A shuffled frog-leaping algorithm for flexible job shop scheduling with the consideration of energy consumption
The DOI matches its Crossref record; 24 of the 24 references it cites were found in a registry or an index.
Abstract
Flexible job shop scheduling problem (FJSP) has been extensively investigated and objectives are often related to time. Energy-related objective should be considered fully in FJSP with the advent of green manufacturing. In this study, FJSP with the minimisation of workload balance and total energy consumption is considered and the conflicting between two objectives is analysed. A shuffled frog-leaping algorithm (SFLA) is proposed based on a three-string coding approach. Population and a non-dominated set are used to construct memeplexes according to tournament selection and the search process of each memeplex is done on its non-dominated member. Extensive experiments are conducted to test the search performance of SFLA and computational results show the conflicting between two objectives of FJSP and the promising advantages of SFLA on the considered FJSP.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
A fast and elitist multiobjective genetic algorithm: NSGA-II
Deb, K., Pratap, A., Agarwal, S., & Meyarivan, T. (2002) · IEEE Transactions on Evolutionary Computation · doi:10.1109/4235.996017 · Cited by 50,053 · cited 2×
“In this study, non-dominated sorting genetic algorithm-II (NSGA-II, Deb et al. 2002) and VNS are chosen.”
MethodMathematical Problems in Engineering
(2022) · Mathematical Problems in Engineering · doi:10.1155/2629 · Cited by 4,033
International Journal of Production Research
HAWKINS, T. H. (1962) · Nature · doi:10.1038/1931144a0 · Cited by 2,111
Routing and scheduling in a flexible job shop by tabu search
Brandimarte, P. (1993) · Annals of Operations Research · doi:10.1007/bf02023073 · Cited by 1,322 · cited 1×
“All experiments are implemented using Microsoft Visual C++ 6.0 and run on 4.0G RAM 1.70 GHz CPU PC. 5.1 Test instances, performance metrics and the chosen algorithms We use 41 instances MK1-13 (Brandimarte 1993), DP1-18 (Dauzère-Pérès and Paulli 1997) and LA21-30 (Hurink et al. 1994).”
MethodInfluentialShuffled frog-leaping algorithm: a memetic meta-heuristic for discrete optimization
Eusuff, M., Lansey, K., & Pasha, F. (2006) · Engineering Optimization · doi:10.1080/03052150500384759 · Cited by 1,185 · cited 2×
“SFLA is originally developed by Eusuff, Lansey, and Pasha (2006) and has been applied to production scheduling problems (Rahimi-Vahed et al. 2009; Pan et al. 2011; Li et al. 2012; Fang and Wang 2013; Lei and Guo 2015b; Lei and Guo (forthcoming); however, SFLA is seldom applied to solve FJSP with…”
MethodIshibuchi, H., Yoshida, T., & Murata, T. (2003) · IEEE Transactions on Evolutionary Computation · doi:10.1109/tevc.2003.810752 · Cited by 773
Tabu search for the job-shop scheduling problem with multi-purpose machines
Hurink, J. L., Jurisch, B., & Thole, M. (1994) · OR Spectrum · doi:10.1007/bf01719451 · Cited by 599 · cited 4×
“We use 41 instances MK1-13 (Brandimarte 1993), DP1-18 (Dauzère-Pérès and Paulli 1997) and LA21-30 (Hurink et al. 1994).”
BackgroundMethodInfluentialOperational methods for minimization of energy consumption of manufacturing equipment
Mouzon, G., Yildirim, M. B., & Twomey, J. (2007) · International Journal of Production Research · doi:10.1080/00207540701450013 · Cited by 597
A new approach to scheduling in manufacturing for power consumption and carbon footprint reduction
Fang, K., Uhan, N., Zhao, F., & Sutherland, J. W. (2011) · Journal of Manufacturing Systems · doi:10.1016/j.jmsy.2011.08.004 · Cited by 552 · cited 9×
“Fang et al. (2011) presented a mathematical programming model for FSP with peak power load and carbon footprint and demonstrated the model using a simple case study.”
BackgroundMethodInfluentialOptimizing the production scheduling of a single machine to minimize total energy consumption costs
Shrouf, F., Ordieres-Meré, J. B., Sánchez, Á. G., & Ortega-Mier, M. (2013) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2013.12.024 · Cited by 479 · cited 1×
“Shrouf et al. (2014) adopted the same framework by Mouzon, Yildirim, and Twomey (2007) to minimise total energy consumption cost in single machine.”
MethodEnergy-efficient scheduling in manufacturing companies: A review and research framework
Gahm, C., Denz, F., Dirr, M., & Tuma, A. (2016) · European Journal of Operational Research · doi:10.1016/j.ejor.2015.07.017 · Cited by 474 · cited 1×
“The reductions of energy consumption or carbon footprint have attracted some attention in recent years (Gahm et al. 2016).”
BackgroundDai, M., Tang, D., Giret, A., Salido, M. A., & Li, W. D. (2013) · Robotics and Computer-Integrated Manufacturing · doi:10.1016/j.rcim.2013.04.001 · Cited by 466 · cited 1×
“Dai et al. (2013) reported a genetic-simulated annealing algorithm to make a significant trade-off between makespan and total energy consumption in flexible flow shop scheduling.”
