Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects

Larsen, Jesper Kranker, Shen, Geoffrey Qiping, Lindhard, Søren Munch, Brunoe, Thomas Ditlev·2016·Journal of Management in Engineering

Abstract

As a result of the loss of financial resources and the need to optimize projects, academics, politicians, and the construction industry have become increasingly aware of the challenges presented by the frequent time and cost overruns and reduced quality of construction projects. The purpose of this study was to analyze the factors that project managers experience as having the greatest effect on time, cost, and quality, and to discover whether the effects of these factors are significantly different from each other. A questionnaire with 26 factors identified from interviews was sent to the full population of publicly employed project managers. Factors were ranked using the relative importance index and tested for significant differences using Friedman’s test. Wilcoxon’s test was used in a post-hoc analysis. From the findings it was determined that the most influential factor for time is unsettled or lack of project funding; for cost, errors or omissions in consultant material; and for quality, errors or omissions in construction work. The main conclusion of this research is that project schedule, budget, and quality level are affected in significantly different ways. Therefore, a project manager cannot handle such critical issues by focusing only on schedule or budget complications; nor can he or she assume that time, cost, and quality are equally affected.

Overview

The claims and statistics of this paper haven’t been checked yet.

Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.

A few free checks a day · papers already verified open instantly · results are public

Integrity signals

Registry

Crossref · 10.1061/(asce)me.1943-5479.0000391

Cites

57 of 57 references verified0 citation errors · 0 not checkable

Statistics

Verification

Claims the paper makes

The claims and statistics of this paper haven’t been checked yet.

Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.

A few free checks a day · papers already verified open instantly · results are public

Self-check

Percentages, sums and reported differences re-computed from the paper’s own numbers.

The self-check needs the paper’s full text.

Citations

Cites

Show all 57 references

Metadata

Authors
Larsen, J. K., Shen, G. Q., Lindhard, S. M., & Brunoe, T. D.
Venue
Journal of Management in Engineering
Published
2016-01
Volume
32
Issue
1
ISSN
  • 0742-597X (ISSN-L)
  • 1943-5479
OpenAlex
W2155576734
Cited by
365
References
57
FWCI
21.61
Type
journal article
Language
en
Open access
closed

About these checks

Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.

Statistics and arithmetic are recomputed, not judged.

Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.

What counts as a claim ›How we measure confidence ›How we check this ›

Are you an author, or do you see a problem with this page? Request a review

How to cite

Cite CoChat for the checks on this page, and the paper for its own findings.

This page
CoChat. (2026). Citation check: Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. https://app.cochat.ai/papers/10.1061/(asce)me.1943-5479.0000391
The paper
Larsen, J. K., Shen, G. Q., Lindhard, S. M., & Brunoe, T. D. (2016). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering. https://doi.org/10.1061/(asce)me.1943-5479.0000391

Data sources

Bibliographic data: Semantic Scholar, OpenAlex, Crossref.

Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).

Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.