Identifying the critical success factors for relationship management in PPP projects
Open accessThe DOI matches its Crossref record; 33 of the 33 references it cites were found in a registry or an index.
Abstract
The longer the contract period, the higher the chance that major changes will arise. Thus a greater reliance on the established relationships is needed to maintain the contractual bond in PPP project. Relationship management (RM) can therefore be expected to be even more valuable in the PPP context. This paper aims to investigate current perceptions and experiences of RM in PPP projects and more importantly, to identify the CSFs for RM in PPP projects. By means of an empirical questionnaire survey geared towards PPP practitioners with direct hands-on experience, the opinions were solicited, analyzed and compared in relation to potential PPP RM success factors. The survey findings indicate that industry practitioners currently lack a general understanding of concepts and applications of RM, given that it is relatively new in PPP. However, they do think that RM is very important to improve the present performance of PPPs. Future PPP business opportunities can also be increased by effective RM. The top four CSFs for RM are found to be commitment of senior executives, defining the objectives, integration of the different divisions and a multidisciplinary team. However, the relative importance presently assigned for each of the above factors is insufficient, and commitment from senior management is perceived as the most difficult factor to improve.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
DEFINING SUPPLY CHAIN MANAGEMENT
Mentzer, J. T., DeWitt, W., Keebler, J. S., Min, S., Nix, N. W., Smith, C. D., & Zacharia, Z. G. (2001) · Journal of Business Logistics · doi:10.1002/j.2158-1592.2001.tb00001.x · Cited by 5,121
Developmental Processes of Cooperative Interorganizational Relationships
Ring, P. S., & van de Ven, A. H. (1994) · The Academy of Management Review · doi:10.2307/258836 · Cited by 4,914
Do formal contracts and relational governance function as substitutes or complements?
Poppo, L., & Zenger, T. (2002) · Strategic Management Journal · doi:10.1002/smj.249 · Cited by 3,652
Structuring cooperative relationships between organizations
Ring, P. S., & van de Ven, A. H. (1992) · Strategic Management Journal · doi:10.1002/smj.4250130702 · Cited by 2,824
From Marketing Mix to Relationship Marketing: Towards a Paradigm Shift in Marketing
Gronroos, C. (1994) · Asia-Australia Marketing Journal · doi:10.1016/s1320-1646(94)70275-6 · Cited by 2,347
Research methods for construction
Fellowa, R., & Liu, A. M. M. (2003) · Cited by 1,448
From Marketing Mix to Relationship Marketing: Towards a Paradigm Shift in Marketing
Grönroos, C. (1994) · Management Decision · doi:10.1108/00251749410054774 · Cited by 1,410
A Communication-Based Marketing Model for Managing Relationships
Duncan, T., & Moriarty, S. E. (1998) · Journal of Marketing · doi:10.1177/002224299806200201 · Cited by 1,232
Understanding customer relationship management (CRM): People, process and technology
Chen, I. J., & Popovich, K. (2003) · Business Process Management Journal · doi:10.1108/14637150310496758 · Cited by 1,227
The allocation of risk in PPP/PFI construction projects in the UK
Bing, L., Akintoye, A., Edwards, P. J., & Hardcastle, C. (2005) · International Journal of Project Management · doi:10.1016/j.ijproman.2004.04.006 · Cited by 901
Critical Success Factors for Public–Private Partnerships in Infrastructure Development
Zhang, X. (2005) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2005)131:1(3 · Cited by 748
Customer Relationship Management: Emerging Practice, Process, and Discipline
Parvatiyar, A., & Sheth, J. N. (2002) · Cited by 718
Towards a Comprehensive Understanding of Public Private Partnerships for Infrastructure Development
Kwak, Y. H., Chih, Y., & Ibbs, C. W. (2009) · California Management Review · doi:10.2307/41166480 · Cited by 582
Managing public–private megaprojects: Paradoxes, complexity, and project design
van Marrewijk, A., Clegg, S. R., Pitsis, T. S., & Veenswijk, M. (2008) · International Journal of Project Management · doi:10.1016/j.ijproman.2007.09.007 · Cited by 518
