Towards integrating construction risk management and stakeholder management: A systematic literature review and future research agendas
The DOI matches its Crossref record; 89 of the 89 references it cites were found in a registry or an index.
Abstract
We propose that integrated management of construction risk and stakeholder is feasible and can promote the effectiveness of both risk management (RM) and stakeholder management (SM). A systematic literature review is conducted on the current construction literature involving both RM and SM, through which we identify four linkage modes between risk and stakeholder management. We further suggest future directions that enable integrating risk and stakeholder management to benefit the management process and/or management outcome of RM and SM. These linkages and directions shed light on enhancing the effectiveness of RM and SM through new ways of thinking about, analyzing, and then managing risks and stakeholders in a holistic and integrated way, but not the traditional endeavor in individual areas. Integrating risk and stakeholder management is challenging, but can be a novel way for improving project performance for which this research conceptually justifies its feasibility and benefits, which merits further study.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Content Analysis: An Introduction to its Methodology.
Shelley, M., & Krippendorff, K. (1984) · Journal of the American Statistical Association · doi:10.2307/2288384 · Cited by 24,312
(2010) · Cited by 24,023
The qualitative content analysis process
Elo, S., & Kyngäs, H. (2008) · Journal of Advanced Nursing · doi:10.1111/j.1365-2648.2007.04569.x · Cited by 22,617 · cited 1×
“To analyze those papers, the technique of content analysis is employed for compressing many words of text in an organized manner, identifying the focus of subject matter, and diagnosing emerging patterns in the current body of knowledge (Elo and Kyngäs, 2008; Krippendorff, 2004).”
MethodTranfield, D., Denyer, D., & Smart, P. (2003) · British Journal of Management · doi:10.1111/1467-8551.00375 · Cited by 15,386 · cited 1×
“The plan for a systematic literature review consists of establishing the literature review purpose and protocol (Denyer and Tranfield, 2009; Tranfield et al., 2003).”
BackgroundA Stakeholder Framework for Analyzing and Evaluating Corporate Social Performance
Clarkson, M. B. E. (1995) · The Academy of Management Review · doi:10.2307/258888 · Cited by 7,838
Mitchell, R. K., Agle, B. R., & Wood, D. J. (1997) · The Academy of Management Review · doi:10.2307/259247 · Cited by 5,039
A guide to the project management body of knowledge (PMBOK guide)
Pmbok (2004) · Cited by 4,316
Project management : a systems approach to planning, scheduling, and controlling
Kerzner, H. (1995) · Thammasat University Digital Collections · Cited by 3,099
Content Analysis in Mass Communication: Assessment and Reporting of Intercoder Reliability
Lombard, M., Snyder-Duch, J., & Bracken, C. C. (2002) · Human Communication Research · doi:10.1111/j.1468-2958.2002.tb00826.x · Cited by 3,068
Realist social theory the morphogenetic approach
Archer, M. S. (1995) · Cited by 2,938
The SAGE handbook of organizational research methods
Buchanan, D., & Bryman, A. E. (2009) · Cited by 2,558
Project management: A systems approach to planning, scheduling and controlling
Botter, C. H. (1982) · European Journal of Operational Research · doi:10.1016/0377-2217(82)90164-3 · Cited by 2,408
(2009) · Cited by 2,062
Risk assessment and risk management: Review of recent advances on their foundation
Aven, T. (2016) · European Journal of Operational Research · doi:10.1016/j.ejor.2015.12.023 · Cited by 1,713 · cited 4×
“Recent research in the generic risk field also calls for enhancing risk assessment and management by focusing on the background knowledge and the dynamic dimensions (Aven, 2016).”
BackgroundInfluentialFriedman, A. L., & Miles, S. (2002) · Journal of Management Studies · doi:10.1111/1467-6486.00280 · Cited by 1,306 · cited 2×
“For instance, the role of stakeholders' social structures (Archer, 1995; Friedman and Miles, 2002) warrants specific consideration.”
