Production planning and scheduling in multi-factory production networks: a systematic literature review
Open accessThe DOI matches its Crossref record; 52 of the 52 references it cites were found in a registry or an index.
Abstract
Multi-factory production planning and scheduling problems have been increasingly studied by scholars recently due to market uncertainty, technological trends like Industry 4.0 and increasing collaboration. Geographically dispersed factories may provide cost-saving potential and increase efficiency while also being subjected to varying capabilities and restrictions such as capacity constraints and labour costs. Traditional approaches in production planning and scheduling focus on the allocation of demand to a single factory and obtain sequences of operations on machines in this factory. In the multi-factory or distributed setting, an additional task includes assigning orders to potential factories beforehand. Starting with the first case studies in the late 1990s, research has increasingly been devoted to this research field and has considered numerous variations of the problem. We review 128 articles on multi-factory production planning and scheduling problems in this contribution and classify the literature according to shop configuration, network structure, objectives, and solution methods. Bibliometric analysis and network analysis are utilised to generate new findings. Research opportunities identified include integration with other planning stages, an investigation of key real-life objectives such as due date compliance and examining dynamic characteristics in the context of Industry 4.0. Besides, empirical studies are necessary to gain new practical insights.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
(1979) · Cited by 43,841
Tranfield, D., Denyer, D., & Smart, P. (2003) · British Journal of Management · doi:10.1111/1467-8551.00375 · Cited by 15,386
Scheduling: Theory, Algorithms, and Systems
(1996) · IIE Transactions · doi:10.1080/15458830.1996.11770714 · Cited by 6,210
Optimization and Approximation in Deterministic Sequencing and Scheduling: a Survey
Graham, R. L., Lawler, E. L., Lenstra, J. K., & Kan, A. H. G. R. (1979) · Annals of Discrete Mathematics · doi:10.1016/s0167-5060(08)70356-x · Cited by 5,854 · cited 2×
“Following the three-field notation α/β/γ of Graham et al. (1979), the third field (γ ) represents the performancemeasure or objective.”
BackgroundMethodMetaheuristics: From Design to Implementation
Talbi, E. (2009) · Wiley eBooks · doi:10.1002/9780470496916 · Cited by 2,380
International Journal of Production Research
HAWKINS, T. H. (1962) · Nature · doi:10.1038/1931144a0 · Cited by 2,111
Ivanov, D., Dolgui, A., & Sokolov, B. (2019) · International Journal of Production Research · doi:10.1080/00207543.2018.1488086 · Cited by 2,055
Conducting research literature reviews: from the Internet to paper
(2005) · Choice Reviews Online · doi:10.5860/choice.42-6198 · Cited by 1,854
A survey of scheduling problems with setup times or costs
Allahverdi, A., Ng, C. T., Cheng, T. C. E., & Kovalyov, M. Y. (2006) · European Journal of Operational Research · doi:10.1016/j.ejor.2006.06.060 · Cited by 1,527 · cited 7×
“Different from the other scheduling problems, in an open shop (OS) each job has to be processed once on each of the m machines, passing them in any order (Allahverdi et al. 2008).”
BackgroundInfluentialWhat a difference a word makes: Understanding threats to performance in a VUCA world
Bennett, N., & Lemoine, G. J. (2014) · Business Horizons · doi:10.1016/j.bushor.2014.01.001 · Cited by 1,371
Supply chain resilience: definition, review and theoretical foundations for further study
Tukamuhabwa, B. R., Stevenson, M., Busby, J., & Zorzini, M. (2015) · International Journal of Production Research · doi:10.1080/00207543.2015.1037934 · Cited by 1,365 · cited 2×
“Gao, Chen, and Deng (2013) use a TS recording the exchange of job sub-sequences for the DPFSP with Cmax objective.”
BackgroundMethodA survey of dynamic scheduling in manufacturing systems
Ouelhadj, D., & Petrović, S. (2008) · Journal of Scheduling · doi:10.1007/s10951-008-0090-8 · Cited by 1,031
Organizing knowledge syntheses: A taxonomy of literature reviews
Cooper, H. M. (1988) · Knowledge in Society · doi:10.1007/bf03177550 · Cited by 1,014
A New Paradigm for Systematic Literature Reviews in Supply Chain Management
Durach, C. F., Kembro, J., & Wieland, A. (2017) · Journal of Supply Chain Management · doi:10.1111/jscm.12145 · Cited by 924 · cited 2×
“The systematic procedure is vital to minimise bias and ensure rigour and relevance of findings and research opportunities identified (Tranfield, Denyer, and Smart 2003; Fink 2013; Durach, Kembro, and Wieland 2017).”
