Illustrative Benchmarking Rework and Rework Costs in Swedish Construction Industry
The DOI matches its Crossref record; 10 of the 10 references it cites were found in a registry or an index.
Abstract
Following several studies investigating the causes of construction rework among some projects in the Swedish construction industry, we conducted this study in cooperation with R&D West, a group of construction companies in Sweden, to measure the costs of rework in construction projects. Rework has become an endemic feature of the procurement process in construction that invariably leads to time and cost overruns in projects. Thus, in order to improve the performance of projects, it is necessary to identify the causes and costs of construction rework. The research presented in this paper identifies, analyzes, and discusses the causes, magnitudes, and costs of rework experienced in seven Swedish construction projects. The findings revealed that the costs of rework for the case study projects were 4.4% of the construction values of the observation period, and the time needed to correct them was 7.1% of the total work time. The construction errors that generated rework were further analyzed according to their origins, types, and positions, causes of construction rework were identified and discussed, and preventive actions were suggested.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
(1984) · Cited by 81,983
Mixing Qualitative and Quantitative Methods: Triangulation in Action.
Jick, T. D. (1979) · Administrative Science Quarterly · doi:10.2307/2392366 · Cited by 7,103
Yin, Robert K., Case Study Research: Design and Methods, 2nd ed. Newbury Park, CA: Sage, 1994.
Yin, R. K. (1994) · Journal of International Crisis and Risk Communication Research · Cited by 2,155
Feigenbaum, A. V. (1961) · Cited by 1,551
The Case Study as a Serious Research Strategy
Yin, R. K. (1981) · Knowledge · doi:10.1177/107554708100300106 · Cited by 738
The causes and costs of defects in construction
Josephson, P.-E., & Hammarlund, Y. (1999) · Automation in Construction · doi:10.1016/s0926-5805(98)00114-9 · Cited by 410
Self-citationZiegel, E. R., & Fergenbaum, A. (1992) · Technometrics · doi:10.2307/1270069 · Cited by 296
Determining the causal structure of rework influences in construction
LOVE, P. E. D., MANDAL, P., & LI, H. (1999) · Construction Management and Economics · doi:10.1080/014461999371420 · Cited by 211
Self-citationRework: a symptom of a dysfunctional supply-chain
Love, P. E. D., Li, H., & Mandal, P. (1999) · European Journal of Purchasing & Supply Management · doi:10.1016/s0969-7012(98)00017-3 · Cited by 134
Self-citationQuality management in civil and structural engineering consulting
Oakland, J. S., & Aldridge, A. J. (1995) · International Journal of Quality & Reliability Management · doi:10.1108/02656719510084763 · Cited by 57
Cited by
Park, C.-S., Lee, D.-Y., Kwon, O.-S., & Wang, X. (2013) · Automation in Construction · doi:10.1016/j.autcon.2012.09.010 · Cited by 367
Taxonomy for change causes and effects in construction projects
Sun, M., & Meng, X. (2009) · International Journal of Project Management · doi:10.1016/j.ijproman.2008.10.005 · Cited by 331
Analyzing Causes for Reworks in Construction Projects in China
Ye, G., Jin, Z., Xia, B., & Skitmore, M. (2015) · Journal of Management in Engineering · doi:10.1061/(asce)me.1943-5479.0000347 · Cited by 178
Integrating three-dimensional road design and pavement structure analysis based on BIM
Tang, F., Ma, T., Zhang, J., Guan, Y., & Chen, L. (2020) · Automation in Construction · doi:10.1016/j.autcon.2020.103152 · Cited by 170
Ding, Z., Liu, S., Liao, L., & Zhang, L. (2019) · Automation in Construction · doi:10.1016/j.autcon.2019.02.012 · Cited by 163
Taheri, A., & Sobanjo, J. (2024) · Infrastructures · doi:10.3390/infrastructures9060090 · Cited by 17
Metadata
- Authors
- Josephson, P.-E., Larsson, B., & Li, H.
- Venue
- Journal of Management in Engineering
- Published
- 2002-04
- Volume
- 18
- Issue
- 2
- Pages
- 76-83
- ISSN
- 0742-597X (ISSN-L)
- 1943-5479
- DOI
- 10.1061/(asce)0742-597x(2002)18:2(76
- OpenAlex
- W2116399486
- Cited by
- 214
- References
- 10
- FWCI
- 3.25
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.