Thirty years of safety climate research: Reflections and future directions
Zohar, D. (2010) · Accident Analysis & Prevention · doi:10.1016/j.aap.2009.12.019 · Cited by 1,114 · cited 1×
“Furthermore, even when senior managers in a larger organization or project put high priority to risk, RM practices may vary across work subunits/groups (Zohar, 2010).”
BackgroundDeveloping design propositions through research synthesis
Denyer, D., Tranfield, D., & van Aken, J. E. (2008) · Organization Studies · doi:10.1177/0170840607088020 · Cited by 1,057
Underestimating Costs in Public Works Projects:Error or Lie?
Flyvbjerg, B., Holm, M. S., & Buhl, S. (2002) · Journal of the American Planning Association · doi:10.1080/01944360208976273 · Cited by 1,046 · cited 1×
“Despite the salience of both risk management (RM) and stakeholder management (SM) in construction projects, there are still numerous project failures resulting from poor management in risk and stakeholder (Flyvbjerg et al., 2002; Mok et al., 2015).”
BackgroundEnterprise Risk Management—Integrated Framework
Anand, S. (2012) · Wiley eBooks · doi:10.1002/9781119201939.app4 · Cited by 884
Understanding the key risks in construction projects in China
Zou, P. X. W., Zhang, G., & Wang, J. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2007.03.001 · Cited by 859 · cited 5×
“To pursue the success of construction projects, risk should be managed effectively (Chapman and Ward, 2004; Du et al., 2016; Zou et al., 2007).”
BackgroundMethodInfluentialSelf-citationOn risk defined as an event where the outcome is uncertain
Aven, T., & Renn, O. (2009) · Journal of Risk Research · doi:10.1080/13669870802488883 · Cited by 783 · cited 1×
“By definition, risk perception refers to individuals' subjective judgment of the risk (Aven and Renn, 2009), which is influenced by an individual's social structures, including interests, roles, and power differentials (Archer, 1995).”
BackgroundEvaluation of stakeholder influence in the implementation of construction projects
Olander, S., & Landin, A. (2005) · International Journal of Project Management · doi:10.1016/j.ijproman.2005.02.002 · Cited by 632 · cited 1×
“Accompanying the stakeholder diversity are the various and normally competing interests and concerns among project stakeholders (Olander, 2007; Olander and Landin, 2005).”
BackgroundStakeholder management studies in mega construction projects: A review and future directions
Mok, K. Y., Shen, G. Q., & Yang, J. (2015) · International Journal of Project Management · doi:10.1016/j.ijproman.2014.08.007 · Cited by 599
Project Risk Management: Processes, Techniques and Insights
Smith, J. U. M. (1998) · Journal of the Operational Research Society · doi:10.1057/palgrave.jors.2600022 · Cited by 555
Realist social theory: the morphogenetic approach
(1996) · Choice Reviews Online · doi:10.5860/choice.34-0623 · Cited by 553
Stakeholder management for public private partnerships
El-Gohary, N., Osman, H., & El-Diraby, T. E. (2006) · International Journal of Project Management · doi:10.1016/j.ijproman.2006.07.009 · Cited by 541
Visualising and mapping stakeholder influence
Bourne, L., & Walker, D. H. T. (2005) · Management Decision · doi:10.1108/00251740510597680 · Cited by 476
Stakeholder impact analysis in construction project management
Olander, S. (2007) · Construction Management and Economics · doi:10.1080/01446190600879125 · Cited by 474 · cited 3×
“Olander, 2007).”
BackgroundRisk assessment of construction projects
Zavadskas, E. K., Turskis, Z., & Tamošaitienė, J. (2010) · Journal of Civil Engineering and Management · doi:10.3846/jcem.2010.03 · Cited by 472 · cited 1×
“Poor implementation of these responsibilities expected by the society can pose threats to project outcomes, the magnitude of which seems to be growing but are often overlooked by project management teams (Aaltonen, 2011; Zavadskas et al., 2010).”
BackgroundSafety climate and injuries: An examination of theoretical and empirical relationships.
