Causes of cost overruns in transport infrastructure projects in Asia: Their significance and relationship with project size
The DOI matches its Crossref record, with a small difference in title or year; 54 of the 56 references it cites were found in a registry or an index.
Abstract
Purpose: One of the world's largest construction markets is in Asia where construction activity is boosted by investment on transport infrastructure. This paper aims to identify and analyse causes of cost overruns in transport infrastructure projects in Asia and assess their importance and statistical relationship with project size. Design/methodology/approach: The paper pursues the following objectives. First, it identifies factors contributing to cost overruns. Second, using case data and regression analysis, it establishes the statistical relationship between project size and cost overruns. Third, it analyses questionnaire data to rank causes of cost overruns according to their frequency, severity and significance. Last, the paper identifies contract types mostly associated with cost escalation. Findings: The findings confirm a moderate correlation between cost overruns and one indicator of project size. Awarding contracts to the lowest bidder is identified as the most significant cause of cost overruns. Lump‐sum contracts were found to have the greatest influence on the occurrence of cost overruns. Research limitations/implications: Stratified sampling would allow the evaluation of how cost overruns are perceived by different professional groups. Further research can focus on measures for the prevention of cost overruns. Originality/value: The causes of cost overruns have been at the focal point of research however, most studies consider cost overruns in specific Asian countries. Moreover, transport infrastructure projects have received little attention or been underrepresented in datasets comprising general construction projects. The paper seeks to fill this gap by carrying out in‐depth investigation of cost overruns in transport infrastructure in the broader context of Asia.
Overview
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
Claims other papers make about this one
Each is checked against this paper’s own text: does it say what the citing paper says it does?
In the citing paper
“Park and Papadopoulou [32] conducted a study on 35 transport infrastructure-related projects which were completed between 1983 and 2010 in Asian developing and emerging countries, including Bangladesh, Hong Kong, India, Malaysia, Myanmar, Pakistan, Singapore, South Korea, Sri Lanka, Taiwan, Thailand, and Vietnam.”
From Blockchain Technology: Potential Applications for Public Sector E-Procurement and Project Management (2022) · cites this paper as [32]
In the citing paper
“and their study found that the most significant reason for the cost-overrun in Asia is the common practice of awarding contracts to the lowest bidder for infrastructure-related projects.”
From Blockchain Technology: Potential Applications for Public Sector E-Procurement and Project Management (2022) · cites this paper as [32]
In the citing paper
“They identified 27 project implementation problems”
From Blockchain Technology: Potential Applications for Public Sector E-Procurement and Project Management (2022) · cites this paper as [32]
In the citing paper
“It has been found that awarding the contract to the lowest bidder is one of the main causes for delaying projects [32,36,54].”
From Blockchain Technology: Potential Applications for Public Sector E-Procurement and Project Management (2022) · cites this paper as [32]
In the citing paper
“Slow inspection is one of the managerial problems and one of the causes of project delays [32,36].”
From Blockchain Technology: Potential Applications for Public Sector E-Procurement and Project Management (2022) · cites this paper as [32]
2 more claims about this paper
Create a free account to see every claim other papers make about this one.
Citations
Cites
Bell, E., Bryman, A., & Harley, B. (2022) · Oxford University Press eBooks · doi:10.1093/hebz/9780198869443.001.0001 · Cited by 10,965
Case Selection Techniques in Case Study Research: A Menu of Qualitative and Quantitative Options
Seawright, J., & Gerring, J. (2008) · Political Research Quarterly · doi:10.1177/1065912907313077 · Cited by 3,827
Megaprojects and Risk: An Anatomy of Ambition
Flyvbjerg, B., Bruzelius, N., & Rothengatter, W. (2003) · Cambridge University Press eBooks · doi:10.1017/cbo9781107050891 · Cited by 2,415
Causes of delay in large construction projects
Assaf, S. A., & Al-Hejji, S. (2006) · International Journal of Project Management · doi:10.1016/j.ijproman.2005.11.010 · Cited by 1,705
Causes and effects of delays in Malaysian construction industry
Sambasivan, M., & Soon, Y. W. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2006.11.007 · Cited by 1,422
Understanding the key risks in construction projects in China
Zou, P. X. W., Zhang, G., & Wang, J. (2007) · International Journal of Project Management · doi:10.1016/j.ijproman.2007.03.001 · Cited by 859
A comparative study of causes of time overruns in Hong Kong construction projects
Chan, D. W., & Kumaraswamy, M. M. (1997) · International Journal of Project Management · doi:10.1016/s0263-7863(96)00039-7 · Cited by 831
Frimpong, Y., Oluwoye, J., & Crawford, L. (2003) · International Journal of Project Management · doi:10.1016/s0263-7863(02)00055-8 · Cited by 796
How common and how large are cost overruns in transport infrastructure projects?
Flyvbjerg, B., Skamris holm, M. K., & Buhl, S. L. (2003) · Transport Reviews · doi:10.1080/01441640309904 · Cited by 783
Factors influencing construction time and cost overruns on high-rise projects in Indonesia
Kaming, P. F., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1997) · Construction Management and Economics · doi:10.1080/014461997373132 · Cited by 698
Research works printed but not linked: 13
- Acharya, N.K., Lee, Y.D., Kim, S.Y. and Lee, J.C. (2006), “Analysis of construction delay factor: a Korean perspective”, Industrial Engineering and Management Systems Proceedings of the 7th Asia Pacific Conference, Bangkok, pp. 883‐95.
