Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects
The DOI matches its Crossref record; 57 of the 57 references it cites were found in a registry or an index.
Abstract
As a result of the loss of financial resources and the need to optimize projects, academics, politicians, and the construction industry have become increasingly aware of the challenges presented by the frequent time and cost overruns and reduced quality of construction projects. The purpose of this study was to analyze the factors that project managers experience as having the greatest effect on time, cost, and quality, and to discover whether the effects of these factors are significantly different from each other. A questionnaire with 26 factors identified from interviews was sent to the full population of publicly employed project managers. Factors were ranked using the relative importance index and tested for significant differences using Friedman’s test. Wilcoxon’s test was used in a post-hoc analysis. From the findings it was determined that the most influential factor for time is unsettled or lack of project funding; for cost, errors or omissions in consultant material; and for quality, errors or omissions in construction work. The main conclusion of this research is that project schedule, budget, and quality level are affected in significantly different ways. Therefore, a project manager cannot handle such critical issues by focusing only on schedule or budget complications; nor can he or she assume that time, cost, and quality are equally affected.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Discovering Statistics Using SPSS
Field, A. P., & Miles, J. N. V. (2000) · Medical Entomology and Zoology · Cited by 28,294
Research methods for business: A skill building approach
(1993) · Long Range Planning · doi:10.1016/0024-6301(93)90168-f · Cited by 16,985
Statistical Methods for Psychology.
Gudgeon, A. C., & Howell, D. C. (1994) · The Statistician · doi:10.2307/2348956 · Cited by 8,278
Nonparametric Statistical Methods
(1999) · Technometrics · doi:10.1080/00401706.1999.10485954 · Cited by 6,090
A framework for quality management research and an associated measurement instrument
Flynn, B. B., Schroeder, R. G., & Sakakibara, S. (1994) · Journal of Operations Management · doi:10.1016/s0272-6963(97)90004-8 · Cited by 1,966
Designing and Conducting Survey Research: A Comprehensive Guide
Rea, L. M., & Parker, R. (1992) · Cited by 1,761
Causes of delay in large construction projects
Assaf, S. A., & Al-Hejji, S. (2006) · International Journal of Project Management · doi:10.1016/j.ijproman.2005.11.010 · Cited by 1,705
Empirical research methods in operations management
Flynn, B. B., Sakakibara, S., Schroeder, R. G., Bates, K. A., & Flynn, E. J. (1990) · Journal of Operations Management · doi:10.1016/0272-6963(90)90098-x · Cited by 1,634
Survey research in operations management: a process‐based perspective
Forza, C. (2002) · International Journal of Operations & Production Management · doi:10.1108/01443570210414310 · Cited by 1,610
Causes and effects of delays in Malaysian construction industry
Sambasivan, M., & Soon, Y. W. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2006.11.007 · Cited by 1,422
Handbook of Psychological Testing
Kline, P. (2013) · Routledge eBooks · doi:10.4324/9781315812274 · Cited by 1,194
Underestimating Costs in Public Works Projects:Error or Lie?
Flyvbjerg, B., Holm, M. S., & Buhl, S. (2002) · Journal of the American Planning Association · doi:10.1080/01944360208976273 · Cited by 1,046
Statistical Package for the Social Sciences (SPSS)
(2008) · Encyclopedia of Survey Research Methods · doi:10.4135/9781412963947.n549 · Cited by 961
Presser, S., Rossi, P. H., Wright, J. D., & Anderson, A. B. (1985) · Social Forces · doi:10.2307/2578982 · Cited by 921
Causes of construction delay: traditional contracts
Odeh, A. M., & Battaineh, H. T. (2002) · International Journal of Project Management · doi:10.1016/s0263-7863(00)00037-5 · Cited by 810
Frimpong, Y., Oluwoye, J., & Crawford, L. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00055-8 · Cited by 796
How common and how large are cost overruns in transport infrastructure projects?