MethodHybrid flow shop scheduling considering machine electricity consumption cost
Luo, H., Du, B., Huang, G. Q., Chen, H., & Li, X. (2013) · International Journal of Production Economics · doi:10.1016/j.ijpe.2013.01.028 · Cited by 381 · cited 1×
“Luo et al. (2013) provided an ant colony optimisation for hybrid flow shop scheduling with the consideration on electricity consumption cost.”
BackgroundZhang, R., & Chiong, R. (2016) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2015.09.097 · Cited by 344 · cited 1×
“Zhang and Chiong (2016) developed a multi-objective GA to minimise total weighted tardiness and total energy consumption of JSP. Flexible job shop scheduling problem (FJSP) is an extension of JSP by allowing an operation to be processed on more than one machine.”
BackgroundA framework to minimise total energy consumption and total tardiness on a single machine
Mouzon, G., & Yildirim, M. B. (2008) · International Journal of Sustainable Engineering · doi:10.1080/19397030802257236 · Cited by 315 · cited 1×
“This framework has been extended for single machine scheduling in their subsequent work (Mouzon and Yildirim 2008).”
BackgroundGreen scheduling of a two-machine flowshop: Trade-off between makespan and energy consumption
Mansouri, S. A., Aktas, E., & Besikci, U. (2016) · European Journal of Operational Research · doi:10.1016/j.ejor.2015.08.064 · Cited by 289 · cited 1×
“Mansouri, Aktas, and Besikci (2016) provided a mixed integer linear multiobjective optimization model, lower bound and a heuristic for two-machine flow shop scheduling with makespan and total energy consumption.”
BackgroundLi, J.-Q., Pan, Q.-K., & Tasgetiren, M. F. (2014) · Applied Mathematical Modelling · doi:10.1016/j.apm.2013.07.038 · Cited by 273
Multiobjective Flexible Job Shop Scheduling Using Memetic Algorithms
Yuan, Y., & Xu, H. (2015) · IEEE Transactions on Automation Science and Engineering · doi:10.1109/tase.2013.2274517 · Cited by 270 · cited 1×
“It has attracted much attention in the past decade and a number of results have been obtained (Li et al. 2011, 2012; Wang, Wang, and Liu 2013, 2014; Chiang and Lin 2013; Yuan and Xu 2015; Ahmadi et al. 2016).”
Carbon-efficient scheduling of flow shops by multi-objective optimization
Ding, J.-Y., Song, S., & Wu, C. (2016) · European Journal of Operational Research · doi:10.1016/j.ejor.2015.05.019 · Cited by 264 · cited 2×
“With respect to relation between pijkl and Ekl, there is an assumption (Ding, Song, and Wu 2016).”
BackgroundTang, D., Dai, M., Salido, M. A., & Giret, A. (2016) · Computers in Industry · doi:10.1016/j.compind.2015.10.001 · Cited by 262 · cited 1×
“Tang et al. (2015) proposed an improved particle swarm optimization for energy-efficient dynamic scheduling in flexible flow shop.”
BackgroundAhmadi, E., Zandieh, M., Farrokh, M., & Emami, S. M. (2016) · Computers & Operations Research · doi:10.1016/j.cor.2016.03.009 · Cited by 225 · cited 2×
“It has attracted much attention in the past decade and a number of results have been obtained (Li et al. 2011, 2012; Wang, Wang, and Liu 2013, 2014; Chiang and Lin 2013; Yuan and Xu 2015; Ahmadi et al. 2016).”
MethodMulti-objective genetic algorithm for energy-efficient job shop scheduling
May, G., Stahl, B., Taisch, M., & Prabhu, V. (2015) · International Journal of Production Research · doi:10.1080/00207543.2015.1005248 · Cited by 222 · cited 1×
“May et al. (2015) proposed a multi-objective GA for energy-efficient job shop scheduling.”
BackgroundYildirim, M. B., & Mouzon, G. (2012) · IEEE Transactions on Engineering Management · doi:10.1109/tem.2011.2171055 · Cited by 172 · cited 1×
“They proposed a multiobjective genetic algorithm (GA) with hybridisation with dominance rules and a heuristic to minimise energy consumption and total completion time on a single machine (Yildirim and Mouzon 2012).”
BackgroundAn effective shuffled frog-leaping algorithm for resource-constrained project scheduling problem
Chen, F., & Wang, L. (2011) · Computers & Operations Research · doi:10.1016/j.cor.2011.07.010 · Cited by 149 · cited 1×
“…Eusuff, Lansey, and Pasha (2006) and has been applied to production scheduling problems (Rahimi-Vahed et al. 2009; Pan et al. 2011; Li et al. 2012; Fang and Wang 2013; Lei and Guo 2015b; Lei and Guo (forthcoming); however, SFLA is seldom applied to solve FJSP with multiple objectives and FJSP…”
Background
Cited by
A review of energy-efficient scheduling in intelligent production systems
Gao, K., Huang, Y., Sadollah, A., & Wang, L. (2020) · Complex & Intelligent Systems · doi:10.1007/s40747-019-00122-6 · Cited by 274
Metadata
- Authors
- Lei, D., Zheng, Y., & Guo, X.
- Venue
- International Journal of Production Research
- Publisher
- Informa UK Limited
- Published
- 2016-11-25
- Volume
- 55
- Issue
- 11
- Pages
- 3126-3140
- ISSN
- 0020-7543 (ISSN-L)
- 1366-588X
- OpenAlex
- W2549540100
- Cited by
- 174
- References
- 24
- FWCI
- 26.30
- Type
- journal article
- Language
- en
- Open access
- closed
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.