Cost and Schedule Risk Analysis of Bridge Construction in Pakistan: Establishing Risk Guidelines

Choudhry, Rafiq M., Aslam, Mohammad A., Hinze, Jimmie W., Arain, Faisal M. · 2014 · Journal of Construction Engineering and Management
Cited by 158

The DOI matches its Crossref record; 1 of the 1 references it cites were found in a registry or an index.

Abstract

The construction process is inherently prone to risks. Risk management is an essential and integral part of project management on virtually all construction projects. Risk analysis is one of the core components of risk management that enables professionals to quantify and analyze risks that may pose potential threats to project performance in terms of cost, quality, safety, and time. This research was conducted to identify and analyze risks associated with bridge construction in Pakistan. A questionnaire was conducted to collect data. Risks affecting bridge construction project performance were identified through interviews conducted with engineers and managers involved with various bridge projects. Cost and schedule impacts of project risks were supplemented by conducting a case study using the Monte Carlo simulation. The key findings indicate that financial risks were a major factor that affected cost and schedule objectives. The highest ranked factor identified was unavailability of funds with a relative importance index greater than 85. The results of the Monte Carlo simulation were compared to the actual completion times and costs of activities in the case study. In all cases of this comparison, the actual completion date and costs fell within the predicted distribution of the Monte Carlo simulation, indicating that risk analysis can help project managers to manage cost and schedule risks. Additionally, this study provided risk analysis guidelines, which were unclear. The results of this paper can help engineers, cost control managers, and project managers evaluate particular risks on their projects and avoid delays and cost overruns.

Overview

The claims and statistics of this paper haven’t been checked yet.

Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.

A few free checks a day · papers already verified open instantly · results are public

Integrity signals

Registry

Crossref · 10.1061/(asce)co.1943-7862.0000857

Cites

1 of 1 references verified0 citation errors · 0 not checkable

Statistics

Verification

Claims the paper makes

The claims and statistics of this paper haven’t been checked yet.

Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.

A few free checks a day · papers already verified open instantly · results are public

Self-check

Percentages, sums and reported differences re-computed from the paper’s own numbers.

The self-check needs the paper’s full text.

Citations

Cites

Show all 1 references

Cited by

See all 158

Metadata

Authors
Choudhry, R. M., Aslam, M. A., Hinze, J. W., & Arain, F. M.
Venue
Journal of Construction Engineering and Management
Published
2014-07
Volume
140
Issue
7
ISSN
  • 0733-9364 (ISSN-L)
  • 1943-7862
OpenAlex
W2056863247
Cited by
158
References
1
FWCI
10.27
Type
journal article
Language
en
Open access
closed

About these checks

Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.

Statistics and arithmetic are recomputed, not judged.

Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.

What counts as a claim ›How we measure confidence ›How we check this ›

Are you an author, or do you see a problem with this page? Request a review

How to cite

Cite CoChat for the checks on this page, and the paper for its own findings.

This page
CoChat. (2026). Citation check: Cost and Schedule Risk Analysis of Bridge Construction in Pakistan: Establishing Risk Guidelines. https://app.cochat.ai/papers/10.1061/(asce)co.1943-7862.0000857
The paper
Choudhry, R. M., Aslam, M. A., Hinze, J. W., & Arain, F. M. (2014). Cost and Schedule Risk Analysis of Bridge Construction in Pakistan: Establishing Risk Guidelines. Journal of Construction Engineering and Management. https://doi.org/10.1061/(asce)co.1943-7862.0000857

Data sources

Bibliographic data: Semantic Scholar, OpenAlex, Crossref.

Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).

Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.