Lock-in and its Influence on the Project Performance of Large-Scale Transportation Infrastructure Projects: Investigating the Way in Which Lock-in Can Emerge and Affect Cost Overruns

Open access
Cantarelli, Chantal C, Flyvbjerg, Bent, van Wee, Bert, Molin, Eric J E · 2010 · Environment and Planning B: Planning and Design
Cited by 104

The DOI matches its Crossref record; 6 of the 6 references it cites were found in a registry or an index.

Abstract

Lock-in, the escalating commitment of decision makers to an ineffective course of action, has the potential to explain the large cost overruns in large-scale transportation infrastructure projects. Lock-in can occur both at the decision-making level (before the decision to build) and at the project level (after the decision to build) and can influence the extent of overruns in two ways. The first involves the ‘methodology’ of calculating cost overruns according to the ‘formal decision to build’. Due to lock-in, however, the ‘real decision to build’ is made much earlier in the decision-making process and the costs estimated at that stage are often much lower than those that are estimated at a later stage in the decision-making process, thus increasing cost overruns. The second way that lock-in can affect cost overruns is through ‘practice’. Although decisions about the project (design and implementation) need to be made, lock-in can lead to inefficient decisions that involve higher costs. Sunk costs (in terms of both time and money), the need for justification, escalating commitment, and inflexibility and the closure of alternatives are indicators of lock-in. Two case studies, of the Betuweroute and the High Speed Link-South projects in the Netherlands, demonstrate the presence of lock-in and its influence on the extent of cost overruns at both the decision-making and project levels. This suggests that recognition of lock-in as an explanation for cost overruns contributes significantly to the understanding of the inadequate planning process of projects and allows development of more appropriate means.

Overview

The claims and statistics of this paper haven’t been checked yet.

Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.

A few free checks a day · papers already verified open instantly · results are public

Integrity signals

Registry

Crossref · 10.1068/b36017

Cites

6 of 6 references verified0 citation errors · 0 not checkable

Statistics

Verification

Claims the paper makes

The claims and statistics of this paper haven’t been checked yet.

Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.

A few free checks a day · papers already verified open instantly · results are public

Self-check

Percentages, sums and reported differences re-computed from the paper’s own numbers.

The self-check needs the paper’s full text.

Citations

Cites

Show all 6 references

Cited by

See all 104

Metadata

Authors
Cantarelli, C. C., Flyvbjerg, B., van Wee, B., & Molin, E. J. E.
Venue
Environment and Planning B: Planning and Design
Published
2010-01-01
Volume
37
Issue
5
Pages
792-807
ISSN
  • 0265-8135 (ISSN-L)
  • 1472-3417
OpenAlex
W2149475851
Cited by
104
References
6
FWCI
3.92
Type
journal article
Language
en
Open access
green

About these checks

Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.

Statistics and arithmetic are recomputed, not judged.

Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.

What counts as a claim ›How we measure confidence ›How we check this ›

Are you an author, or do you see a problem with this page? Request a review

How to cite

Cite CoChat for the checks on this page, and the paper for its own findings.

This page
CoChat. (2026). Citation check: Lock-in and its Influence on the Project Performance of Large-Scale Transportation Infrastructure Projects: Investigating the Way in Which Lock-in Can Emerge and Affect Cost Overruns. https://app.cochat.ai/papers/10.1068/b36017
The paper
Cantarelli, C. C., Flyvbjerg, B., van Wee, B., & Molin, E. J. E. (2010). Lock-in and its Influence on the Project Performance of Large-Scale Transportation Infrastructure Projects: Investigating the Way in Which Lock-in Can Emerge and Affect Cost Overruns. Environment and Planning B: Planning and Design. https://doi.org/10.1068/b36017

Data sources

Bibliographic data: Semantic Scholar, OpenAlex, Crossref.

Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).

Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.