Designing with reused building components: some challenges
Abstract
What are the implications of component reuse strategies on the way buildings are designed and procured? Two building project case studies highlight the organizational and procedural problems for reusing components. Designers need additional information to design effectively with reclaimed components for new projects. They need to understand the risks, economics and implications to the programme. The design process needs to allow for more flexible design and specification. Additional skills are needed to source and evaluate components. Robust procurement contracts are needed to accommodate component dismantling and reuse. The impediments to the reuse of construction components are rarely technical or economic. Instead, they are mostly based on organizational, contractual and social structures. Quelles sont les incidences des stratégies de réutilisation de composants sur la conception et l'approvisionnement des bâtiments? Deux études de cas relatives à des projets de construction mettent en lumière les problèmes d'organisation et de procédure relatifs à la réutilisation de composants. Les architectes ont besoin d'informations complémentaires pour concevoir de manière effective de nouveaux projets en utilisant des composants de réemploi. Ils ont besoin de comprendre les risques, de connaître les caractéristiques économiques et les conséquences pour les programmes. La procédure de conception doit prévoir des spécifications et des concepts plus souples. Des compétences additionnel…
Integrity signals
Registry
Cites
Statistics
Claims the paper makes
Claims other papers make about this one
Each is checked against this paper’s own text: does it say what the citing paper says it does?
Increased cost of landfilling can act as a reuse driver because it increases the disposal cost of CDW.
“Moreover, the increased cost of landfilling can act as a reuse driver because it increases the disposal cost of CDW (Dantata et al., 2005; Gorgolewski, 2008; Chileshe et al., 2016a; Chinda and Ammarapala, 2016).”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
Integrating reuse in the design process of new projects is one method to increase reuse rates by organizations.
“One method to increase the reuse rates by the organizations is through integrating reuse in the design process of new projects (Gorgolewski, 2008; Gorgolewski et al., 2008; Rogers, 2011; Tingley et al., 2017 (among others)).”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
Reusing recovered components, such as structural components, to serve the same purpose has a positive impact on the success of reuse.
“Some articles advise that reusing the recovered components, such as the structural components, to serve the same purpose (for instance, similar loads) has a positive impact on the success of this intervention (Gorgolewski, 2008; Gorgolewski et al., 2008; Pongiglione and Calderini, 2014).”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
Availability of information about the characteristics, details, certificates and drawings of recovered building components can positively contribute to increasing reuse rates.
“According to Gorgolewski (2008), Gorgolewski et al. (2008) and Pongiglione and Calderini (2014), the availability of information about the characteristics, details, certificates and drawings of the recovered building components can positively contribute to increasing the reuse rates as well.”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski (2008)
Environmental policies and green building rating systems such as BREEAM and LEED have a positive impact on reuse rates.
“The environmental policies (Chileshe et al., 2018) and green building rating systems such as Building Research Establishment Environmental Assessment Method (BREEAM) and Leadership in Energy and Environmental Design (LEED) are reported to have a positive impact on reuse rates (Shaurette, 2006; Gorgolewski, 2008).”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
A reclaimed components management coordinator and knowledge of a known list of structural components to reuse early in the design phase can potentially increase the adoption of reuse by firms.
“Also, a reclaimed components management coordinator (Gorgolewski, 2008; Tingley et al., 2017) and the knowledge of a known list of structural components to reuse early on in the design phase are recommended in order to potentially increase the adoption of reuse by the firms (Gorgolewski, 2008; Rose and Stegemann, 2018).”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
Integrating reuse in contractual requirements will increase reuse rates.
“some articles suggest that by integrating reuse in the contractual requirements, reuse rates will increase (Gorgolewski, 2008; Gorgolewski et al., 2008; MacKinnon, 2000).”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
Positive perception and willingness of stakeholders such as clients, designers and contractors to integrate reused components into their projects are determining.
“However, from a social perspective, positive perception and willingness of the stakeholders such as clients (Arif et al., 2012; Dunant et al., 2017, 2018; Gorgolewski, 2008; Gorgolewski et al., 2008; Sansom and Avery, 2014; Shaurette, 2006; ), designers (Dunant et al., 2017, 2018; Gorgolewski, 2008; Gorgolewski et al., 2008; Rameezdeen et al., 2016; Tingley et al., 2017) and contractors (Chileshe”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
Sometimes it is required to purchase identified reused components early in the project to cope with uncertainty about the timely availability of the desired elements.
