Determining the Probability of Project Cost Overruns
The DOI matches its Crossref record; 30 of the 30 references it cites were found in a registry or an index.
Abstract
The statistical characteristics of cost overruns experienced from contract award in 276 Australian construction and engineering projects were analyzed. The skewness and kurtosis values of the cost overruns are computed to determine if the empirical distribution of the data follows a normal distribution. The Kolmogorov-Smirnov, Anderson-Darling, and chi-squared nonparametric tests are used to determine the goodness of fit of the selected probability distributions. A three-parameter Frechet probability function is found to describe the behavior of cost overruns and provide the best overall distribution fit. The Frechet distribution is then used to calculate the probability of a cost overrun being experienced. The statistical characteristics of contract size and cost overruns were also analyzed. The Cauchy (<A$1 million), Wakeby (A$1 to 10 million,
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Judgment under Uncertainty: Heuristics and Biases
(1982) · doi:10.1017/cbo9780511809477 · Cited by 8,240
An Introduction to Statistical Modeling of Extreme Values
Coles, S. (2001) · Springer Series in Statistics · doi:10.1007/978-1-4471-3675-0 · Cited by 7,352
Mersenne twister: a 623-dimensionally equidistributed uniform pseudo-random number generator
Matsumoto, M., & Nishimura, T. (1998) · ACM Transactions on Modeling and Computer Simulation · doi:10.1145/272991.272995 · Cited by 5,780
Questionnaire Design, Interviewing and Attitude Measurement
Albuam, G., & Oppenheim, A. N. (1993) · Journal of Marketing Research · doi:10.2307/3172892 · Cited by 4,971
Judgment under uncertainty: List of contributors
Kahneman, D. J., Slovic, P., & Tversky, A. (1982) · Cited by 4,670
Judgment under uncertainty: Causality and attribution
Kahneman, D. J., Slovic, P., & Tversky, A. (1982) · Cited by 4,670
Delusions of success. How optimism undermines executives' decisions.
Lovallo, D. P., & Kahneman, D. J. (2003) · Harvard business review · Cited by 1,124
Underestimating Costs in Public Works Projects:Error or Lie?
Flyvbjerg, B., Holm, M. S., & Buhl, S. (2002) · Journal of the American Planning Association · doi:10.1080/01944360208976273 · Cited by 1,046
Frimpong, Y., Oluwoye, J., & Crawford, L. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00055-8 · Cited by 796
Policy and Planning for Large-Infrastructure Projects: Problems, Causes, Cures
Flyvbjerg, B. (2007) · Environment and Planning B: Planning and Design · doi:10.1068/b32111 · Cited by 521
Influence of Project Type and Procurement Method on Rework Costs in Building Construction Projects
Love, P. E. D. (2002) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2002)128:1(18 · Cited by 463
Self-citationFlyvbjerg, B. (2008) · European Planning Studies · doi:10.1080/09654310701747936 · Cited by 438
Albaum, G., Alreck, P. L., & Settle, R. B. (1985) · Journal of Marketing Research · doi:10.2307/3151595 · Cited by 391
Cost overruns in road construction—what are their sizes and determinants?
Odeck, J. (2004) · Transport Policy · doi:10.1016/s0967-070x(03)00017-9 · Cited by 385
Analysis of cost and schedule performance of international development projects
Ahsan, K., & Gunawan, I. (2010) · International Journal of Project Management · doi:10.1016/j.ijproman.2009.03.005 · Cited by 375
Construction Claims and Disputes: Causes and Cost/Time Overruns
Semple, C., Hartman, F. T., & Jergeas, G. F. (1994) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(1994)120:4(785 · Cited by 374
Cost Overruns and Demand Shortfalls in Urban Rail and Other Infrastructure
Flyvbjerg, B. (2007) · Transportation Planning and Technology · doi:10.1080/03081060701207938 · Cited by 167
Love, P. E. D., Edwards, D. J., & Irani, Z. (2012) · IEEE Transactions on Engineering Management · doi:10.1109/tem.2011.2163628 · Cited by 167
Self-citationPredicting Cost Deviation in Reconstruction Projects: Artificial Neural Networks versus Regression
Attalla, M., & Hegazy, T. (2003) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2003)129:4(405 · Cited by 142
Predictors of Cost‐Overrun Rates
Jahren, C. T., & Ashe, A. M. (1990) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(1990)116:3(548 · Cited by 134
Reasons for Cost and Schedule Increase for Engineering Design Projects
Chang, A. S.-T. (2002) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(2002)18:1(29 · Cited by 133
Procedures for Dealing with Optimism Bias in Transport Planning: Guidance Document
Flyvbjerg, B., Glenting, C., & Rønnest, A. (2004) · VBN Forskningsportal (Aalborg Universitet) · Cited by 130
Cost overruns in public projects
Arditi, D., Akan, G. T., & Gurdamar, S. (1985) · International Journal of Project Management · doi:10.1016/0263-7863(85)90053-5 · Cited by 121
Three-Stage Least-Squares Analysis of Time and Cost Overruns in Construction Contracts
Bhargava, A., Anastasopoulos, P. C., Labi, S., Sinha, K. C., & Mannering, F. (2010) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000225 · Cited by 118
Causal Discovery and Inference of Project Disputes
Love, P. E. D., Davis, P. R., Cheung, S. O., & Irani, Z. (2011) · IEEE Transactions on Engineering Management · doi:10.1109/tem.2010.2048907 · Cited by 101
Self-citationProcurement Systems — A guide to Best Practice in Construction
Woodward, J. F. (2001) · International Journal of Project Management · doi:10.1016/s0263-7863(00)00046-6 · Cited by 95
Divergence or Congruence? A Path Model of Rework for Building and Civil Engineering Projects
Love, P. E. D., Edwards, D. J., Smith, J., & Walker, D. H. T. (2009) · Journal of Performance of Constructed Facilities · doi:10.1061/(asce)cf.1943-5509.0000054 · Cited by 90
Self-citationBudgeting Owner’s Construction Contingency
Günhan, S., & Arditi, D. (2007) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2007)133:7(492 · Cited by 62
Accuracy of Traffic Forecasts and Cost Estimates on Large Transportation Projects
Skamris, M. K., & Flyvbjerg, B. (1996) · Transportation Research Record Journal of the Transportation Research Board · doi:10.3141/1518-12 · Cited by 41
Cost prediction using decision/risk analysis methodologies
Birnie, J., & Yates, A. (1991) · Construction Management and Economics · doi:10.1080/01446199100000015 · Cited by 32
Cited by
Love, P. E. D., Ahiaga-Dagbui, D. D., & Irani, Z. (2016) · Transportation Research Part A: Policy and Practice · doi:10.1016/j.tra.2016.08.007 · Cited by 138
Self-citation
Metadata
- Authors
- Love, P. E. D., Wang, X., Sing, C.-P., & Tiong, R. L. K.
- Venue
- Journal of Construction Engineering and Management
- Published
- 2013-03
- Volume
- 139
- Issue
- 3
- Pages
- 321-330
- ISSN
- 0733-9364 (ISSN-L)
- 1943-7862
- OpenAlex
- W1985706306
- Cited by
- 169
- References
- 30
- FWCI
- 9.95
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.