Causes of delays on construction projects: a comprehensive list

Open access
Durdyev, Serdar, Hosseini, M. Reza · 2019 · International Journal of Managing Projects in Business

Abstract

Purpose: The purpose of this paper is to present a systematic review of studies on CPD published between 1985 and 2018. Design/methodology/approach: Before identifying common CPD, research trends were examined in terms of the number of publications in selected journals, as well as the contributions made by countries, institutions and researchers. Findings: The findings reveal that researchers from developing countries have contributed the most to identifying the causes of CPD. A total of 149 causes of CPD were identified in a thorough review of 97 selected studies. Weather/climate conditions, poor communication, lack of coordination and conflicts between stakeholders, ineffective or improper planning, material shortages, financial problems, payment delays, equipment/plant shortage, lack of experience/qualification/competence among project stakeholders, labour shortages and poor site management were identified as the ten most common CPDs. Originality/value: Being the first study of its type, this study provides insight into the research output related to this area and identifies a common set of CPDs, which may provide a better understanding of the key areas requiring attention where steps should be taken to minimise or control factors causing delays in construction projects.

Overview

The claims and statistics of this paper haven’t been checked yet.

Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.

A few free checks a day · papers already verified open instantly · results are public

Integrity signals

Registry

Crossref · 10.1108/ijmpb-09-2018-0178

Cites

2 of 2 references verified0 citation errors · 0 not checkable

Statistics

Verification

Claims the paper makes

The claims and statistics of this paper haven’t been checked yet.

Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.

A few free checks a day · papers already verified open instantly · results are public

Self-check

Percentages, sums and reported differences re-computed from the paper’s own numbers.

The self-check needs the paper’s full text.

Citations

Cites

Show all 2 references

Cited by

See all 245

Metadata

Authors
Durdyev, S., & Hosseini, M. R.
Venue
International Journal of Managing Projects in Business
Publisher
Emerald
Published
2019-04-12
Volume
13
Issue
1
Pages
20-46
ISSN
1753-8378 (ISSN-L)
OpenAlex
W2946135269
Cited by
245
References
2
FWCI
14.13
Type
journal article
Language
en
Open access
green

About these checks

Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.

Statistics and arithmetic are recomputed, not judged.

Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.

What counts as a claim ›How we measure confidence ›How we check this ›

Are you an author, or do you see a problem with this page? Request a review

How to cite

Cite CoChat for the checks on this page, and the paper for its own findings.

This page
CoChat. (2026). Citation check: Causes of delays on construction projects: a comprehensive list. https://app.cochat.ai/papers/10.1108/ijmpb-09-2018-0178
The paper
Durdyev, S., & Hosseini, M. R. (2019). Causes of delays on construction projects: a comprehensive list. International Journal of Managing Projects in Business. https://doi.org/10.1108/ijmpb-09-2018-0178

Data sources

Bibliographic data: Semantic Scholar, OpenAlex, Crossref.

Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).

Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.