Project cost risk analysis: A Bayesian networks approach for modeling dependencies between cost items
The DOI matches its Crossref record; 32 of the 32 references it cites were found in a registry or an index.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
A guide to the project management body of knowledge (PMBOK guide)
Pmbok (2004) · Cited by 4,316
Risk Analysis: A Quantitative Guide
Vose, D. (2000) · Cited by 1,747
Advantages and challenges of Bayesian networks in environmental modelling
Uusitalo, L. (2007) · Ecological Modelling · doi:10.1016/j.ecolmodel.2006.11.033 · Cited by 1,118
Learning Bayesian networks from data: An information-theory based approach
Cheng, J., Greiner, R., Kelly, J., Bell, D., & Liu, W. (2002) · Artificial Intelligence · doi:10.1016/s0004-3702(02)00191-1 · Cited by 803
Frimpong, Y., Oluwoye, J., & Crawford, L. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00055-8 · Cited by 796
Bayesian Networks for Data Mining
Heckerman, D. (1997) · Data Mining and Knowledge Discovery · doi:10.1023/a:1009730122752 · Cited by 630
Cost escalation and schedule delays in road construction projects in Zambia
Kaliba, C., Muya, M., & Mumba, K. (2009) · International Journal of Project Management · doi:10.1016/j.ijproman.2008.07.003 · Cited by 596
Object-Oriented Bayesian Networks
Koller, D., & Pfeffer, A. (2013) · arXiv (Cornell University) · doi:10.48550/arxiv.1302.1554 · Cited by 488
Product Cost Estimation: Technique Classification and Methodology Review
Niazi, A., Dai, J. S., Balabani, S., & Seneviratne, L. (2006) · Journal of Manufacturing Science and Engineering · doi:10.1115/1.2137750 · Cited by 475
Causes of delay and cost overruns in Nigerian construction projects
Mansfield, N., Ugwu, O., & Doran, T. (1994) · International Journal of Project Management · doi:10.1016/0263-7863(94)90050-7 · Cited by 457
Real-world applications of Bayesian networks
Heckerman, D., Mamdani, A., & Wellman, M. P. (1995) · Communications of the ACM · doi:10.1145/203330.203334 · Cited by 377 · cited 1×
“Bayesian networks (BNs) are a framework that presents probabilistic relationships and enables probabilistic inference among a set of variables (Heckerman et al., 1995).”
BackgroundKadane, J., & Wolfson, L. J. (1998) · Journal of the Royal Statistical Society: Series D (The Statistician) · doi:10.1111/1467-9884.00113 · Cited by 331 · cited 1×
“However, modeling this correlation is known to be much more difficult for human subjects to do without using various conditioning arrangements (Kadane and Wolfson, 1998).”
BackgroundQuantifying schedule risk in construction projects using Bayesian belief networks
Luu, V. T., Kim, S.-Y., Tuan, N. V., & Ogunlana, S. O. (2008) · International Journal of Project Management · doi:10.1016/j.ijproman.2008.03.003 · Cited by 309
A neural network approach for early cost estimation of structural systems of buildings
Murat Günaydın, H., & Zeynep Doğan, S. (2004) · International Journal of Project Management · doi:10.1016/j.ijproman.2004.04.002 · Cited by 285
A proposed validation framework for expert elicited Bayesian Networks
Pitchforth, J., & Mengersen, K. (2013) · Expert Systems with Applications · doi:10.1016/j.eswa.2012.07.026 · Cited by 225
Chin, K., Tang, D. W., Yang, J., Wong, S. Y., & Wang, H. (2009) · Expert Systems with Applications · doi:10.1016/j.eswa.2009.02.019 · Cited by 204
A case-based reasoning cost estimating model using experience by analytic hierarchy process
An, S.-H., Kim, G.-H., & Kang, K.-I. (2007) · Building and Environment · doi:10.1016/j.buildenv.2006.06.007 · Cited by 174
BBN-based software project risk management
Fan, C.-F., & Yu, Y.-C. (2004) · Journal of Systems and Software · doi:10.1016/j.jss.2003.12.032 · Cited by 171
Case-Based Reasoning Approach in Bid Decision Making
Chua, D. K. H., Li, D. Z., & Chan, W. T. (2001) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2001)127:1(35 · Cited by 166
Pajares, J., & López-Paredes, A. (2011) · International Journal of Project Management · doi:10.1016/j.ijproman.2010.04.005 · Cited by 162