Beus, J. M., Payne, S. C., Bergman, M. E., & Arthur, W. (2010) · Journal of Applied Psychology · doi:10.1037/a0019164 · Cited by 459 · cited 1×
“Taking safety risk management as an example, a meta-analysis found management commitment to safety was the most critical safety climate for mitigating workplace injuries and accidents (Beus et al., 2010).”
MethodTowards a better modelling and assessment of construction risk: Insights from a literature review
Taroun, A. (2014) · International Journal of Project Management · doi:10.1016/j.ijproman.2013.03.004 · Cited by 387 · cited 8×
“Humans together with their subjective judgment are indispensable to perceive, assess, and deal with risks in the construction industry (Taroun, 2014; Wang and Yuan, 2011; C. M. Wang et al., 2016), therefore, the abovementioned risk-related differences among stakeholders cannot be neglected.”
BackgroundInfluentialLee, M., Wu, Y., & Tsai, C. (2009) · International Journal of Science Education · doi:10.1080/09500690802314876 · Cited by 378
Project risk management in the Queensland engineering construction industry: a survey
Lyons, T., & Skitmore, M. (2004) · International Journal of Project Management · doi:10.1016/s0263-7863(03)00005-x · Cited by 340
Benefits of management systems integration: a literature review
Bernardo, M., Simon, A., Tarí, J. J., & Molina-Azorín, J. F. (2015) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2015.01.075 · Cited by 332 · cited 2×
“For example, a literature review of quality and environment IMSs has found it to be of greater benefits than implementing quality and environment management separately, resulting in improvements such as cost savings and a more positive organizational image (Bernardo et al., 2015).”
BackgroundYang, R. J., & Zou, P. X. W. (2014) · Building and Environment · doi:10.1016/j.buildenv.2013.12.014 · Cited by 321
Self-citationQuantifying schedule risk in construction projects using Bayesian belief networks
Luu, V. T., Kim, S.-Y., Tuan, N. V., & Ogunlana, S. O. (2008) · International Journal of Project Management · doi:10.1016/j.ijproman.2008.03.003 · Cited by 309
Tsai, C., & Lydia Wen, M. (2005) · International Journal of Science Education · doi:10.1080/0950069042000243727 · Cited by 307 · cited 1×
“…of synthesizing the existing body of knowledge, keholder concepts, management processes, and outcomes. creating new knowledge on a wider scale than is possible with empirical studies, and identifying new agendas for future research (Denyer and Tranfield, 2009; Taroun, 2014; Tsai and Wen, 2005).”
BackgroundA corporate social responsibility indicator system for construction enterprises
Zhao, Z.-Y., Zhao, X.-J., Davidson, K., & Zuo, J. (2012) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2011.12.036 · Cited by 307 · cited 1×
“, 2015), which often address the social objectives or responsibilities of business activities (Zhao et al., 2012).”
BackgroundStakeholder Engagement: Achieving Sustainability in the Construction Sector
Bal, M., Bryde, D., Fearon, D., & Ochieng, E. (2013) · Sustainability · doi:10.3390/su5020695 · Cited by 299 · cited 1×
“Defective SM processes such as inadequate attention to the demands of certain stakeholder at the planning stage will increase potential threats at later stages (Bal et al., 2013).”
BackgroundProject Stakeholder Management
Karlsen, J. T. (2002) · Engineering Management Journal · doi:10.1080/10429247.2002.11415180 · Cited by 296 · cited 1×
“…stakeholder analysis and assessment (assessing stakeholder interests/attributes and relationships in a qualitative and/or quantitative way), developing strategies for managing stakeholders, and executing and controlling SM strategies (Aaltonen et al., 2015; Karlsen, 2002; Mok et al., 2015).”
BackgroundLock, D. (1987) · Cited by 258
Risk management in small construction projects in Singapore: Status, barriers and impact
Hwang, B.-G., Zhao, X., & Toh, L. P. (2014) · International Journal of Project Management · doi:10.1016/j.ijproman.2013.01.007 · Cited by 234 · cited 1×
“Following this definition, the purpose of project RM is to increase the likelihood and impact of positive events, and reduce those of negative events in the project (Arashpour et al., 2017; Hwang et al., 2014).”
