better economies of scale at higher volumes.
- The narrative reports that Simulated Annealing and Tabu Search reduced makespan by about 2.2–3.2% (e.g., 569.67 vs 588.54 minutes at Demand 1), but Table 2 lists the Initial Method at 569.68, 663.29, and 756.90 minutes and Simulated Annealing/Tabu Search at 588.54, 681.38, and 774.22 minutes, reversing that direction.
- Simulated Annealing used different job sequences across demands yet matched Tabu Search in cost and makespan, suggesting job order may not materially affect outcomes when the optimization method is effective.
Methods
- Quantitative simulation experiment comparing three scheduling approaches—Initial Method, Simulated Annealing, and Tabu Search—for a vehicle production system with six vehicle types and four workstations.
- Three demand scenarios were used: 186, 216, and 246 units. Production cost was calculated as TC = (CL + CM + CE + CO) × M, with fixed, labor, and per-workstation production costs; Microsoft Excel was used for simulation and analysis.
- The study compared makespan, total production cost, and unit cost, examined time–cost relationships, and validated the model against historical data or industry benchmarks and internal consistency checks.
Limitations
- The paper states that the demand range was restricted and external factors were excluded; the cost model also omitted production quality, downtime, and failure rate.
- The paper notes that the identical Simulated Annealing and Tabu Search results need further investigation, possibly due to a narrow solution space or parameter settings, and that linearity may not hold at much wider production volumes.
- Evident from the text: the makespan results are contradictory—the narrative and abstract/conclusion describe metaheuristics as achieving shorter makespan, while Table 2 shows the Initial Method with lower makespan values—which limits confidence in the reported makespan–cost relationship.
Model-written summary. Check it against the paper before relying on it.
Integrity signals
Registry
Cites
Statistics
Claims the paper makes
0 of 4 cited sources checked · 0 supported · 0 flagged
- Findingown data
Simulated Annealing and Tabu Search unit cost decreased from $1,318 at Demand 1 to $1,311 at Demand 3.
“The Unit Cost Analysis provides additional insight that Initial Method: Unit Cost increased slightly from $1,276 (Request 1) to $1,282 (Request 3) and Simulated Annealing/Tabu Search: Unit Cost decreased from $1,318 (Request 1) to $1,311 (Request 3).”
Quote in the paperSubstantial claim - Findingown data
Initial Method unit cost increased slightly from $1,276 at Demand 1 to $1,282 at Demand 3.
“The Unit Cost Analysis provides additional insight that Initial Method: Unit Cost increased slightly from $1,276 (Request 1) to $1,282 (Request 3) and Simulated Annealing/Tabu Search: Unit Cost decreased from $1,318 (Request 1) to $1,311 (Request 3).”
Quote in the paperNot a substantial claim - Findingown data
A makespan reduction of approximately 3.2% by Simulated Annealing and Tabu Search results in a cost increase of between 2.3% and 3.3%.
“Based on the Efficiency Trade-off, a makespan reduction of approximately 3.2% by Simulated Annealing and Tabu Search results in a cost increase of between 2.3% to 3.3%.”
Quote in the paperSubstantial claim - Interpretationown data
Job order may not significantly affect costs or makespan as long as the optimization method used is effective.
“This indicates that in this case, job order may not significantly affect costs or makespan as long as the optimization method used is effective.”
Quote in the paperSubstantial claim - Interpretationown data
Simulated Annealing and Tabu Search have the potential to achieve better economies of scale at higher production volumes, indicated by a decrease in unit cost as demand increases.
“This trend shows that although Simulated Annealing and Tabu Search result in higher Total Production Costs, these methods have the potential to achieve better economies of scale at higher production volumes.”
- Also stated in: § Conclusions · hedged
“Unit Cost analysis reveals that Simulated Annealing and Tabu Search have the potential to achieve better economies of scale at high production volumes, indicated by a decrease in Unit Cost as demand increases.”