Flyvbjerg, B., Skamris holm, M. K., & Buhl, S. L. (2003) · Transport Reviews · doi:10.1080/01441640309904 · Cited by 783
Analysing factors affecting delays in Indian construction projects
Doloi, H., Sawhney, A., Iyer, K. C., & Rentala, S. (2012) · International Journal of Project Management · doi:10.1016/j.ijproman.2011.10.004 · Cited by 745
(1983) · Elsevier eBooks · doi:10.1016/c2013-0-11411-0 · Cited by 710
The Anatomy of Major Projects: A Study of the Reality of Project Management
Morris, P. W. G., & Hough, G. H. (1988) · Medical Entomology and Zoology · Cited by 696
Risk Modeling, Assessment, And Management
Haimes, Y. Y. (1999) · IEEE Transactions on Systems, Man, and Cybernetics, Part C (Applications and Reviews) · doi:10.1109/tsmcc.1999.760577 · Cited by 625
Cost escalation and schedule delays in road construction projects in Zambia
Kaliba, C., Muya, M., & Mumba, K. (2009) · International Journal of Project Management · doi:10.1016/j.ijproman.2008.07.003 · Cited by 596
Significant factors causing delay in the UAE construction industry
Faridi, A. S., & El‐Sayegh, S. M. (2006) · Construction Management and Economics · doi:10.1080/01446190600827033 · Cited by 551
Delays in construction projects: The case of Jordan
Sweis, G., Sweis, R., Abu Hammad, A., & Shboul, A. (2008) · International Journal of Project Management · doi:10.1016/j.ijproman.2007.09.009 · Cited by 534
Factors affecting cost performance: evidence from Indian construction projects
Iyer, K. C., & Jha, K. N. (2005) · International Journal of Project Management · doi:10.1016/j.ijproman.2004.10.003 · Cited by 504
An empirical analysis of the relationship between project planning and project success
Dvir, D., Raz, T., & Shenhar, A. J. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00012-1 · Cited by 498
Applied nonparametric statistical methods
(1989) · Choice Reviews Online · doi:10.5860/choice.26-6314 · Cited by 493
Olawale, Y. A., & Sun, M. (2010) · Construction Management and Economics · doi:10.1080/01446191003674519 · Cited by 478 · cited 3×
“Comparing these results with previous studies done byKaliba et al. (2009); Koushki et al. (2005); Olawale and Sun (2010), time, cost and quality, which were not found related in any previous studies, have been found of particular importance when a factor affects a construction project.”
BackgroundResultInfluentialLarge construction projects in developing countries: a case study from Vietnam
Long, N. D., Ogunlana, S. O., Quang, T., & Lam, K. C. (2004) · International Journal of Project Management · doi:10.1016/j.ijproman.2004.03.004 · Cited by 467
Causes of Delay in Building Construction Projects in Egypt
Abd El-Razek, M. E., Bassioni, H. A., & Mobarak, A. M. (2008) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2008)134:11(831 · Cited by 463
Delays and cost increases in the construction of private residential projects in Kuwait
Koushki, P. A., Al‐Rashid, K., & Kartam, N. (2005) · Construction Management and Economics · doi:10.1080/0144619042000326710 · Cited by 456
Construction Delays and Their Causative Factors in Nigeria
Aibinu, A. A., & Odeyinka, H. A. (2006) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2006)132:7(667 · Cited by 348
Risk Modeling, Assessment, and Management
Liu, S. T. (1999) · Technometrics · doi:10.1080/00401706.1999.10485950 · Cited by 328
Causes of delays in Saudi Arabian public sector construction projects
Al‐Kharashi, A., & Skitmore, M. (2009) · Construction Management and Economics · doi:10.1080/01446190802541457 · Cited by 327
Doloi, H. (2013) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000621 · Cited by 325
Problems causing delays in major construction projects in Thailand
Toor, S.-U.-R., & Ogunlana, S. (2008) · Construction Management and Economics · doi:10.1080/01446190801905406 · Cited by 307
In search of excellence in project management
Kerzner, H. (1987) · Journal of systems management · doi:10.5555/25198.25371 · Cited by 266
CAUSES OF DELAYS IN CONSTRUCTION PROJECTS IN TURKEY
Kazaz, A., Ulubeyli, S., & Tuncbilekli, N. A. (2012) · Journal of Civil Engineering and Management · doi:10.3846/13923730.2012.698913 · Cited by 234
Evaluation of project outcomes
Liu, A. M. M., & Walker, A. (1998) · Construction Management and Economics · doi:10.1080/014461998372493 · Cited by 227
Construction Project Cost Escalation Factors
Shane, J. S., Molenaar, K. R., Anderson, S., & Schexnayder, C. (2009) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(2009)25:4(221 · Cited by 220
Kouzes, J. M., & Posner, B. Z. (1998) · Scholar Commons (Santa Clara University) · Cited by 216
Delays in Building Construction Projects in Ghana
Fugar, F. D., & Agyakwah-Baah, A. B. (1970) · Construction Economics and Building · doi:10.5130/ajceb.v10i1-2.1592 · Cited by 211
Delays in Building Construction Projects in Ghana
Fugar, F. D., & Agyakwah-Baah, A. B. (2010) · Australasian Journal of Construction Economics and Building · doi:10.5130/ajceb.v10i1/2.1592 · Cited by 203
Causes of Delay in the Planning and Design Phases for Construction Projects
Yang, J.-B., & Wei, P.-R. (2010) · Journal of Architectural Engineering · doi:10.1061/(asce)1076-0431(2010)16:2(80 · Cited by 191
Critical Success Factors for Key Project Players and Objectives: Case Study of Singapore
Hwang, B., & Lim, E.-S. J. (2012) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000597 · Cited by 183
Causes of Variation in Construction Project Task Starting Times and Duration
Wambeke, B. W., Hsiang, S. M., & Liu, M. (2011) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000342 · Cited by 168
Why Does Project Management Fail?