MethodProject stakeholder analysis as an environmental interpretation process
Aaltonen, K. (2011) · International Journal of Project Management · doi:10.1016/j.ijproman.2010.02.001 · Cited by 228 · cited 2×
“Poor implementation of these responsibilities expected by the society can pose threats to project outcomes, the magnitude of which seems to be growing but are often overlooked by project management teams (Aaltonen, 2011; Zavadskas et al., 2010).”
BackgroundInfluence, stakeholder mapping and visualization
Walker, D. H. T., Bourne, L. M., & Shelley, A. (2008) · Construction Management and Economics · doi:10.1080/01446190701882390 · Cited by 221 · cited 1×
“Typically, an external stakeholder lacks any formal project authority (Aaltonen, 2011; Walker et al., 2008).”
BackgroundInvestigating the use of the stakeholder notion in project management literature, a meta-analysis
Achterkamp, M. C., & Vos, J. F. J. (2008) · International Journal of Project Management · doi:10.1016/j.ijproman.2007.10.001 · Cited by 221 · cited 3×
“Meta-analyses of stakeholder theory applications in a project context have shown that management of stakeholders is vital to the successful implementation of various kinds of projects, among which the construction industry is a dominant sector (Achterkamp and Vos, 2008; Littau et al., 2010).”
BackgroundFactors affecting contractors’ risk attitudes in construction projects: Case study from China
Wang, J., & Yuan, H. (2011) · International Journal of Project Management · doi:10.1016/j.ijproman.2010.02.006 · Cited by 216 · cited 2×
“Specifically, risk-based decisions such as the decision on the concession period between the public and private sector in a PPP arrangement can vary (Xu and Moon, 2014) can vary among stakeholders (e.g., Shealy et al., 2016; Van Os et al., 2015; Wang and Yuan, 2011; J. Wang et al., 2016).”
BackgroundIn search of opportunity management: Is the risk management process enough?
Olsson, R. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2007.03.005 · Cited by 214 · cited 3×
“Research a negative (threat) or positive (opportunity) impact on one or more project objectives (Chapman and Ward, 2003; Lehtiranta, 2014; Olsson, 2007; PMI, 2013).”
BackgroundModelling stakeholder-associated risk networks in green building projects
Yang, R. J., Zou, P. X. W., & Wang, J. (2016) · International Journal of Project Management · doi:10.1016/j.ijproman.2015.09.010 · Cited by 207 · cited 1×
“Academia should make efforts to advance such a fundamental and likely difficult transformation, because the construction practice has a lasting negative view on the risk and the stakeholder (Wang et al., 2017; Yang et al., 2016; Zou et al., 2007).”
BackgroundSelf-citationThe ranking of construction management journals
Wing, C. K. (1997) · Construction Management and Economics · doi:10.1080/014461997372953 · Cited by 198
Risk Management in the Chinese Construction Industry
Tang, W., Qiang, M., Duffield, C. F., Young, D. M., & Lu, Y. (2007) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2007)133:12(944 · Cited by 198 · cited 1×
“Among the included literature, empirical surveys in various countries or regions also reveal that although practitioners desire joint RM, in reality, the mechanism for such a joint effort is lacking (Choudhry and Iqbal, 2013; Nguyen and Chileshe, 2015; Tang et al., 2007).”
Background25 Years of Stakeholder Theory in Project Management Literature (1984-2009)
Littau, P., Jujagiri, N. J., & Adlbrecht, G. (2010) · Project Management Journal · doi:10.1002/pmj.20195 · Cited by 197 · cited 1×
“Two of the present authors first coded all the target articles published, and subsequently compared and discussed the results case by case to resolve the discrepancies in coding (Lombard et al., 2002).”
