Towards integrating construction risk management and stakeholder management: A systematic literature review and future research agendas
The DOI matches its Crossref record; 6 of the 6 references it cites were found in a registry or an index.
Abstract
We propose that integrated management of construction risk and stakeholder is feasible and can promote the effectiveness of both risk management (RM) and stakeholder management (SM). A systematic literature review is conducted on the current construction literature involving both RM and SM, through which we identify four linkage modes between risk and stakeholder management. We further suggest future directions that enable integrating risk and stakeholder management to benefit the management process and/or management outcome of RM and SM. These linkages and directions shed light on enhancing the effectiveness of RM and SM through new ways of thinking about, analyzing, and then managing risks and stakeholders in a holistic and integrated way, but not the traditional endeavor in individual areas. Integrating risk and stakeholder management is challenging, but can be a novel way for improving project performance for which this research conceptually justifies its feasibility and benefits, which merits further study.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
The qualitative content analysis process
Elo, S., & Kyngäs, H. (2008) · Journal of Advanced Nursing · doi:10.1111/j.1365-2648.2007.04569.x · Cited by 22,617
Tranfield, D., Denyer, D., & Smart, P. (2003) · British Journal of Management · doi:10.1111/1467-8551.00375 · Cited by 15,386
Mitchell, R. K., Agle, B. R., & Wood, D. J. (1997) · The Academy of Management Review · doi:10.2307/259247 · Cited by 5,039
Content Analysis in Mass Communication: Assessment and Reporting of Intercoder Reliability
Lombard, M., Snyder-Duch, J., & Bracken, C. C. (2002) · Human Communication Research · doi:10.1111/j.1468-2958.2002.tb00826.x · Cited by 3,068
Risk assessment and risk management: Review of recent advances on their foundation
Aven, T. (2016) · European Journal of Operational Research · doi:10.1016/j.ejor.2015.12.023 · Cited by 1,713
Developing design propositions through research synthesis
Denyer, D., Tranfield, D., & van Aken, J. E. (2008) · Organization Studies · doi:10.1177/0170840607088020 · Cited by 1,057
Cited by
Halder, A. (2024) · Innovative Infrastructure Solutions · doi:10.1007/s41062-024-01521-6 · Cited by 10
Metadata
- Authors
- Xia, N., Zou, P. X. W., Griffin, M. A., Wang, X., & Zhong, R.
- Venue
- International Journal of Project Management
- Publisher
- Elsevier BV
- Published
- 2018-07
- Volume
- 36
- Issue
- 5
- Pages
- 701-715
- ISSN
- 0263-7863 (ISSN-L)
- OpenAlex
- W2802787660
- Cited by
- 229
- References
- 6
- FWCI
- 3.37
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
How to cite
Cite CoChat for the checks on this page, and the paper for its own findings.
- This page
- CoChat. (2026). Citation check: Towards integrating construction risk management and stakeholder management: A systematic literature review and future research agendas. https://app.cochat.ai/papers/10.1016/j.ijproman.2018.03.006
- The paper
- Xia, N., Zou, P. X. W., Griffin, M. A., Wang, X., & Zhong, R. (2018). Towards integrating construction risk management and stakeholder management: A systematic literature review and future research agendas. International Journal of Project Management. https://doi.org/10.1016/j.ijproman.2018.03.006
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.