Some efficient heuristic methods for the flow shop sequencing problem
Taillard, É. D. (1990) · European Journal of Operational Research · doi:10.1016/0377-2217(90)90090-x · Cited by 869 · cited 1×
“For the DPFSP, Naderi and Ruiz (2010) tested six heuristics from the PFSP literature and concluded that NEH by Nawaz, Enscore, and Ham (1983), using the Taillard (1990) accelerations, performed best.”
MethodConducting systematic literature review in operations management
Thomé, A. M. T., Scavarda, L. F., & Scavarda, A. J. (2016) · Production Planning & Control · doi:10.1080/09537287.2015.1129464 · Cited by 812 · cited 7×
“Full-text review is perceived as a crucial step in achieving a meaningful sample for the review (Tranfield, Denyer, and Smart 2003; Vom Brocke et al. 2009; Thomé, Scavarda, and Scavarda 2016).”
BackgroundMethodInfluentialBabich, V., & Hilary, G. (2020) · Manufacturing & Service Operations Management · doi:10.1287/msom.2018.0752 · Cited by 782
Integrated Production and Outbound Distribution Scheduling: Review and Extensions
Chen, Z. (2009) · Operations Research · doi:10.1287/opre.1080.0688 · Cited by 610 · cited 2×
“The term was considered in the search, but we excluded articles that primarily focus on integrating other related problems, such as integrated planning of lot sizing and scheduling or scheduling and distribution (refer to Chen 2010 or Copil et al. 2017).”
BackgroundScope for industrial applications of production scheduling models and solution methods
Harjunkoski, I., Maravelias, C. T., Bongers, P. M. M., Castro, P. M., Engell, S., Grossmann, I. E., Hooker, J., Méndez, C. A., Sand, G., & Wassick, J. M. (2013) · Computers & Chemical Engineering · doi:10.1016/j.compchemeng.2013.12.001 · Cited by 585 · cited 1×
“Integrated production and distribution scheduling is also a vital area for further studies, especially when more than one delivery mode is available (Chen 2010; Harjunkoski et al. 2014; Fu, Aloulou, and Triki 2017).”
BackgroundBlockchain-oriented dynamic modelling of smart contract design and execution in the supply chain
Dolgui, A., Ivanov, D., Potryasaev, S., Sokolov, B., Ivanova, M., & Werner, F. (2020) · International Journal of Production Research · doi:10.1080/00207543.2019.1627439 · Cited by 543 · cited 1×
“Others presented hybrids of thesemodels, utilising new technologies like blockchain for smart manufacturing (Leng et al., “ManuChain,” 2019; Lohmer 2019; Dolgui et al. 2020).”
MethodThe job shop scheduling problem: Conventional and new solution techniques
Błażewicz, J., Domschke, W., & Pesch, E. (1996) · European Journal of Operational Research · doi:10.1016/0377-2217(95)00362-2 · Cited by 536 · cited 1×
“Production planning and scheduling problems have been analysed and solved extensively in the past, but to a large extent only considered the traditional single factory configuration (Blazewicz, Domschke, and Pesch 1996; Allahverdi et al. 2008; Allahverdi 2015).”
BackgroundInternational Journal of Computer Integrated Manufacturing
(2003) · International Journal of Computer Integrated Manufacturing · doi:10.1080/0951192031000075962 · Cited by 491
Industry 4.0: Smart Scheduling
Rossit, D. A., Tohmé, F., & Frutos, M. (2018) · International Journal of Production Research · doi:10.1080/00207543.2018.1504248 · Cited by 385 · cited 1×
“Similar to the literature on traditional production scheduling, minimising the makespan is the most common objective used for distributed problems (Allahverdi 2015; Rossit, Tohmé, and Frutos 2018).”
BackgroundAn Improved Genetic Algorithm for the Distributed and Flexible Job-shop Scheduling problem
De Giovanni, L., & Pezzella, F. (2010) · European Journal of Operational Research · doi:10.1016/j.ejor.2009.01.008 · Cited by 345 · cited 4×
“Similar to flowshops, in a distributed flexible jobshop (DFJSP) more than one machine exists in at least one stage (Chan, Chung, and Chan 2005; De Giovanni and Pezzella 2010).”
