Construction project risk assessment by using adaptive-network-based fuzzy inference system: An empirical study
Open accessThe DOI matches its Crossref record; 1 of the 1 references it cites were found in a registry or an index.
Abstract
Managers require a good understanding about the nature of risks involved in a construction project because the duration, quality, and budget of projects can be affected by these risks. Thus, the identification of risks and the determination of their priorities in every phase of the construction can assist project managers in planning and taking proper actions against those risks. Therefore, prioritizing risks via the risk factors can increase the reliability of success. In this research, first the risks involved in construction projects has been identified and arranged in a systematic hierarchical structure. Next, based on the obtained data an Adaptive Neuro-Fuzzy Inference System (ANFIS) has been designed for the evaluation of project risks. In addition, a stepwise regression model has also been designed and its results are compared with the results of ANFIS. The results show that the ANFIS models are more satisfactory in the assessment of construction projects risks. Our proposed methodology can be applied by managers of construction projects and practitioners to assess of risk factor of construction projects in a proper manner.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Eybpoosh, M., Dikmen, I., & Talat Birgonul, M. (2011) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000382 · Cited by 217 · cited 1×
“17 Eybpoosh et al. (2011) Shortage of materials, Poor contract management, Time and cost overrun, Market-level risks, Project characteristics and contractual Conditions, Change orders 18 Fu-zhou and Hong-yuan (2011) Economic risk, Political risk, Construction risk, Other risks”
Background
Cited by
Construction projects selection and risk assessment by fuzzy AHP and fuzzy TOPSIS methodologies
Taylan, O., Bafail, A. O., Abdulaal, R. M. S., & Kabli, M. R. (2014) · Applied Soft Computing · doi:10.1016/j.asoc.2014.01.003 · Cited by 574
Risk paths in international construction projects: Case study from Chinese contractors
Liu, J., Zhao, X., & Yan, P. (2016) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001116 · Cited by 203
Afzal, F., Yunfei, S., Nazir, M., & Bhatti, S. M. (2021) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-02-2019-0047 · Cited by 172
Islam, M. S., Nepal, M. P., Skitmore, M., & Attarzadeh, M. (2017) · Advanced Engineering Informatics · doi:10.1016/j.aei.2017.06.001 · Cited by 163
Metadata
- Authors
- Ebrat, M., & Ghodsi, R.
- Venue
- KSCE Journal of Civil Engineering
- Publisher
- Elsevier BV
- Published
- 2014-06
- Volume
- 18
- Issue
- 5
- Pages
- 1213-1227
- ISSN
- 1226-7988 (ISSN-L)
- OpenAlex
- W1966625806
- Cited by
- 58
- References
- 1
- FWCI
- 4.11
- Type
- journal article
- Language
- en
- Open access
- hybrid
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
How to cite
Cite CoChat for the checks on this page, and the paper for its own findings.
- This page
- CoChat. (2026). Citation check: Construction project risk assessment by using adaptive-network-based fuzzy inference system: An empirical study. https://app.cochat.ai/papers/10.1007/s12205-014-0139-5
- The paper
- Ebrat, M., & Ghodsi, R. (2014). Construction project risk assessment by using adaptive-network-based fuzzy inference system: An empirical study. KSCE Journal of Civil Engineering. https://doi.org/10.1007/s12205-014-0139-5
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.