“Sometimes it is required to purchase the identified reused components early in the project (Gorgolewski, 2008; Gorgolewski et al., 2008) to cope with uncertainty about the timely availability of the desired elements (Chileshe et al., 2015; Gorgolewski et al., 2008).”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
Additional charges which can increase the overall price of recovered components are cost of testing, cost of treatment of salvaged parts, cost of insurance and cost of marketing.
“Other additional charges which can increase the overall price of the recovered components are cost of testing (Dunant et al., 2018; Gorgolewski, 2008; Rameezdeen et al., 2016; Tingley et al., 2017; Yeung et al., 2015), cost of treatment of the salvaged parts (Chini and Acquaye, 2001; Dunant et al., 2018; Huuhka and Hakanen, 2015), cost of insurance (Tingley et al., 2017) and cost of marketing for”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
Another economic barrier to BCR is the higher cost of design with reused components.
“Another economic barrier to the BCR is the higher cost of design with the reused components (Dunant et al., 2017; Gorgolewski, 2008; Gorgolewski et al., 2008).”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
The time required for deconstruction and reuse, and the consequent project scheduling, is one of the main barriers to reuse.
“According to the reviewed articles, the time required for deconstruction and reuse, and the consequent project scheduling, is one of the main barriers to reuse (Dantata et al., 2005; Gorgolewski, 2008; Gorgolewski et al., 2008; MacKinnon, 2000; Shaurette, 2006 (among others)).”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
Purchasing reused components early may raise cash flow problems and increase the overall cost of the project due to additional storage costs, which is another barrier to BCR.
“Consequently, this practise may raise cash flow problems and increase the overall cost of the project due to additional storage costs, which is another barrier to the BCR (Chinda and Ammarapala, 2016; da Rocha and Sattler, 2009; Gorgolewski, 2008; Gorgolewski et al., 2008; Yeung et al., 2015 (among others)).”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
During deconstruction, more time is required to carefully remove and sort recovered building components, which increases the cost of sorting.
“During the deconstruction phase, more time is required to carefully remove and sort the recovered building components (Gorgolewski, 2008), which increases the cost of sorting (Rameezdeen et al., 2016).”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
The design gap results in permanent joints, composite joints, and hard-to-access connections.
“Some outcomes of this design gap are permanent joints (welding, etc.) (Gorgolewski, 2008; Pongiglione and Calderini, 2014; Tingley et al., 2017), composite joints (Tingley et al., 2017) and hard to access connections (Tingley et al., 2017)”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
Design of new buildings with reused components needs to remain flexible to accommodate alternative dimensions due to uncertainty in availability of desired sections.
“the design of the new buildings with reused building components needs to remain flexible. This is because the design should be able to accommodate alternative dimensions of the reused components due to the uncertainty in the availability of the desired sections (Gorgolewski, 2008; Gorgolewski et al., 2008).”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
Unknown remaining capacity happens when information about characteristics, details, certificates and drawings of reused components are not available.
“The latter happens when the information about the characteristics, details, certificates and drawings of the reused components are not available (Gorgolewski, 2008; Gorgolewski et al., 2008; Huuhka and Hakanen, 2015; Rose and Stegemann, 2018; Tingley et al., 2017; Yeung et al., 2015).”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
To secure safety, new components should be over-dimensioned, resulting in overdesigned structures.
“However, to secure the safety of such structures, the new components should be over-dimensioned, which eventually results in overdesigned structures (Brütting et al., 2019; Gorgolewski, 2008; Gorgolewski et al., 2008; Pongiglione and Calderini, 2014).”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
Because deconstruction is not considered at the design stage, building components are prone to more damage during the deconstruction phase.
“Because deconstruction is not considered at the design stage, building components are prone to more damage during the deconstruction phase (Chini and Acquaye, 2001; Gorgolewski, 2008; Pongiglione and Calderini, 2014).”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
If the client is motivated to use reused building components, barriers such as unwillingness of the design team or contractors can be handled effectively.