Avots, I. (1969) · California Management Review · doi:10.2307/41164208 · Cited by 167
What Is Preproject Planning, Anyway?
Gibson, G. E., Wang, Y. R., Cho, C.-S., & Pappas, M. P. (2005) · Journal of Management in Engineering · doi:10.1061/(asce)0742-597x(2006)22:1(35 · Cited by 136
Applied Nonparametric Statistical Methods.
Banks, D. L., & Sprent, P. (1990) · Journal of the American Statistical Association · doi:10.2307/2289571 · Cited by 125
Cost overruns in public projects
Arditi, D., Akan, G. T., & Gurdamar, S. (1985) · International Journal of Project Management · doi:10.1016/0263-7863(85)90053-5 · Cited by 121
Investigating the relationship between planning reliability and project performance
González, V. A., Alarcón, L. F., & Mundaca, F. (2008) · Production Planning & Control · doi:10.1080/09537280802059023 · Cited by 105
Quality and Safety Management in Construction
Loushine, T. W., Hoonakker, P., Carayon, P., & Smith, M. J. (2006) · Total Quality Management & Business Excellence · doi:10.1080/14783360600750469 · Cited by 99
The effects of design quality on quality performance
Fynes, B., & de Búrca, S. (2004) · International Journal of Production Economics · doi:10.1016/j.ijpe.2004.02.008 · Cited by 93
Risk-management infrastructures
Williams, T. (1993) · International Journal of Project Management · doi:10.1016/0263-7863(93)90003-6 · Cited by 86
Twenty Nonparametric Statistics And Their Large Sample Approximations
Fahoome, G. F. (2002) · Journal of Modern Applied Statistical Methods · doi:10.22237/jmasm/1036110540 · Cited by 51
Front-End Planning Implementation in Singapore: Status, Importance, and Impact
Hwang, B., & Ho, J. W. (2011) · Journal of Construction Engineering and Management · doi:10.1061/(asce)co.1943-7862.0000456 · Cited by 35
Contractor Prebid Planning Principles
Thomas, H. R., & Ellis, R. D. (2007) · Journal of Construction Engineering and Management · doi:10.1061/(asce)0733-9364(2007)133:8(542 · Cited by 27
Cited by
Causes of delays on construction projects: a comprehensive list
Durdyev, S., & Hosseini, M. R. (2019) · International Journal of Managing Projects in Business · doi:10.1108/ijmpb-09-2018-0178 · Cited by 245
Causes of delay in the global construction industry: a meta analytical review
Sanni-Anibire, M. O., Mohamad Zin, R., & Olatunji, S. O. (2022) · International Journal of Construction Management · doi:10.1080/15623599.2020.1716132 · Cited by 173
Metadata
- Authors
- Larsen, J. K., Shen, G. Q., Lindhard, S. M., & Brunoe, T. D.
- Venue
- Journal of Management in Engineering
- Published
- 2016-01
- Volume
- 32
- Issue
- 1
- ISSN
- 0742-597X (ISSN-L)
- 1943-5479
- OpenAlex
- W2155576734
- Cited by
- 365
- References
- 57
- FWCI
- 21.61
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.