Quote in the paperSubstantial claim - Also stated in: § Conclusions · hedged
- Interpretationcitation
Simulated Annealing and Tabu Search offer greater flexibility in terms of speed of response to changing requests.
“However, Simulated Annealing and Tabu Search offer greater flexibility in terms of speed of response to changing requests.”
Quote in the paperNot a substantial claim - Interpretationcitation
The method with a shorter makespan allows increasing production capacity without adding physical facilities.
“The method with a shorter makespan allows increasing production capacity without adding physical facilities.”
Quote in the paperSubstantial claim - Interpretationreasoning
The exclusion of production quality, downtime, and failure rate may result in results that do not reflect real-world conditions.
“However, the exclusion of these factors may result in results that do not reflect realworld conditions, as in practice, production quality and disruptions significantly influence total operational costs.”
Quote in the paperSubstantial claim - Premisecitation
Production costs can be calculated using the formula TC = (CL + CM + CE + CO) × M, where TC is Total Cost, CL is Labor Cost, CM is Machine Cost, CE is Energy Cost, CO is Other Costs, and M is Makespan.
“Calculation of production costs uses the formula TC = (CL + CM + CE + CO) × M where TC is Total Cost, CL is Labor Cost, CM is Machine Cost, CE is Energy Cost, CO is Other Costs, and M is Makespan (Pinedo 2022).”
- Also stated in: § Results · plain
“Calculation of production costs based on makespan involves the components of labor, machine, energy and other costs multiplied by the makespan value (Pinedo, 2022).”
Quote in the paperSubstantial claim0 of 1 sources checked- cites Pinedo 2022 source
- Also stated in: § Results · plain
- Premisecitation
Computer simulation is an effective tool for analyzing and optimizing complex production systems such as the Toyota Production System.
“Computer simulation has become a very effective tool in analyzing and optimizing complex production systems such as TPS.Using simulation, researchers and practitioners can display various scenarios and parameters without disturbing the actual production operation (Banks et al., 2010).”
Quote in the paperSubstantial claim0 of 1 sources checked- cites Banks et al., 2010
Couldn’t be matched to a paper in Crossref, so it can’t be checked.
- Interpretationcitation
The linear relationship between makespan, costs, and production volume may not apply to a much wider range of production due to capacity constraints or diseconomies of scale.
“However, it should be noted that this linearity may not apply to a much wider range of production due to factors such as capacity constraints or diseconomies of scale (Heizer, et al., 2023).”
Quote in the paperNot a substantial claim0 of 1 sources checked- cites Heizer, et al., 2023
Couldn’t be matched to a paper in Crossref, so it can’t be checked.
- May combine two claims. 7
- Classified as probably not a substantial claim. 2
May combine two claims.
Findingown dataThere is an inverse relationship between makespan and production costs: the Initial Method with the longest makespan produces the lowest costs, while Simulated Annealing and Tabu Search with shorter makespans produce higher costs.
“The data shows that there is an inverse relationship between makespan and production costs.The Initial Method with the longest makespan produces the lowest costs, while Simulated Annealing and Tabu Search with shorter makespans produce higher costs.”
Quote in the paperSubstantial claimMay combine two claims.
Findingown dataThe increase in makespan and costs from Demand 1 to Demand 2 and Demand 3 is relatively consistent for all methods, showing a relationship that tends to be linear between makespan, costs, and production volume in the analyzed demand range.
“The increase in makespan and costs from Demand 1 to Demand 2 and Demand 3 is relatively consistent for all methods.This shows a relationship that tends to be linear between makespan, costs, and production volume in the analyzed demand range.”
Quote in the paperNot a substantial claimMay combine two claims.
Findingown dataSimulated Annealing and Tabu Search produce identical makespan and shorter makespan than the Initial Method for all demand levels, with reductions of 3.2%, 2.7%, and 2.2% for Demand 1, 2, and 3 respectively.
