Illustrative Benchmarking Rework and Rework Costs in Swedish Construction Industry

Josephson, Per-Erik, Larsson, Bengt, Li, Heng · 2002 · Journal of Management in Engineering
DOI 10.1061/(asce)0742-597x(2002)18:2(76
Cited by 214

The DOI matches its Crossref record; 1 of the 1 references it cites were found in a registry or an index.

Abstract

Following several studies investigating the causes of construction rework among some projects in the Swedish construction industry, we conducted this study in cooperation with R&D West, a group of construction companies in Sweden, to measure the costs of rework in construction projects. Rework has become an endemic feature of the procurement process in construction that invariably leads to time and cost overruns in projects. Thus, in order to improve the performance of projects, it is necessary to identify the causes and costs of construction rework. The research presented in this paper identifies, analyzes, and discusses the causes, magnitudes, and costs of rework experienced in seven Swedish construction projects. The findings revealed that the costs of rework for the case study projects were 4.4% of the construction values of the observation period, and the time needed to correct them was 7.1% of the total work time. The construction errors that generated rework were further analyzed according to their origins, types, and positions, causes of construction rework were identified and discussed, and preventive actions were suggested.

Overview

The claims and statistics of this paper haven’t been checked yet.

Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.

A few free checks a day · papers already verified open instantly · results are public

Integrity signals

Registry

Crossref · 10.1061/(asce)0742-597x(2002)18:2(76)

Cites

1 of 1 references verified0 citation errors · 0 not checkable

Statistics

Verification

Claims the paper makes

The claims and statistics of this paper haven’t been checked yet.

Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.

A few free checks a day · papers already verified open instantly · results are public

Self-check

Percentages, sums and reported differences re-computed from the paper’s own numbers.

The self-check needs the paper’s full text.

Citations

Cites

Cited by

See all 214

Metadata

Authors
Josephson, P.-E., Larsson, B., & Li, H.
Venue
Journal of Management in Engineering
Published
2002-04
Volume
18
Issue
2
Pages
76-83
ISSN
  • 0742-597X (ISSN-L)
  • 1943-5479
DOI
10.1061/(asce)0742-597x(2002)18:2(76
OpenAlex
W2116399486
Cited by
214
References
1
FWCI
3.25
Type
journal article
Language
en
Open access
closed

About these checks

Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.

Statistics and arithmetic are recomputed, not judged.

Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.

What counts as a claim ›How we measure confidence ›How we check this ›

Are you an author, or do you see a problem with this page? Request a review

Data sources

Bibliographic data: Semantic Scholar, OpenAlex, Crossref.

Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).

Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.