Dealing with construction cost overruns using data mining
Open accessThe DOI matches its Crossref record; 6 of the 6 references it cites were found in a registry or an index.
Abstract
One of the main aims of any construction client is to procure a project within the limits of a predefined budget. However, most construction projects routinely overrun their cost estimates. Existing theories on construction cost overrun suggest a number of causes ranging from technical difficulties, optimism bias, managerial incompetence and strategic misrepresentation. However, much of the budgetary decision-making process in the early stages of a project is carried out in an environment of high uncertainty with little available information for accurate estimation. Using non-parametric bootstrapping and ensemble modelling in artificial neural networks, final project cost-forecasting models were developed with 1600 completed projects. This helped to extract information embedded in data on completed construction projects, in an attempt to address the problem of the dearth of information in the early stages of a project. It was found that 92% of the 100 validation predictions were within ±10% of the actual final cost of the project while 77% were within ±5% of actual final cost. This indicates the model’s ability to generalize satisfactorily when validated with new data. The models are being deployed within the operations of the industry partner involved in this research to help increase the reliability and accuracy of initial cost estimates.
Overview
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Integrity signals
Registry
Cites
Statistics
Verification
Claims the paper makes
The claims and statistics of this paper haven’t been checked yet.
Free: it reads the open-access text and checks the first 5 claims that cite a source we can check. Create a free account to check every claim.
Self-check
Percentages, sums and reported differences re-computed from the paper’s own numbers.
The self-check needs the paper’s full text.
Citations
Cites
Prospect Theory: An Analysis of Decision under Risk
Kahneman, D., & Tversky, A. (1979) · Econometrica · doi:10.2307/1914185 · Cited by 48,524
Kruger, J., & Dunning, D. (1999) · Journal of Personality and Social Psychology · doi:10.1037/0022-3514.77.6.1121 · Cited by 7,731
Unrealistic optimism about future life events
Weinstein, N. D. (1980) · Journal of Personality and Social Psychology · doi:10.1037/0022-3514.39.5.806 · Cited by 4,999 · cited 1×
“Further developments of the strategic misrepresentation perspective by Flyvbjerg led to theories based on optimism bias, after Weinstein (1980).”
BackgroundThe KDD process for extracting useful knowledge from volumes of data
Fayyad, U., Piatetsky-Shapiro, G., & Smyth, P. (1996) · Communications of the ACM · doi:10.1145/240455.240464 · Cited by 1,934 · cited 1×
“Fayyad et al. (1996) noted that the real value of storing data lies in the ability to exploit useful trends and patterns in the data to meet business or operational goals as well as for decision support and policymaking.”
BackgroundBootstrap Methods: Another Look at the Jackknife
Efron, B. (1992) · Springer Series in Statistics · doi:10.1007/978-1-4612-4380-9_41 · Cited by 1,374
Flyvbjerg, B. (2008) · European Planning Studies · doi:10.1080/09654310701747936 · Cited by 438 · cited 3×
“While strategic misrepre-sentation is often intentional, according to Flyvbjerg et al ., optimism bias is not.”
BackgroundInfluential
Cited by
Big data analytics in supply chain management: A state-of-the-art literature review
Nguyen, T., ZHOU, L., Spiegler, V., Ieromonachou, P., & Lin, Y. (2018) · Computers & Operations Research · doi:10.1016/j.cor.2017.07.004 · Cited by 565
Data mining in the construction industry: Present status, opportunities, and future trends
Yan, H., Yang, N., Peng, Y., & Ren, Y. (2020) · Automation in Construction · doi:10.1016/j.autcon.2020.103331 · Cited by 161
Love, P. E. D., Ahiaga-Dagbui, D. D., & Irani, Z. (2016) · Transportation Research Part A: Policy and Practice · doi:10.1016/j.tra.2016.08.007 · Cited by 138
“Two predominant schools–of-thought have emerged from the on-going discourse regarding the sources of cost overruns (Ahiaga-Dagbui and Smith, 2014).”
InfluentialSelf-citationGhazal, M. M., & Hammad, A. (2022) · International Journal of Construction Management · doi:10.1080/15623599.2020.1738205 · Cited by 52
Metadata
- Authors
- Ahiaga-Dagbui, D. D., & Smith, S. D.
- Venue
- Construction Management and Economics
- Publisher
- Informa UK Limited
- Published
- 2014-07-24
- Volume
- 32
- Issue
- 7-8
- Pages
- 682-694
- ISSN
- 0144-6193 (ISSN-L)
- 1466-433X
- OpenAlex
- W1992699707
- Cited by
- 90
- References
- 6
- FWCI
- 6.57
- Type
- journal article
- Language
- en
- Open access
- green
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review
Data sources
Bibliographic data: Semantic Scholar, OpenAlex, Crossref.
Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).
Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.