“Results show that SA and TS achieve a lower makespan than the Initial Method, although their total production costs are slightly higher.”
- Also stated in: § Makespan · plain
“Based on the image above, the data shows that Simulated Annealing and Tabu Search produce identical and shorter makespan compared to the Initial Method for all levels of demand showing results Demand 1: 569.67 minutes vs 588.54 minutes (3.2% reduction), Demand 2: 663.27 minutes vs 681.38 minutes (2.7% reduction), and Demand 3: 756.91 minutes vs 774.22 minutes (2.2% reduction).”
- Also stated in: § Conclusions · plain
“The results show that Simulated Annealing and Tabu Search produce shorter makespan compared to the Initial Method, with a reduction of around 2.2-3.2% for various demand levels.”
Quote in the paperSubstantial claim- Also stated in: § Makespan · plain
May combine two claims.
Findingown dataDespite producing shorter makespan, Simulated Annealing and Tabu Search produce higher Total Production Cost than the Initial Method, with increases of 3.3%, 2.7%, and 2.3% for Demand 1, 2, and 3 respectively.
“Interestingly, despite producing shorter makespan, Simulated Annealing and Tabu Search actually produce higher Total Production Cost as shown in Table 3 from Demand 1: $245,229 vs $237,377 (3.3% increase), Demand 2: $283,881 vs $276,350 (2.7% increase), and Demand 3: $322,534 vs $315,323 (2.3% increase).”
- Also stated in: § Conclusions · plain
“Interestingly, even though it produces a shorter makespan, Simulated Annealing and Tabu Search actually produce a higher Total Production Cost, with an increase of 2.3-3.3%.”
Quote in the paperSubstantial claim- Also stated in: § Conclusions · plain
Probably not a substantial claim: may not pass S3 (load-bearing).
Findingnone givenAll methods have good scalability in dealing with increasing demand.
“Meanwhile, Production Flexibility shows that all methods have good scalability in dealing with increasing demand.”
Quote in the paperNot a substantial claimMay combine two claims.
Interpretationnone givenThe study's demand range is restricted and external factors were excluded.
“Limitations include a restricted demand range and the exclusion of external factors, suggesting areas for further research on production quality in manufacturing.”
- Also stated in: § Makespan and Cost Relationship · plain
“In this study, factors such as production quality, downtime, and failure rate were not included in the cost model.”
Quote in the paperNot a substantial claim- Also stated in: § Makespan and Cost Relationship · plain
May combine two claims.
PremisecitationProduction processes that require shorter time usually show higher efficiency and allow for reduced production costs.
“Production processes that require shorter time usually show higher efficiency and allow for reduced production costs (Pinedo 2022).”
Quote in the paperSubstantial claim0 of 1 sources checked- cites Pinedo 2022 source
Classified as probably not a substantial claim. May combine two claims.
Study design and conductnone givenModel validation was carried out by comparing simulation results with historical data or industry benchmarks, as well as checking internal consistency of the model.
“Model validation is carried out by comparing simulation results with historical data or industry benchmarks, as well as checking the internal consistency of the model to ensure the reliability of the results.”
Quote in the paperSubstantial claim
The paper relies on this without support.
The per-unit-time cost components (labor, machine, energy, and other costs) are constant across the three scheduling methods and demand levels.
“Calculation of production costs uses the formula TC = (CL + CM + CE + CO) × M where TC is Total Cost, CL is Labor Cost, CM is Machine Cost, CE is Energy Cost, CO is Other Costs, and M is Makespan (Pinedo 2022).”
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
Each contradiction between two passages listed here was confirmed by an independent check.
Makespan ranking is reversed in the conclusions
MajorTable 2 gives the Initial Method a shorter makespan than Simulated Annealing and Tabu Search at every demand level. The discussion says the Initial Method has the longest makespan, so its claimed time-cost trade-off rests on the opposite ranking from the reported results.
