Reasons for delays in public projects in Turkey

Arditi, David, Akan, Guzin Tarim, Gurdamar, San·1985·Construction Management and Economics

Abstract

The effects of construction delays are not confined to the construction industry but influence the state of the overall economy of a country. This is particularly so in Turkey where construction investments account for almost half of all investments and where delays have reached significant magnitudes in the 1970–80 decade. A Iurge number of public agencies that are construction owners and a large number of contractors that undertake construction work for public agencies in Turkey were surveyed to identify and rank in an order of importance the causes for such delays. The results indicate that shortages of some resources; public agencies' and contractors' fincincial dfiiculties; organizational deficiencies and delays in design work, frequent chunge orders and considerable extra work are the most important sources of delay. While some of the causes are dependent on national economic policies, others may be overcome by measures to be taken by public agencies and contractors.

Overview

The claims and statistics of this paper haven’t been checked yet.

Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.

A few free checks a day · papers already verified open instantly · results are public

Integrity signals

Registry

Crossref · 10.1080/01446198500000013

Cites

Statistics

Verification

Claims the paper makes

The claims and statistics of this paper haven’t been checked yet.

Run the check — free, no account needed. It reads the open-access text and checks the sources it cites.

A few free checks a day · papers already verified open instantly · results are public

Self-check

Percentages, sums and reported differences re-computed from the paper’s own numbers.

The self-check needs the paper’s full text.

Citations

Cited by

See all 198

Metadata

Authors
Arditi, D., Akan, G. T., & Gurdamar, S.
Venue
Construction Management and Economics
Published
1985-09
Volume
3
Issue
2
Pages
171-181
ISSN
  • 0144-6193 (ISSN-L)
  • 1466-433X
OpenAlex
W2043020664
Cited by
198
References
0
FWCI
0.64
Type
journal article
Language
en
Open access
closed

About these checks

Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.

Statistics and arithmetic are recomputed, not judged.

Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.

What counts as a claim ›How we measure confidence ›How we check this ›

Are you an author, or do you see a problem with this page? Request a review

How to cite

Cite CoChat for the checks on this page, and the paper for its own findings.

This page
CoChat. (2026). Citation check: Reasons for delays in public projects in Turkey. https://app.cochat.ai/papers/10.1080/01446198500000013
The paper
Arditi, D., Akan, G. T., & Gurdamar, S. (1985). Reasons for delays in public projects in Turkey. Construction Management and Economics. https://doi.org/10.1080/01446198500000013

Data sources

Bibliographic data: Semantic Scholar, OpenAlex, Crossref.

Contains information from the Semantic Scholar Academic Graph Datasets, made available under the ODC Attribution License (ODC-BY 1.0).

Semantic Scholar’s data is described in: Kinney, R., et al. (2023). The Semantic Scholar Open Data Platform. arXiv:2301.10140.