Analyzing Causes for Reworks in Construction Projects in China
The DOI matches its Crossref record; 26 of the 26 references it cites were found in a registry or an index.
Abstract
Although rework is a common phenomenon in the Chinese construction industry and significantly affects project success, the reasons for rework remain largely unknown and most construction companies are unable to manage the issue effectively. To investigate the causes of rework in construction projects, a total of 39 causes were first identified through a comprehensive literature review and semistructured interviews with 13 experienced construction professionals in China. A questionnaire survey was further conducted to prioritize these causes, in which unclear project process management, poor quality of construction technology, and the use of poor construction materials rank the highest. Finally, a factor analysis revealed 11 major underlying dimensions of these causes, relating to design management, communication management, field management, project scope management, project process management, active rework, project plan changes, subcontractor management, contract management, owner capability, and the external environment. The contribution of this work lies in its examination of the underlying causes of rework perceived by construction professionals in the world’s largest developing country, which is characterized by its unique economic and social systems. In particular, newly identifed causes of contract management, active rework, and scope management help expand existing knowledge of the underlying causes of rework for the global construction community.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Marketing Research: An Applied Orientation
Kahle, L. R., & Malhotra, N. K. (1994) · Journal of Marketing Research · doi:10.2307/3151953 · Cited by 7,087
Questionnaire Design, Interviewing and Attitude Measurement
Albuam, G., & Oppenheim, A. N. (1993) · Journal of Marketing Research · doi:10.2307/3172892 · Cited by 4,971
Project management : a systems approach to planning, scheduling, and controlling
Kerzner, H. (1995) · Thammasat University Digital Collections · Cited by 3,099
Research methods for construction
Fellowa, R., & Liu, A. M. M. (2003) · Cited by 1,448
Survey Methods in Social Investigation.
T., C. G., & Moser, C. A. (1958) · The Incorporated Statistician · doi:10.2307/2986383 · Cited by 1,434
Vonnahme, M. C. (2002) · Cited by 806
Survey Methods in Social Investigation.
Moss, L., Moser, C. A., & Kalton, G. (1972) · Journal of the Royal Statistical Society. Series A (General) · doi:10.2307/2344698 · Cited by 552
Quantifying the causes and costs of rework in construction
Love, P. E. D., & Li, H. (2000) · Construction Management and Economics · doi:10.1080/01446190050024897 · Cited by 486
Influence of Project Type and Procurement Method on Rework Costs in Building Construction Projects
Love, P. E. D. (2002) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2002)128:1(18 · Cited by 463
The causes and costs of defects in construction
Josephson, P.-E., & Hammarlund, Y. (1999) · Automation in Construction · doi:10.1016/s0926-5805(98)00114-9 · Cited by 410
Metadata
- Authors
- Ye, G., Jin, Z., Xia, B., & Skitmore, M.
- Venue
- Journal of Management in Engineering
- Published
- 2015-11
- Volume
- 31
- Issue
- 6
- ISSN
- 0742-597X (ISSN-L)
- 1943-5479
- OpenAlex
- W2013323185
- Cited by
- 178
- References
- 26
- FWCI
- 5.75
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
How to cite
Cite CoChat for the checks on this page, and the paper for its own findings.
- This page
- CoChat. (2026). Citation check: Analyzing Causes for Reworks in Construction Projects in China. https://app.cochat.ai/papers/10.1061/(asce)me.1943-5479.0000347
- The paper
- Ye, G., Jin, Z., Xia, B., & Skitmore, M. (2015). Analyzing Causes for Reworks in Construction Projects in China. Journal of Management in Engineering. https://doi.org/10.1061/(asce)me.1943-5479.0000347
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.