BackgroundMethodInfluentialLeng, J., Yan, D., Liu, Q., Xu, K., Zhao, J. L., Shi, R., Wei, L., Zhang, D., & Chen, X. (2020) · IEEE Transactions on Systems, Man, and Cybernetics: Systems · doi:10.1109/tsmc.2019.2930418 · Cited by 246
Makerchain: A blockchain with chemical signature for self-organizing process in social manufacturing
Leng, J., Jiang, P., Xu, K., Liu, Q., Zhao, J. L., Bian, Y., & Shi, R. (2019) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2019.06.265 · Cited by 241
Production scheduling in the context of Industry 4.0: review and trends
Parente, M., Figueira, G., Amorim, P., & Marques, A. (2020) · International Journal of Production Research · doi:10.1080/00207543.2020.1718794 · Cited by 232
Timing Channel in IaaS: How to Identify and Investigate
Fu, X., Yang, R., Du, X., Luo, B., & Guizani, M. (2019) · IEEE Access · doi:10.1109/access.2018.2876146 · Cited by 200
The Distributed Assembly Permutation Flowshop Scheduling Problem
Hatami, S., Ruiz, R., & Andrés-Romano, C. (2013) · International Journal of Production Research · doi:10.1080/00207543.2013.807955 · Cited by 197
Note: A local-search heuristic for large set-covering problems
Jacobs, L. W., & Brusco, M. J. (1995) · Naval Research Logistics (NRL) · doi:10.1002/1520-6750(199510)42:7<1129::aid-nav3220420711>3.0.co;2-m · Cited by 174 · cited 1×
“IGAs typically consist of initialisation, construction and destruction procedures with an acceptance criterion and are simple to set up and apply (Jacobs and Brusco 1995).”
The distributed permutation flow shop to minimise the total flowtime
Fernandez-Viagas, V., Perez-Gonzalez, P., & Framinan, J. M. (2018) · Computers & Industrial Engineering · doi:10.1016/j.cie.2018.03.014 · Cited by 169 · cited 1×
“Lately, several authors utilised constructive heuristics for DPFSP and DAPFSP configurations (Fernandez-Viagas, Perez-Gonzalez, and Framinan 2018; Zhang, Xing, andCao 2018b; Pan et al., “Effective Heuristics,” 2019; Pan et al., “Effective Constructive Heuristics,” 2019).”
BackgroundMoon, C., Kim, J., & Hur, S. (2002) · Computers & Industrial Engineering · doi:10.1016/s0360-8352(02)00078-5 · Cited by 169
A survey of multi-factory scheduling
Behnamian, J., & Ghomi, S. M. T. F. (2014) · Journal of Intelligent Manufacturing · doi:10.1007/s10845-014-0890-y · Cited by 164
Wasp-like Agents for Distributed Factory Coordination
Cicirello, V. A., & Smith, S. F. (2004) · Autonomous Agents and Multi-Agent Systems · doi:10.1023/b:agnt.0000018807.12771.60 · Cited by 153 · cited 4×
“Among the combinations are a hybrid MAS and DES for SM (Nigro et al. 2003), a wasplike MAS approach for PM (Cicirello and Smith 2004), a distributedMAS for multi-tier andmulti-site production (Chen, Huang, and Lai 2009), and agent-based models (Karageorgos et al. 2003; Lau et al. 2006).”
BackgroundMethodInfluentialAgent-based optimisation of logistics and production planning
Karageorgos, A., Mehandjiev, N., Weichhart, G., & Hämmerle, A. (2003) · Engineering Applications of Artificial Intelligence · doi:10.1016/s0952-1976(03)00076-9 · Cited by 145 · cited 10×
“…for further studies considering objective functions include objectives such as earliness/tardiness to meet quoted due dates which are vital to ensure ontime delivery to meet customer demands and fulfil justin-time principles in supply chains (Guo et al. 2015; Karimi and Davoudpour 2015).”
BackgroundMethodInfluentialEvolutionary algorithm for advanced process planning and scheduling in a multi-plant
Moon, C., & Seo, Y. (2005) · Computers & Industrial Engineering · doi:10.1016/j.cie.2005.01.016 · Cited by 108
Minimizing makespan for solving the distributed no-wait flowshop scheduling problem
Lin, S.-W., & Ying, K. (2016) · Computers & Industrial Engineering · doi:10.1016/j.cie.2016.07.027 · Cited by 102
Distributed scheduling: a review of concepts and applications
Toptal, A., & Sabuncuoğlu, İ. (2009) · International Journal of Production Research · doi:10.1080/00207540903121065 · Cited by 88
Aissani, N., Bekrar, A., Trentesaux, D., & Beldjilali, B. (2011) · Journal of Intelligent Manufacturing · doi:10.1007/s10845-011-0580-y · Cited by 74 · cited 3×
“Aissani et al. (2012) used reinforcement learning in anMAS for flexible JS to reach real-time decisions. Lim, Tan, and Leung (2013) applied a currencybidding mechanism combined with a GA.”