“On the other hand, according to Gorgolewski (2008), if the client is motivated to use the reused building components, the barriers such as the unwillingness of the design team (Chileshe et al., 2015; Rameezdeen et al., 2016) or the contractors (Gorgolewski, 2008) can be handled effectively.”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
Educating stakeholders on the advantages of deconstruction and reuse could be an effective measure to cope with some social resistance against reuse.
“Therefore, educating the stakeholders on the advantages of deconstruction and reuse, as identified by Chileshe et al. (2015) and Gorgolewski (2008), could be an effective measure to cope with some of the social resistance against reuse.”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
Construction sector's resistance against reuse stems from potential risks perceived by stakeholders during deconstruction or while using recovered building components.
“Another reason for this negative perception, and, at a larger scale, the construction sector’s resistance against reuse (Durão et al., 2014; Gorgolewski, 2008; Rameezdeen et al., 2016; Tingley et al., 2017), stems from the potential risks perceived by the stakeholders during deconstruction or while using the recovered building components (Chileshe et al., 2015; Dunant et al., 2017; Gorgolewski, 20”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
While choosing deconstruction improves supply of reused components, due to perceived economic and programming reasons, it is not yet a preferred option among contractors.
“Gorgolewski (2008) argues that while choosing deconstruction to remove the existing buildings improves the supply of the reused components, due to the perceived economic and programming reasons, it is not yet a preferred option among the contractors (Gorgolewski, 2008).”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
Existing regulations do not support deconstruction and reuse.
“One of the challenges ahead of reuse is that the existing regulations do not support deconstruction and reuse (Chileshe et al., 2015, 2016b; Gorgolewski, 2008, Hglmeier et al., 2013; Huuhka and Hakanen, 2015; Huuhka et al., 2015; Rameezdeen et al., 2016 (among others)).”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
Perceptions of clients, contractors and designers have a higher impact on successful integration of recovered components into a new building.
“Among the stakeholders, the perceptions of clients (Chileshe et al., 2015; da Rocha and Sattler, 2009; Dunant et al., 2017; Rose and Stegemann, 2018), contractors (Gorgolewski, 2008; Shaurette, 2006) and designers (Gorgolewski, 2008) have a higher impact on the successful integration of recovered components into a new building.”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
Stakeholders are unaware of the full benefits of deconstruction and reuse.
“One reason for such reluctance is because the stakeholders are unaware of the full benefits of deconstruction and reuse (Chileshe et al., 2015, 2016b; Gorgolewski, 2008; Huuhka and Hakanen, 2015; Rameezdeen et al., 2016).”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
Lack of skills, experience, and knowledge in deconstruction, salvage and using reused components negatively affects reuse of building components.
“According to the literature, the lack of skills, experience, and knowledge in deconstruction, salvage and using reused components negatively affect the reuse of the building components (Chileshe et al., 2015, 2016b; Gorgolewski, 2008, Shaurette, 2006, Yeung et al., 2015).”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
Lack of space for storage results in transportation and storage of recovered components at a different location and increases overall cost of reused elements.
“This lack of space for storage (Chinda and Ammarapala, 2016; Dunant et al., 2017, 2018; Gorgolewski, 2008; Rose and Stegemann, 2018; Shaurette, 2006) results in the transportation and storage of the recovered components at a different location and would increase the overall cost of the reused elements.”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
Lack of procedures to evaluate and guarantee performance of reused components, and existing codes, standards and procedures not considering BCR, further decrease the reuse rate in construction.
“Therefore, the lack of procedures to evaluate and guarantee the performance of reused components (Shaurette, 2006, Tingley et al., 2017), and the fact that the existing codes, standards and procedures do not consider BCR (Gorgolewski, 2008; Huuhka and Hakanen, 2015; Rameezdeen et al., 2016; Tingley et al., 2017), further decrease the reuse rate in construction.”