BackgroundStakeholders and uncertainty management in projects
Ward, S., & Chapman, C. (2008) · Construction Management and Economics · doi:10.1080/01446190801998708 · Cited by 196
Risk/Reward Compensation Model for Civil Engineering Infrastructure Alliance Projects
Love, P. E. D., Davis, P. R., Chevis, R., & Edwards, D. J. (2010) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000263 · Cited by 185
Cuppen, E. H. W. J., Bosch-Rekveldt, M. G. C., Pikaar, E., & Mehos, D. C. (2016) · International Journal of Project Management · doi:10.1016/j.ijproman.2016.01.003 · Cited by 183 · cited 2×
“Collaboration between the internal and external groups may also be possible (Cuppen et al., 2016).”
BackgroundA review of stakeholder management performance attributes in construction projects
Oppong, G. D., Chan, A. P. C., & Dansoh, A. (2017) · International Journal of Project Management · doi:10.1016/j.ijproman.2017.04.015 · Cited by 181 · cited 4×
“In addition, the construction industry seems to lack a well-established scale for measuring SM outcomes (Oppong et al., 2017).”
BackgroundInfluentialWang, C. M., Xu, B. B., Zhang, S., & Chen, Y. Q. (2016) · International Journal of Project Management · doi:10.1016/j.ijproman.2016.07.004 · Cited by 172
Critical factors and paths influencing construction workers’ safety risk tolerances
Wang, J., Zou, P. X. W., & Li, P. P. (2016) · Accident Analysis & Prevention · doi:10.1016/j.aap.2015.11.027 · Cited by 170
Self-citationLinking corporate social responsibility and organizational performance in the construction industry
Loosemore, M., & Lim, B. T. H. (2017) · Construction Management and Economics · doi:10.1080/01446193.2016.1242762 · Cited by 169
Why risk efficiency is a key aspect of best practice projects
Chapman, C. B., & Ward, S. C. (2004) · International Journal of Project Management · doi:10.1016/j.ijproman.2004.05.001 · Cited by 169 · cited 1×
“To pursue the success of construction projects, risk should be managed effectively (Chapman and Ward, 2004; Du et al., 2016; Zou et al., 2007).”
BackgroundZou, P. X. W., Chen, Y., & Chan, T.-Y. (2009) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000175 · Cited by 165 · cited 1×
“RM attitudes from upper leaders and RM culture among team members across different levels are indispensable in determining a construction stakeholder's overall RM capability (Loosemore et al., 2006; Zou et al., 2010).”
BackgroundSelf-citationGuo, F., Chang-Richards, Y., Wilkinson, S., & Li, T. C. (2014) · International Journal of Project Management · doi:10.1016/j.ijproman.2013.10.001 · Cited by 163
A method to measure success dimensions relating to individual stakeholder groups
Davis, K. (2016) · International Journal of Project Management · doi:10.1016/j.ijproman.2015.12.009 · Cited by 153 · cited 1×
“Likewise, the outcomes of SM have also considered as one indicator of project success (Davis, 2016).”
BackgroundCritical Reading and Writing for Postgraduates
Wall, K. (2007) · DOAJ (DOAJ: Directory of Open Access Journals) · Cited by 140
Mostafa, S., Chileshe, N., & Abdelhamid, T. (2016) · Construction Innovation · doi:10.1108/ci-09-2014-0043 · Cited by 139
Zhang, S., Zhang, S., Gao, Y., & Ding, X. (2016) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001111 · Cited by 126 · cited 1×
“But investigation of the mechanisms through which RM process elements such as risk allocation would influence SM outcomes has been rare (Zhang et al., 2016).”