Trust and Adaptation in Relational Contracting
Jeffries, F. L., & Reed, R. (2000) · The Academy of Management Review · doi:10.5465/amr.2000.3707747 · Cited by 416
Downsizing to Improve Strategic Position
Drew, S. A. W. (1994) · Management Decision · doi:10.1108/00251749410050624 · Cited by 377
Success factors: public works and public‐private partnerships
Jacobson, C., & Choi, S. O. (2008) · International Journal of Public Sector Management · doi:10.1108/09513550810896514 · Cited by 327
Critical success factors for a customer relationship management strategy
Mendoza, L. E., Marius, A., Pérez, M., & Grimán, A. C. (2007) · Information and Software Technology · doi:10.1016/j.infsof.2006.10.003 · Cited by 291
Parker, D., & Hartley, K. (2003) · Journal of Purchasing and Supply Management · doi:10.1016/s0969-7012(02)00035-7 · Cited by 279
Relationship management in the management of PFI/PPP projects in the UK
Smyth, H., & Edkins, A. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2006.08.003 · Cited by 249
The Management of Complex Projects: A Relationship Approach
Pryke, S. D., & Smyth, H. (2006) · Cited by 221
Co‐opetition: the organisation of the future
Zineldin, M. (2004) · Marketing Intelligence & Planning · doi:10.1108/02634500410568600 · Cited by 210
Construction supply chain partnerships: skills, knowledge and attitudinal requirements
Briscoe, G., Dainty, A. R. J., & Millett, S. (2001) · European Journal of Purchasing & Supply Management · doi:10.1016/s0969-7012(01)00005-3 · Cited by 186
Organizational commitment and governance for supply chain success
Fawcett, S. E., Ogden, J. A., Magnan, G. M., & Bixby Cooper, M. (2006) · International Journal of Physical Distribution & Logistics Management · doi:10.1108/09600030610642913 · Cited by 184
Pauget, B., & Wald, A. E. (2012) · International Journal of Project Management · doi:10.1016/j.ijproman.2012.07.001 · Cited by 170
Formal versus informal contracts: achieving alliance success
Frankel, R., Whipple, J. S., & Frayer, D. J. (1996) · International Journal of Physical Distribution & Logistics Management · doi:10.1108/09600039610114992 · Cited by 163
Avoiding Supply Chain Management Failure: Lessons from Business Process Re‐engineering
Burgess, R. (1998) · The International Journal of Logistics Management · doi:10.1108/09574099810805717 · Cited by 140
An Innovative Public–Private Partnership: New Approach to Development
Samii, R., Wassenhove, L. N. V., & Bhattacharya, S. (2002) · World Development · doi:10.1016/s0305-750x(02)00015-3 · Cited by 129
Choosing an appropriate research methodology
Walker, D. H. T. (1997) · Construction Management and Economics · doi:10.1080/01446199700000003 · Cited by 113
Selecting sustainable teams for PPP projects
Kumaraswamy, M. M., & Anvuur, A. M. (2007) · Building and Environment · doi:10.1016/j.buildenv.2007.02.001 · Cited by 108
Self-citationANALYSIS OF CRITICAL SUCCESS FACTORS RELEVANCE ALONG SAP IMPLEMENTATION PHASES
Esteves, J., & Pastor, J. (2001) · Journal of the Association for Information Systems · Cited by 97
Managing trust and relationships in PPPs: some Australian experiences
Teicher, J., Alam, Q., & Gramberg, B. V. (2006) · International Review of Administrative Sciences · doi:10.1177/0020852306061624 · Cited by 84
Building “relationally integrated value networks” (RIVANS)
Anvuur, A. M., Kumaraswamy, M. M., & Mahesh, G. (2010) · Engineering Construction & Architectural Management · doi:10.1108/09699981111098711 · Cited by 47
Self-citation
Cited by
Sustainable project management through project control in infrastructure projects
Kivilä, J., Martinsuo, M., & Vuorinen, L. (2017) · International Journal of Project Management · doi:10.1016/j.ijproman.2017.02.009 · Cited by 301
Metadata
- Authors
- Zou, W., Kumaraswamy, M., Chung, J., & Wong, J.
- Venue
- International Journal of Project Management
- Publisher
- Elsevier BV
- Published
- 2014-02
- Volume
- 32
- Issue
- 2
- Pages
- 265-274
- ISSN
- 0263-7863 (ISSN-L)
- OpenAlex
- W2000077167
- Cited by
- 265
- References
- 33
- FWCI
- 40.79
- Type
- journal article
- Language
- en
- Open access
- green
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.