From Components reuse in the building sector – A systematic review (2020) · cites this paper as Gorgolewski, 2008
Cited by
Sorted by citations
Material efficiency: A white paper
Allwood, J. M., Ashby, M. F., Gutowski, T. G., & Worrell, E. (2011) · Resources, Conservation and Recycling · doi:10.1016/j.resconrec.2010.11.002 · Cited by 927 · see citing works
The Environmental Impacts of Reuse: A Review
Cooper, D. R., & Gutowski, T. G. (2017) · Journal of Industrial Ecology · doi:10.1111/jiec.12388 · Cited by 337 · see citing works
Akinade, O. O., Oyedele, L. O., Ajayi, S. O., Bilal, M., Alaka, H. A., Owolabi, H. A., Bello, S. A., Jaiyeoba, B. E., & Kadiri, K. O. (2017) · Waste Management · doi:10.1016/j.wasman.2016.08.017 · Cited by 270 · see citing works
Iacovidou, E., & Purnell, P. (2016) · Science of The Total Environment · doi:10.1016/j.scitotenv.2016.03.098 · Cited by 200 · see citing works
Components reuse in the building sector – A systematic review
Rakhshan, K., Morel, J.-C., Alaka, H., & Charef, R. (2020) · Waste Management & Research: The Journal for a Sustainable Circular Economy · doi:10.1177/0734242x20910463 · Cited by 167 · see citing works
“Extending the life of an entire building (or at least some parts of it, for example, its structure) at the end of its useful life due to its historical/social values (Addis, 2006; Gorgolewski, 2008).”
BackgroundMethodResultInfluentialSmart steel: new paradigms for the reuse of steel enabled by digital tracking and modelling
Ness, D., Swift, J., Ranasinghe, D. C., Xing, K., & Soebarto, V. (2015) · Journal of Cleaner Production · doi:10.1016/j.jclepro.2014.08.055 · Cited by 113 · see citing works
Reusing concrete panels from buildings for building: Potential in Finnish 1970s mass housing
Huuhka, S., Kaasalainen, T., Hakanen, J. H., & Lahdensivu, J. (2015) · Resources, Conservation and Recycling · doi:10.1016/j.resconrec.2015.05.017 · Cited by 82 · see citing works
Characterising existing buildings as material banks (E-BAMB) to enable component reuse
Rose, C. M., & Stegemann, J. A. (2019) · Proceedings of the Institution of Civil Engineers - Engineering Sustainability · doi:10.1680/jensu.17.00074 · Cited by 78 · see citing works
- Authors
- Gorgolewski, M.
- Affiliations
- Toronto Metropolitan University (CA)
- Corresponding author
- Gorgolewski, Mark
- ORCID
- Gorgolewski, Mark
- Venue
- Building Research & Information
- Publisher
- Informa UK Limited
- Published
- 2008-03
- Volume
- 36
- Issue
- 2
- Pages
- 175-188
- ISSN
- 0961-3218 (ISSN-L)
- 1466-4321
- OpenAlex
- W2037227085
- Cited by
- 220
- References
- 0
- Citations by year
- 2026: 24 · 2025: 22 · 2024: 23 · 2023: 22 · 2022: 23 · 2021: 23 · 2020: 19 · 2019: 12 · 2018: 14 · 2017: 5 · 2016: 10 · 2015: 7 · 2014: 7 · 2013: 4 · 2012: 1
- FWCI
- 3.74
- Type
- journal article
- Language
- en
- Open access
- closed
- Locations
- Building Research & Information (publishedVersion)
- Funders
- Canadian Institute of Steel Construction
- Government of Canada
- Natural Resources Canada
- Topics
- Physical Sciences › Engineering › Building and Construction › Sustainable Building Design and Assessment
- Social Sciences › Business, Management and Accounting › Strategy and Management › Sustainable Supply Chain Management
- Physical Sciences › Engineering › Building and Construction › BIM and Construction Integration
- Keywords
- component reuse, adaptive reuse, building design process, construction procurement, procurement contracts, design specifications, design skills
About these checks
Registry, retraction, Cites and statistics results are computed, not judged, with one exception: a printed reference that no index lists is read once by a model before it counts as a citation error. Claims are extracted by a model and kept only when their quote appears verbatim in the text; each cited source is then checked, with a model’s help, for whether it says what the claim relies on. Those verdicts can be wrong — read the claim’s quote and the cited source before relying on one.
Statistics and arithmetic are recomputed, not judged.
Confidence bands are shown only for fields calibrated on our annotated test set. None is calibrated yet, so no band is shown.
What counts as a claim ›How we measure confidence ›How we check this ›
Are you an author, or do you see a problem with this page? Request a review