“The data shows that there is an inverse relationship between makespan and production costs.The Initial Method with the longest makespan produces the lowest costs, while Simulated Annealing and Tabu Search with shorter makespans produce higher costs.”
“Table 2 Makespan value Method Demand 1 (minutes) Demand 2 (minutes) Demand 3 (minutes) Job Sequence Initial Method 569.68 663.29 756.90 Same for every demand Simulated Annealing 588.54 681.38 774.22Not the same for every demand Tabu Search 588.54 681.38 774.22 Same for every demand”
Cites
The publisher hasn’t deposited this paper’s reference list.
Research works printed but not linked: 9
- [4]4. Chase, R., & Jacobs, F. (2021). Operations and Supply Chain Management (16th ed.). New York: McGraw- Hill Education.
- [5]5. Drury, C. (2018). Management and Cost Accounting (10th ed.). Andover: Cengage Learning.
- [6]6. Heizer, J., Render, B., & Munson, C. (2023). Opera- tions Management: Sustainability and Supply Chain Mangement (14th ed.). Edinburgh: Pearson Education Limited.
- [7]7. Horngren, C., Datar, S., & Rajan, M. (2012). Cost Ac- counting A Managerial Emphasis (14th ed.). Harlow: Pearson Education.
- [13]13. Liker, J. (2004). The Toyota Way: 14 Management Prin- ciples from The World's Greatest Manufacturer. New York: McGraw-Hill.
- [15]15. Monden, Y. (2011). TOYOTA Production System an Integrated Approach to Just-in-Time (4th ed.). New York: CRC Press.
- [22]22. Pindyck, R., & Rubinfeld, D. (2020). Microeconomics (9th ed.). Barkeley: Pearson.
- [25]25. Rother, M., Shook, J., Womack, J., & Jones. (2003). Learning to See: Value Stream Mapping to Add Value and Eliminate (1st ed.). Boston: Learn Enterprise Institute.
- [30]30. Slack, N., Brandon-Jones, A., & Johnston, R. (2013). Operation Management (7th ed.). Upper Saddle River: Pearson Education.
Cited by
Sorted by citations
Sari, G. M., & Yudoko, G. (2026) · Almana : Jurnal Manajemen dan Bisnis · doi:10.36555/almana.v10i2.3037
“Therefore, cost and margin visibility in this case need to reflect not only product grade, but also formula and production route (Mangngenre et al., 2025; Pasaribu and Hasanuh, 2021).”
- Authors
- MANGNGENRE, S., INDAH, A. B. R., IKASARY, D., HAMZI, A., & NOVAWANDA, O.
- Affiliations
- Hasanuddin University (ID)
- Jazan University (SA)
- University of Surabaya (ID)
- Venue
- Management and Production Engineering Review
- Published
- 2025-09-30
- ISSN
- 2080-8208 (ISSN-L)
- 2082-1344
- OpenAlex
- W7106302438
- Cited by
- 0
- References
- 0
- FWCI
- 0.00
- Type
- journal article
- Language
- pl
- Open access
- diamond
- doi.org
- Locations
- Management and Production Engineering Review (publishedVersion)
- Funders
- Universitas Hasanuddin
- Topics
- Physical Sciences › Engineering › Industrial and Manufacturing Engineering › Scheduling and Optimization Algorithms
- Social Sciences › Business, Management and Accounting › Strategy and Management › Management and Optimization Techniques
- Physical Sciences › Engineering › Industrial and Manufacturing Engineering › Advanced Manufacturing and Logistics Optimization
- Keywords
- Toyota Production System, makespan, production costs, scheduling algorithms, simulated annealing, tabu search, demand level, unit cost, economies of scale, time-cost trade-off, break-even point, production constraints, technology investment
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Claims read by deepseek-v4.1-flash under definition version 3 (extract-v3) on 2026-10-11.
Classified by jev-1.13-20260917 (gold-guideline-v0.2) on 2026-10-11.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review