BackgroundContractor’s Risk Attitudes in the Selection of International Construction Projects
Han, S. H., Diekmann, J. E., & Ock, J. H. (2005) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2005)131:3(283 · Cited by 125
Stakeholder Dynamics during the Project Front-End: The Case of Nuclear Waste Repository Projects
Aaltonen, K., Kujala, J., Havela, L., et al. (2015) · Project Management Journal · doi:10.1002/pmj.21549 · Cited by 119 · cited 1×
“Traditionally, full SM process in construction projects involves the following steps: collecting stakeholder-related document and making stakeholder management planning, stakeholder identification and classification, stakeholder analysis and assessment (assessing stakeholder interests/attributes and relationships in a…”
Wang, T., Tang, W., Du, L., Duffield, C. F., & Wei, Y. (2016) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000459 · Cited by 102
Critical Reading and Writing for Postgraduates
Wallace, M., & Alison Wray, A. (2006) · ORCA Online Research @Cardiff (Cardiff University) · Cited by 101
Quality and Safety Management in Construction
Loushine, T. W., Hoonakker, P., Carayon, P., & Smith, M. J. (2006) · Total Quality Management & Business Excellence · doi:10.1080/14783360600750469 · Cited by 99
Assessing risk management capability of contractors in subway projects in mainland China
Mu, S., Cheng, H., Chohr, M., & Peng, W. (2013) · International Journal of Project Management · doi:10.1016/j.ijproman.2013.08.007 · Cited by 97 · cited 1×
“Empirical investigations on RM practices also show that RM attitudes or systems at the upper organization can be poor, notwithstanding the relatively mature techniques specific for analyzing project risk (Choudhry and Iqbal, 2013; Mu et al., 2014).”
BackgroundYang, R. J., Wang, Y., & Jin, X. (2014) · Project Management Journal · doi:10.1002/pmj.21412 · Cited by 97 · cited 1×
“As argued by construction studies (Oppong et al., 2017; Xia et al., 2017; Yang et al., 2014), a broad stakeholder definition seems to best fit construction”
BackgroundRevisiting the construction project failure factors in Vietnam
Nguyen, T. P., & Chileshe, N. (2015) · Built Environment Project and Asset Management · doi:10.1108/bepam-10-2013-0042 · Cited by 97 · cited 1×
“Among the included literature, empirical surveys in various countries or regions also reveal that although practitioners desire joint RM, in reality, the mechanism for such a joint effort is lacking (Choudhry and Iqbal, 2013; Nguyen and Chileshe, 2015; Tang et al., 2007).”
BackgroundArashpour, M., Abbasi, B., Arashpour, M., Hosseini, M. R., & Yang, R. J. (2017) · International Journal of Project Management · doi:10.1016/j.ijproman.2017.02.016 · Cited by 93 · cited 1×
“Following this definition, the purpose of project RM is to increase the likelihood and impact of positive events, and reduce those of negative events in the project (Arashpour et al., 2017; Hwang et al., 2014).”
MethodOn the management of social risks of hydraulic infrastructure projects in China: A case study
Shi, Q., Liu, Y., Zuo, J., Pan, N., & Ma, G. (2014) · International Journal of Project Management · doi:10.1016/j.ijproman.2014.06.003 · Cited by 92 · cited 2×
“Threats arising from external groups involve such as opposition from project affected communities (Shi et al., 2015), which often address the social objectives or responsibilities of business activities (Zhao et al.”
BackgroundQuantile Uncertainty and Value‐at‐Risk Model Risk
Alexander, C., & Sarabia, J. M. (2012) · Risk Analysis · doi:10.1111/j.1539-6924.2012.01824.x · Cited by 82 · cited 1×
“, Value-at-Risk (VaR))metrics (Alexander and Sarabia, 2012; Aven, 2016); in the construction industry, the dominant metric is the multiplication of the risk's probability and severity (Taroun, 2014).”
BackgroundRisk Management Affecting IS/IT Project Success through Communicative Action
de Bakker, K., Boonstra, A., & Wortmann, H. (2011) · Project Management Journal · doi:10.1002/pmj.20242 · Cited by 79
Xia, N., Zhong, R., Wu, C., Wang, X., & Wang, S. (2017) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001322 · Cited by 71 · cited 3×
“For example, it has been contended that less is known about how risks are perceived by individuals (Xia et al., 2017) despite the prevailing Probability–Impact (P\I) risk model evaluating risk quantitatively and rationally (Taroun, 2014).”