BackgroundMethodTime-Variant Graph Classification
Wang, H., Wu, J. X., Xingquan Zhu, A., Chen, Y., & Chengqi Zhang, B. (2018) · IEEE Transactions on Systems Man and Cybernetics Systems · doi:10.1109/tsmc.2018.2830792 · Cited by 72
Modeling and Pareto optimization of multi-objective order scheduling problems in production planning
Guo, Z., Wong, W. K., Li, Z., & Ren, P. (2013) · Computers & Industrial Engineering · doi:10.1016/j.cie.2013.01.006 · Cited by 70
Minimizing the total completion time in a distributed two stage assembly system with setup times
Xiong, F., Xing, K., Wang, F., Lei, H., & Han, L. (2014) · Computers & Operations Research · doi:10.1016/j.cor.2014.02.005 · Cited by 68
Leng, J.-W., & Jiang, P. (2017) · Journal of Intelligent Manufacturing · doi:10.1007/s10845-017-1301-y · Cited by 64
Modelling of risk transmission and control strategy in the transnational supply chain
Lei, Z., Lim, M. K., Cui, L., & Wang, Y. (2019) · International Journal of Production Research · doi:10.1080/00207543.2019.1698782 · Cited by 60 · cited 6×
“ICAs originate from evolution processes in colonisation (Behnamian and Fatemi Ghomi 2012; Karimi and Davoudpour 2017b; Lei et al. 2019; Marandi and Fatemi Ghomi 2019).”
BackgroundMethodInfluentialArgoneto, P., & Renna, P. (2014) · Enterprise Information Systems · doi:10.1080/17517575.2014.928950 · Cited by 58
Distribution of manufacturing strategy decision-making in multi-plant networks
Olhager, J., & Feldmann, A. (2017) · International Journal of Production Research · doi:10.1080/00207543.2017.1401749 · Cited by 52 · cited 3×
“Distribution of production capacity among several factories, which are, in many cases, geographically distributed, is increasingly used (Olhager and Feldmann 2018).”
BackgroundInfluentialChen, W., Huang, C., & Lai, Y.-C. (2008) · Computers & Industrial Engineering · doi:10.1016/j.cie.2008.08.012 · Cited by 46 · cited 3×
“…Lei et al. (2019) PM √ st, det √ Cmax ICA DPMSP Azevedo and Sousa (2000) FS √ st, det √ ∑ Tj+∑Ej, Cost √ SA Gnoni et al. (2003) FS √ dyn, stoch √ Cost √ √ Miller and De Matta (2003) FS √ dyn, det √ Cost √ Lin and Chen (2007) FS √ dyn, det √ Cost √ Chen, Huang, and Lai (2009) FS √…”
BackgroundMethodWang, P.-S., Yang, T., & Yu, L.-C. (2018) · Computers & Industrial Engineering · doi:10.1016/j.cie.2018.03.043 · Cited by 35
Optimisation approaches for distributed scheduling problems
Chan, H. K., & Chung, S. H. (2013) · International Journal of Production Research · doi:10.1080/00207543.2012.755345 · Cited by 26 · cited 2×
“Large companies have several production sites to which orders must be assigned in order to efficiently fulfil customer orders (Chan and Chung 2013; Ruiz, Pan, and Naderi 2019).”
BackgroundGuo, Z., Yang, C., Wang, W., & Yang, J. (2015) · Computers & Industrial Engineering · doi:10.1016/j.cie.2015.01.023 · Cited by 23
Graph colouring-based algorithm to parallel jobs scheduling on parallel factories
Behnamian, J. (2015) · International Journal of Computer Integrated Manufacturing · doi:10.1080/0951192x.2015.1099074 · Cited by 16 · cited 3×
“In the context of distributed manufacturing, algorithms were presented by Chan, Kumar, and Mishra (2008) and Behnamian (2016, 2017b) as well as Ji et al. (2016) and Zhang, Xing, and Cao (2018a) for hybridised variants.”
MethodAdvanced scheduling with genetic algorithms in supply networks
Ławrynowicz, A. (2011) · Journal of Manufacturing Technology Management · doi:10.1108/17410381111149620 · Cited by 16
Cited by
Deep reinforcement learning in production systems: a systematic literature review
Panzer, M., & Bender, B. (2022) · International Journal of Production Research · doi:10.1080/00207543.2021.1973138 · Cited by 282
Metadata
- Authors
- Lohmer, J., & Lasch, R.
- Venue
- International Journal of Production Research
- Publisher
- Informa UK Limited
- Published
- 2020-07-29
- Volume
- 59
- Issue
- 7
- Pages
- 2028-2054
- ISSN
- 0020-7543 (ISSN-L)
- 1366-588X
- OpenAlex
- W3046048052
- Cited by
- 178
- References
- 52
- FWCI
- 1.35
- Type
- journal article
- Language
- en
- Open access
- green
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.