- Ashworth, A. (2004), Cost Studies of Buildings, 4th ed., Pearson Education Limited, Harlow.
- Ashworth, A. (2008), Pre‐Contract Studies: Development Economics, Tendering and Estimating, 3rd ed., Blackwell Publishing Limited, Oxford.
- Azhar, N., Farooqui, R.U. and Ahmed, S.M. (2008), “Cost overrun factors in construction industry of Pakistan”, Construction in developing countries proceedings of the 1st international conference, Karachi, pp. 499‐508.
- Burke, R. (2003), Project Management Planning and Control Techniques, 4th ed., John Wiley and Sons, Chichester.
- Chimwaso, D.K. (2000), “An evaluation of cost performance of public projects: a case of Botswana”, Construction in Developing Countries Proceedings of the 2nd International Conference, Gabarone, pp. 81‐91.
- Coakes, S.J. and Ong, C. (2011), SPSS Version 18.0 for Windows Analysis without Anguish, John Wiley and Sons, Milton.
- Hackett, M., Robinson, I. and Statham, G. (2007), The Aqua Group Guide to Procurement, Tendering and Contract Administration, Blackwell Publishing Limited, Oxford.
- Jackson, S. (2002), “Project cost overruns and risk management”, Construction Management Proceedings of the 18th Annual Association of Researchers Conference, Newcastle, pp. 165‐73.
- Knight, A. and Ruddock, L. (2008), Advanced Research Methods in the Built Environment, Wiley‐Blackwell, Oxford.
- Nega, F. (2008), “Causes and effects of cost overrun on public building construction projects in Ethiopia”, MSc dissertation, Addis Ababa University, Addis Ababa.
- Pitcher, R. (1994), Project Cost Control in Construction, 2nd ed., Blackwell Scientific Publications, Oxford.
- Russell, R.S. and Taylor, B.W. (2009), Operations Management along the Supply Chain, 6th ed., John Wiley & Sons, Chiehester.
Cited by
Cost overrun in the Malaysian construction industry projects: A deeper insight
Shehu, Z., Endut, I. R., Akintoye, A., & Holt, G. D. (2014) · International Journal of Project Management · doi:10.1016/j.ijproman.2014.04.004 · Cited by 210
Memon, A. H., & Rahman, I. A. (2014) · The Scientific World Journal · doi:10.1155/2014/165158 · Cited by 193
Time Delay and Cost Overrun in Qatari Public Construction Projects
Senouci, A. B., Ismail, A., & Eldin, N. N. (2016) · Procedia Engineering · doi:10.1016/j.proeng.2016.11.632 · Cited by 141
Cost Overrun Causative Factors in Road Infrastructure Projects: A Frequency and Importance Analysis
Herrera, R. F., Sánchez, O., Castañeda, K., & Porras-Díaz, H. (2020) · Applied Sciences · doi:10.3390/app10165506 · Cited by 108
Review of construction journals on causes of project cost overruns
Durdyev, S. (2020) · Engineering Construction & Architectural Management · doi:10.1108/ecam-02-2020-0137 · Cited by 125
Metadata
- Authors
- Park, Y., & Papadopoulou, T. C.
- Affiliations
- Hyundai Engineering (South Korea) (KR)
- Kingston University London (GB)
- Venue
- Built Environment Project and Asset Management
- Publisher
- Emerald
- Published
- 2012-11-16
- Volume
- 2
- Issue
- 2
- Pages
- 195-216
- ISSN
- 2044-124X (ISSN-L)
- OpenAlex
- W1533006508
- Cited by
- 91
- References
- 56
- Citations by year
- 2026: 4 · 2025: 9 · 2024: 3 · 2023: 9 · 2022: 10 · 2021: 11 · 2020: 10 · 2019: 8 · 2018: 4 · 2017: 7 · 2016: 3 · 2015: 4 · 2014: 7 · 2013: 2
- FWCI
- 5.50
- Type
- journal article
- Language
- en
- Open access
- closed
- Licence
- www.emerald.com/insight/site-policies (tdm)
- Locations
- Built Environment Project and Asset Management (publishedVersion)
- Topics
- Social Sciences › Decision Sciences › Management Science and Operations Research › Construction Project Management and Performance
- Social Sciences › Business, Management and Accounting › Strategy and Management › Value Engineering and Management
- Social Sciences › Business, Management and Accounting › Strategy and Management › Public-Private Partnership Projects
- Keywords
- cost overruns, transport infrastructure, construction projects, project size, fixed-price contracts, contract types, cost escalation, Asia
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
How to cite
Cite CoChat for the checks on this page, and the paper for its own findings.
- This page
- CoChat. (2026). Citation check: Causes of cost overruns in transport infrastructure projects in Asia: Their significance and relationship with project size. https://app.cochat.ai/papers/10.1108/20441241211280873
- The paper
- Park, Y., & Papadopoulou, T. C. (2012). Causes of cost overruns in transport infrastructure projects in Asia: Their significance and relationship with project size. Built Environment Project and Asset Management. https://doi.org/10.1108/20441241211280873
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.