BackgroundSelf-citationTymvios, N., & Gambatese, J. (2015) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001067 · Cited by 69
Understanding delays in housing construction: evidence from Northern Ireland
McCord, J., McCord, M. J., Davis, P. T., Haran, M. E., & Rodgers, W. J. (2015) · Journal of Financial Management of Property and Construction · doi:10.1108/jfmpc-07-2015-0028 · Cited by 66
Relational Risk Management in Construction Projects: Modeling the Complexity
Lehtiranta, L. (2011) · Leadership and Management in Engineering · doi:10.1061/(asce)lm.1943-5630.0000114 · Cited by 55 · cited 1×
“Such risk can be termed as “project network risk”, referring to a specific set of risk conditions or events that result from work linkages, interfaces among two or more stakeholders (Lehtiranta, 2011; Lowe and Leiringer, 2006; Shokri et al., 2016).”
BackgroundUsing Framing Effects to Inform More Sustainable Infrastructure Design Decisions
Shealy, T., Klotz, L. E., Weber, E. U., Johnson, E. J., & Bell, R. G. (2016) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001152 · Cited by 51
Commercial Management of Projects: Defining the Discipline
Lowe, D., & Leiringer, R. (2006) · Wiley eBooks · doi:10.1002/9780470759509 · Cited by 49 · cited 1×
“Such risk can be termed as “project network risk”, referring to a specific set of risk conditions or events that result from work linkages, interfaces among two or more stakeholders (Lehtiranta, 2011; Lowe and Leiringer, 2006; Shokri et al., 2016).”
BackgroundHuman Safety Risks and Their Interactions in China’s Subways: Stakeholder Perspectives
Wang, X., Xia, N., Zhang, Z., Wu, C., & Liu, B. (2017) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000544 · Cited by 47 · cited 1×
“Academia should make efforts to advance such a fundamental and likely difficult transformation, because the construction practice has a lasting negative view on the risk and the stakeholder (Wang et al., 2017; Yang et al., 2016; Zou et al., 2007).”
BackgroundSelf-citationPrediction of Total Cost of Construction Project with Dependent Cost Items
Firouzi, A., Yang, W. H., & Li, C. (2016) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001194 · Cited by 43
A Fuzzy-Based Integrated Framework for Assessing Time Contingency in Construction Projects
Pawan, P., & Lorterapong, P. (2015) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0001073 · Cited by 42 · cited 1×
“In the construction sector, RM has been frequently integrated into the fields of quality, cost, schedule, and safety management (Loushine et al., 2006; Love et al., 2016; Luu et al., 2009; Pawan and Lorterapong, 2016).”
van Os, A., van Berkel, F. J. F. W., de Gilder, D., van Dyck, C., & Groenewegen, P. (2014) · International Journal of Project Management · doi:10.1016/j.ijproman.2014.10.016 · Cited by 40
Urban regeneration and democratization of information access: CitiStat experience in Baltimore
Gullino, S. (2008) · Journal of Environmental Management · doi:10.1016/j.jenvman.2007.08.027 · Cited by 35 · cited 1×
“External stakeholders can also bring benefits to the projects, for example, they may provide useful suggestions with their “local” knowledge (Gullino, 2009).”
BackgroundHwang, B., & Han Boey, N. G. (2015) · Technological and Economic Development of Economy · doi:10.3846/20294913.2015.1067847 · Cited by 28 · cited 2×
“Construction projects are also frequently faced with complex problems related to stakeholders, including conflict among project team members such as clients and contractors (Hwang and Ng, 2016; Lehtiranta, 2014), as well as protest from external parties such as the affected community (Mok et al.”
Background
Cited by
Halder, A. (2024) · Innovative Infrastructure Solutions · doi:10.1007/s41062-024-01521-6 · Cited by 10
Metadata
- Authors
- Xia, N., Zou, P. X. W., Griffin, M. A., Wang, X., & Zhong, R.
- Venue
- International Journal of Project Management
- Publisher
- Elsevier BV
- Published
- 2018-07
- Volume
- 36
- Issue
- 5
- Pages
- 701-715
- ISSN
- 0263-7863 (ISSN-L)
- OpenAlex
- W2802787660
- Cited by
- 229
- References
- 89
- FWCI
- 3.37
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.