Critical Factors Affecting Schedule Performance: Evidence from Indian Construction Projects
The DOI matches its Crossref record; 14 of the 14 references it cites were found in a registry or an index.
Abstract
Over 40% of Indian construction projects are facing time overrun ranging from 1 to 252 months; the reasons for which are being studied by researchers to suggest possible remedial measures. This paper identifies 55 attributes responsible for impacting performance of the projects. These attributes were then presented to Indian construction professionals in the form of a questionnaire. Statistical analysis of responses on the attributes segregated them into distinct sets of success attributes and failure attributes. Factor analysis of sets of success attributes and failure attributes separately grouped them into six critical success factors and seven critical failure factors. In order to understand the extent of contribution these factors have on the outcome of a construction project, a second stage questionnaire survey was also undertaken. The analyses of responses of the second stage questionnaire led us to conclude that two success factors and one failure factor: commitment of project participants; owner’s competence; and conflict among project participants contribute significantly in enhancement of current performance level of the project. The extent of their contribution has, however, been observed to vary for a given level of project performance. The analyses results are expected to help project professionals to focus on a few factors and get the optimum results rather than giving attention to all the factors and not getting the proportionate results.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Critical Success Factors for Public–Private Partnerships in Infrastructure Development
Zhang, X. (2005) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2005)131:1(3 · Cited by 748
The changing role of the information systems executive : a critical success factors perspectivePreprint
Rockart, J. F. (1980) · RePEc: Research Papers in Economics · Cited by 550
Systems Analysis and Project Management.
Schmidt, R. N., Cleland, D. I., & King, W. R. (1969) · Administrative Science Quarterly · doi:10.2307/2391604 · Cited by 411
Factors Affecting Project Success
Baker, B. N., Murphy, D. C., & Fisher, D. (1997) · Project Management Handbook · doi:10.1002/9780470172353.ch35 · Cited by 401
Design and Build Project Success Factors: Multivariate Analysis
Chan, A. P. C., Ho, D. C. K., & Tam, C. M. (2001) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2001)127:2(93 · Cited by 316
Morris, P. W. G., & Hough, G. (1987) · UCL Discovery (University College London) · Cited by 300
Critical Success Factors in R&D Projects
Pinto, J. K., & Slevin, D. P. (1989) · Research-Technology Management · doi:10.1080/08956308.1989.11670572 · Cited by 294
Constructive Conflict Resolution: Principles, Training, and Research
Deutsch, M. (1994) · Journal of Social Issues · doi:10.1111/j.1540-4560.1994.tb02395.x · Cited by 239
Why Does Project Management Fail?
Avots, I. (1969) · California Management Review · doi:10.2307/41164208 · Cited by 167
Conceptual Model of Partnering
Crowley, L. G., & Karim, M. A. (1995) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(1995)11:5(33 · Cited by 162
The conflict-positive organization : stimulate diversity and create unity
Tjosvold, D. (1990) · Cited by 154
Rowlinson, S., & McDermott, P. (2005) · Routledge eBooks · doi:10.4324/9780203982785 · Cited by 105
Critical Success Factors for the Construction Industry
Abraham, G. L. (2003) · Construction Research Congress · doi:10.1061/40671(2003)63 · Cited by 66
Conflict management styles in Hong Kong industries
Cheung, C. C., & Chuah, K. B. (1999) · International Journal of Project Management · doi:10.1016/s0263-7863(98)00059-3 · Cited by 58
Cited by
Stakeholder management studies in mega construction projects: A review and future directions
Mok, K. Y., Shen, G. Q., & Yang, J. (2015) · International Journal of Project Management · doi:10.1016/j.ijproman.2014.08.007 · Cited by 599
Critical analysis of green building research trend in construction journals
Darko, A., & Chan, A. P. C. (2016) · Habitat International · doi:10.1016/j.habitatint.2016.07.001 · Cited by 342
A fuzzy synthetic evaluation approach for risk assessment: a case of Singapore's green projects
Zhao, X., Hwang, B.-G., & Gao, Y. (2016) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2015.11.042 · Cited by 279
Causes of delays on construction projects: a comprehensive list
Durdyev, S., & Hosseini, M. R. (2019) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-09-2018-0178 · Cited by 245
Commitment, coordination, competence and the iron triangle
Jha, K. N., & Iyer, K. C. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2006.11.009 · Cited by 243
“These 55 attributes were collected through case studies, project management literatures and personal interviews of experts in construction industry [24,27].”
BackgroundMethodSelf-citation
Metadata
- Authors
- Iyer, K. C., & Jha, K. N.
- Venue
- Journal of Construction Engineering and Management
- Published
- 2006-08
- Volume
- 132
- Issue
- 8
- Pages
- 871-881
- ISSN
- 0733-9364 (ISSN-L)
- 1943-7862
- DOI
- 10.1061/(asce)0733-9364(2006)132:8(871
- OpenAlex
- W2168188048
- Cited by
- 244
- References
- 14
- FWCI
- 6.24
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.