Determining the Probability of Project Cost Overruns
The DOI matches its Crossref record; 30 of the 30 references it cites were found in a registry or an index.
Abstract
The statistical characteristics of cost overruns experienced from contract award in 276 Australian construction and engineering projects were analyzed. The skewness and kurtosis values of the cost overruns are computed to determine if the empirical distribution of the data follows a normal distribution. The Kolmogorov-Smirnov, Anderson-Darling, and chi-squared nonparametric tests are used to determine the goodness of fit of the selected probability distributions. A three-parameter Frechet probability function is found to describe the behavior of cost overruns and provide the best overall distribution fit. The Frechet distribution is then used to calculate the probability of a cost overrun being experienced. The statistical characteristics of contract size and cost overruns were also analyzed. The Cauchy (<A$1 million), Wakeby (A$1 to 10 million,
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Judgment under Uncertainty: Heuristics and Biases
(1982) · doi:10.1017/cbo9780511809477 · Cited by 8,240
An Introduction to Statistical Modeling of Extreme Values
Coles, S. (2001) · Springer Series in Statistics · doi:10.1007/978-1-4471-3675-0 · Cited by 7,352
Mersenne twister: a 623-dimensionally equidistributed uniform pseudo-random number generator
Matsumoto, M., & Nishimura, T. (1998) · ACM Transactions on Modeling and Computer Simulation · doi:10.1145/272991.272995 · Cited by 5,780
Questionnaire Design, Interviewing and Attitude Measurement
Albuam, G., & Oppenheim, A. N. (1993) · Journal of Marketing Research · doi:10.2307/3172892 · Cited by 4,971
Judgment under uncertainty: List of contributors
Kahneman, D. J., Slovic, P., & Tversky, A. (1982) · Cited by 4,670
Judgment under uncertainty: Causality and attribution
Kahneman, D. J., Slovic, P., & Tversky, A. (1982) · Cited by 4,670
Delusions of success. How optimism undermines executives' decisions.
Lovallo, D. P., & Kahneman, D. J. (2003) · Harvard business review · Cited by 1,124
Underestimating Costs in Public Works Projects:Error or Lie?
Flyvbjerg, B., Holm, M. S., & Buhl, S. (2002) · Journal of the American Planning Association · doi:10.1080/01944360208976273 · Cited by 1,046
Frimpong, Y., Oluwoye, J., & Crawford, L. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00055-8 · Cited by 796
Policy and Planning for Large-Infrastructure Projects: Problems, Causes, Cures
Flyvbjerg, B. (2007) · Environment and Planning B: Planning and Design · doi:10.1068/b32111 · Cited by 521
Cited by
Love, P. E. D., Ahiaga-Dagbui, D. D., & Irani, Z. (2016) · Transportation Research Part A: Policy and Practice · doi:10.1016/j.tra.2016.08.007 · Cited by 138
Self-citation
Metadata
- Authors
- Love, P. E. D., Wang, X., Sing, C.-P., & Tiong, R. L. K.
- Venue
- Journal of Construction Engineering and Management
- Published
- 2013-03
- Volume
- 139
- Issue
- 3
- Pages
- 321-330
- ISSN
- 0733-9364 (ISSN-L)
- 1943-7862
- OpenAlex
- W1985706306
- Cited by
- 169
- References
- 30
- FWCI
- 9.95
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
How to cite
Cite CoChat for the checks on this page, and the paper for its own findings.
- This page
- CoChat. (2026). Citation check: Determining the Probability of Project Cost Overruns. https://app.cochat.ai/papers/10.1061/(asce)co.1943-7862.0000575
- The paper
- Love, P. E. D., Wang, X., Sing, C.-P., & Tiong, R. L. K. (2013). Determining the Probability of Project Cost Overruns. Journal of Construction Engineering and Management. https://doi.org/10.1061/(asce)co.1943-7862.0000575
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.