Risk Paths in International Construction Projects: Case Study from Chinese Contractors

Open access
Liu, Junying, Zhao, Xianbo, Yan, Peng · 2016 · Journal of Construction Engineering and Management

The DOI matches its Crossref record; 76 of the 76 references it cites were found in a registry or an index.

Abstract

AbstractContracting in overseas construction markets involves not only the typical risks at home, but also the complex and diverse risks peculiar to international transactions. In addition, international construction project risks are highly interdependent. The objectives of this study are to (1) explore the risk paths in the international construction projects performed by Chinese contractors, and (2) examine the risk effects on the objectives of these projects. To achieve the research objectives, a total of 60 risks were identified from literature review and a questionnaire survey was conducted with 104 professionals from Chinese international contractors. Adopting the structural equation modeling technique, this study proposed a networking of 20 significant risk paths. Specifically, host government–related risk, contractor’s lack of experience, and contractors’ lack of managerial skills had significant effect on project cost, quality, and schedule objectives, respectively. Moreover, host government–rel...

Overview

Integrity signals

Registry

Crossref · 10.1061/(asce)co.1943-7862.0001116

Cites

76 of 76 references verified0 citation errors · 0 not checkable

Statistics

Recomputing p-values needs the paper’s full text.

Verification

Claims the paper makes

We couldn’t retrieve this paper’s full text, so its claims and self-check weren’t run. The registry and citation checks still apply.

Claims other papers make about this one

Each is checked against this paper’s own text: does it say what the citing paper says it does?

Citations

Cites

Show all 76 references

Research works printed but not linked: 3

  1. Cendrowski H., 2009, Enterprise risk management and COSO: A guide for directors, executives, and practitioners
  2. Patton M. Q., 2001, Qualitative research & evaluation components
  3. Zou P. X. Zhang G. and Wang J.-Y. (2006). “Identifying key risks in construction projects: Life cycle and stakeholder perspectives.” Pacific Rim Real Estate Society Conf. Univ. of Auckland Business School Auckland New Zealand.

Cited by

See all 207

Metadata

Authors
Liu, J., Zhao, X., & Yan, P.
Affiliations
  • Tianjin University (CN)
  • Central Queensland University (AU)
  • Ph.D. Candidate, Dept. of Construction Management, College of Management and Economics, Tianjin Univ., 92 Weijin Rd., Tianjin 300072, China (corresponding author).
Venue
Journal of Construction Engineering and Management
Published
2016-06
Volume
142
Issue
6
ISSN
  • 0733-9364 (ISSN-L)
  • 1943-7862
OpenAlex
W2238965708
Cited by
203
References
74
Citations by year
2026: 7 · 2025: 20 · 2024: 17 · 2023: 28 · 2022: 18 · 2021: 21 · 2020: 23 · 2019: 24 · 2018: 20 · 2017: 20 · 2016: 5
FWCI
25.20
Type
journal article
Language
en
Open access
Licence
cc-by
Locations
  • Journal of Construction Engineering and Management (publishedVersion)
  • Acquire (CQUniversity) (submittedVersion)
  • Figshare (submittedVersion, cc-by)
Funders
National Science Foundation
Topics
  • Social Sciences › Decision Sciences › Management Science and Operations Research › Construction Project Management and Performance
  • Physical Sciences › Engineering › Building and Construction › BIM and Construction Integration
  • Social Sciences › Business, Management and Accounting › Strategy and Management › Public-Private Partnership Projects
Keywords
international construction projects, Chinese contractors, contractor experience, management skills, project cost performance, project quality, project schedule, productivity, risk interrelationships

About these checks

Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.

Statistics and arithmetic are recomputed, not judged.

Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.

What counts as a claim ›How we measure confidence ›How we check this ›

Are you an author, or do you see a problem with this page? Request a review

How to cite

Cite CoChat for the checks on this page, and the paper for its own findings.

This page
CoChat. (2026). Citation check: Risk Paths in International Construction Projects: Case Study from Chinese Contractors. https://app.cochat.ai/papers/10.1061/(asce)co.1943-7862.0001116
The paper
Liu, J., Zhao, X., & Yan, P. (2016). Risk Paths in International Construction Projects: Case Study from Chinese Contractors. Journal of Construction Engineering and Management. https://doi.org/10.1061/(asce)co.1943-7862.0001116

Data sources

Bibliographic data: Semantic Scholar, OpenAlex, Crossref.

Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).

Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.