Cost overruns in public projects
Arditi, D., Akan, G. T., & Gurdamar, S. (1985) · International Journal of Project Management · doi:10.1016/0263-7863(85)90053-5 · Cited by 121
Web-based CBR system applied to early cost budgeting for pavement maintenance project
Chou, J. (2008) · Expert Systems with Applications · doi:10.1016/j.eswa.2008.01.025 · Cited by 117
Determining Attribute Weights in a CBR Model for Early Cost Prediction of Structural Systems
Doğan, S. Z., Arditi, D., & Günaydın, H. M. (2006) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2006)132:10(1092 · Cited by 116
Bayesian Belief Networks: Odds and Ends
van der Gaag, L. C. (1996) · The Computer Journal · doi:10.1093/comjnl/39.2.97 · Cited by 110
Cheng, M., Peng, H.-S., Wu, Y.-W., & Chen, T.-L. (2010) · Automation in Construction · doi:10.1016/j.autcon.2010.02.008 · Cited by 93
Project Scheduling: Improved Approach to Incorporate Uncertainty Using Bayesian Networks
Khodakarami, V., Fenton, N., & Neil, M. (2007) · Project Management Journal · doi:10.1177/875697280703800205 · Cited by 89
Self-citationAHP- and simulation-based budget determination procedure for public building construction projects
Lai, Y.-T., Wang, W.-C., & Wang, H.-H. (2008) · Automation in Construction · doi:10.1016/j.autcon.2007.10.007 · Cited by 86 · cited 1×
“Without considering the uncertainty involved, there is a high risk that the actual cost of a project exceeds what it was originally anticipated, which in turn causes several other risks such as delays and performance problems (Elkjaer, 2000; Lai et al., 2008).”
BackgroundDetailed cost estimating in the automotive industry: Data and information requirements
Roy, R., Souchoroukov, P., & Shehab, E. (2011) · International Journal of Production Economics · doi:10.1016/j.ijpe.2011.05.018 · Cited by 71
Elkjaer, M. (2000) · International Journal of Project Management · doi:10.1016/s0263-7863(98)00078-7 · Cited by 53 · cited 1×
“Without considering the uncertainty involved, there is a high risk that the actual cost of a project exceeds what it was originally anticipated, which in turn causes several other risks such as delays and performance problems (Elkjaer, 2000; Lai et al., 2008).”
BackgroundChapman, C. B., & Ward, S. C. (2011) · Cited by 49
Impossible Certainty: Cost Risk Analysis for Air Force Systems
Arena, M. V., Younossi, O., Galway, L. A., Fox, B. H., Graser, J. C., Sollinger, J. M., Wu, F., & Wong, C. (2006) · Defense Technical Information Center (DTIC) · Cited by 46
Graham, L. D., Smith, S. D., & Dunlop, P. (2005) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2005)131:2(230 · Cited by 30
Cited by
Afzal, F., Yunfei, S., Nazir, M., & Bhatti, S. M. (2021) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-02-2019-0047 · Cited by 172
Islam, M. S., Nepal, M. P., Skitmore, M., & Attarzadeh, M. (2017) · Advanced Engineering Informatics · doi:10.1016/j.aei.2017.06.001 · Cited by 163
A hybrid BN-HFACS model for predicting safety performance in construction projects
Xia, N., Zou, P. X. W., Liu, X., Wang, X., & Zhu, R. (2018) · Safety Science · doi:10.1016/j.ssci.2017.09.025 · Cited by 163
Tlili, A., Denden, M., Essalmi, F., Jemni, M., Chang, M., Kinshuk, & Chen, N.-S. (2023) · Interactive Learning Environments · doi:10.1080/10494820.2019.1636084 · Cited by 65
Kwon, H., & Kang, C. W. (2019) · Project Management Journal · doi:10.1177/8756972818810963 · Cited by 50
“Uncertainty of cost items is an important aspect in complex projects, and cost uncertainty analysis aims to help decision makers understand and model different factors that affect funding exposure and ultimately estimate the cost of projects (Khodakarami & Abdi, 2014).”
Background
Metadata
- Authors
- Khodakarami, V., & Abdi, A.
- Venue
- International Journal of Project Management
- Publisher
- Elsevier BV
- Published
- 2014-10
- Volume
- 32
- Issue
- 7
- Pages
- 1233-1245
- ISSN
- 0263-7863 (ISSN-L)
- OpenAlex
- W2042794667
- Cited by
- 164
- References
- 32
- FWCI
- 17.66
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.